Roman Mosaic & Tile Co. v. Thomas P. Carney, Inc.

729 A.2d 73, 1999 Pa. Super. 73, 1999 Pa. Super. LEXIS 356
CourtSuperior Court of Pennsylvania
DecidedApril 9, 1999
StatusPublished
Cited by18 cases

This text of 729 A.2d 73 (Roman Mosaic & Tile Co. v. Thomas P. Carney, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roman Mosaic & Tile Co. v. Thomas P. Carney, Inc., 729 A.2d 73, 1999 Pa. Super. 73, 1999 Pa. Super. LEXIS 356 (Pa. Ct. App. 1999).

Opinion

OLSZEWSKI, J.:

¶ 1 Before this Court are the direct appeals of Thomas P. Carney, Inc. (“Carney”) and Continental Insurance Company (“Continental”) and the cross-appeal of Roman Mosaic and Tile Company (“Roman”). After a hearing without a jury on the merits of Roman’s complaint, the trial court found in favor of Roman and against Carney and Continental in the amount of $611,763.22, plus interest and costs. We affirm.

¶ 2 On May 11, 1992, Carney was retained as the general contractor by the City of Philadelphia to renovate numerous terminals at the Philadelphia International Airport. Continental executed a surety bond in the amount of $20,198,681.00. Part of the renovation included the laying *75 of terrazzo flooring. The flooring work was subcontracted to Roman per its bid of $11.50 per square foot, totaling $2,685,-800.00, not including final resealing and buffing of the floor (“final cleaning”). A separate bid for $90,000.00 was submitted by Roman for the final cleaning job, but this bid was rejected by Carney.

¶ 3 Roman proceeded to install the terrazzo flooring according to specification of the project. During the course of the project, Carney was often late in advancing payment to Roman, and Roman resorted to two work stoppages in order to force Carney to remit moneys due under the contract. Also during the course of the project, the City of Philadelphia modified the scope of the project, reducing the amount of terrazzo flooring to be installed. Roman had already purchased the tile needed for much of the project and, per the terms of the subcontract agreement, requested a credit of $380,247.00 for the cost of the purchased tile which would now not be needed. Alternatively Roman requested payment of a $22,000.00 restocking fee. Carney failed to accede to either request.

¶ 4 Roman substantially finished the project in good and workmanlike manner by August 1994, excepting a final “punch list” of cosmetic defects that needed to be corrected. By October 1994, Roman had received approximately 67.27% of the money due it. Roman subsequently stopped work on the project and refused to continue unless moneys due were paid. Testimony elicited at trial indicates that the final cleaning would have rectified 96% of the punch list items. In December, 1994, Carney contracted the final cleaning project to Marine Deck and Floor Company (“Marine”) on a time and material basis.

¶ 5 The City, however, was unhappy with the timeliness of Marine’s work, which resulted in Roman being awarded the remaining part of the cleaning project; by May 1995, only one-third of the job was completed. Roman was to be paid for its work on a pro-rated basis commensurate with its earlier bid and the percentage amount of work needed to finish the job, or $71,581.00. Despite final approval of the work by the City of Philadelphia and proper invoicing by Roman, Carney failed to pay the amount due.

¶ 6 Roman filed suit against Carney and Continental in May, 1995. A four-day bench trial was held from December 2 to December 5, 1996. The trial court issued its decision in favor of Roman on September 3, 1997. Carney filed a notice of appeal on September 26, 1997, and Continental followed suit on October 1, 1997. Roman then filed notice of cross-appeal on October 10, 1997. The trial court issued a Rule 1925 opinion on December 31, 1997. On March 12, 1998, the Central Legal Staff of this Court informed counsel for Carney that the appeal was premature and that because post-trial motions had not been filed, the issues presented had been waived. Continental subsequently filed a motion with the trial court for post-trial relief nunc pro tunc on March 12, 1998, and Carney followed with a separate but likewise motion on March 17, 1998. Roman, in turn, filed motions to strike. By order issued May 11, 1998, the trial court denied Roman’s motion to strike and simultaneously denied appellants’ petitions for post-trial relief on the basis set forth in its September 3, 1997, opinion. On June 18, 1998, upon praecipe of Roman, an entry of judgment was issued. This appeal followed.

¶ 7 Initially we address two procedural questions raised by Roman on cross-appeal: whether the trial court erred in granting Continental’s and Carney’s motions for post-trial relief nunc pro tunc and whether the trial court erred by not permitting Roman to amend its complaint.

¶ 8 Our standard of review in reviewing a trial court’s grant of appeal nunc pro tunc, when objections are raised, is one of an abuse of discretion. Millard v. Nagle, 402 Pa.Super. 376, 587 A.2d 10, 12 (1991). The trial court is required to *76 set forth its rationale for considering the merits of untimely post-trial motions. Id. Roman did raise objections to the appellants’ petitions for relief, in the form of a motion to strike. Here, the trial court appended ah extended footnote to its May 11, 1998, order granting the appeal nunc pro tunc but dismissing the post-trial motions. The court noted that all parties filed their original appeals without benefit of post-trial motions simply because counsel failed to properly consult the rules of civil procedure. The court did, however, limit the issues considered on post-trial motions to those raised in the original statements of issues raised on appeal, thus minimizing surprise and prejudice to Roman. The court also noted that the procedural error was not objected to initially by Roman. We do not find that the trial court abused its discretion in this matter.

¶ 9 We also find, though, that Roman failed to preserve the issue of its amended complaint for appellate review. Keeping in step with the other litigants in this ease, Roman also filed its original notice of appeal before seeking post-trial relief from the trial court. Unlike the other litigants, however, Roman did not petition the trial court for permission to file post-trial motions nunc pro tunc. Instead, it sought to quash the other litigants’ motions for relief as untimely filed. It is well established that issues not raised in post-trial motions are waived for appellate review. Dollar Bank v. Swartz, 540 Pa. 369, 657 A.2d 1242, 1245 (1995). Moreover, we have previously held that the failure to file post-trial motions relieves this Court of the need to address the merits of an appellant’s complaint. See, e.g., Matthews v. Joines, 700 A.2d 1322 (Pa.Super.1997). We are therefore compelled to find that, by failing to petition the trial court to file post-trial motions nunc pro tunc, Roman has waived the issue regarding the trial court’s decision to not allow amendment of its complaint.

¶ 10 The questions raised by appellants are properly before this Court. Specifically, appellants complain that the trial court: (1) failed to apply clear terms dictating unit prices to be applied to changes in the work; (2) failed as a matter of law to determine the costs of the credits; (3) improperly admitted and considered extrinsic evidence in interpreting the contract; and (4) erred in finding that Carney breached the contract by failing to make timely payments to Roman.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eastern Steel Const. v. International Fidelity
2022 Pa. Super. 149 (Superior Court of Pennsylvania, 2022)
Guardian Protection v. Integrity Surveillance
Superior Court of Pennsylvania, 2019
Est. of Theodore R. Flint v. Giansante, L.
Superior Court of Pennsylvania, 2019
Janeway Towing v. Credit Connection Auto Sales
Superior Court of Pennsylvania, 2017
Gettysburg Historic Holdings Inc. v. Adams County
3 Pa. D. & C.5th 95 (Adams County Court of Common Pleas, 2007)
Hirsch v. EPL Technologies, Inc.
910 A.2d 84 (Superior Court of Pennsylvania, 2006)
John B. Conomos, Inc. v. Sun Co., Inc.
831 A.2d 696 (Superior Court of Pennsylvania, 2003)
Breza v. Don Farr Moving & Storage Co.
828 A.2d 1131 (Superior Court of Pennsylvania, 2003)
Beemus v. Interstate National Dealer Services, Inc.
823 A.2d 979 (Superior Court of Pennsylvania, 2003)
Bernotas v. Super Fresh Food Markets, Inc.
816 A.2d 225 (Superior Court of Pennsylvania, 2002)
Skurnowicz v. Lucci
798 A.2d 788 (Superior Court of Pennsylvania, 2002)
Morrison v. Correctional Physician Services Inc.
50 Pa. D. & C.4th 558 (Philadelphia County Court of Common Pleas, 2001)
First Union National Bank v. Quality Carriers Inc.
48 Pa. D. & C.4th 1 (Philadelphia County Court of Common Pleas, 2000)
Kaiser v. Old Republic Insurance
741 A.2d 748 (Superior Court of Pennsylvania, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
729 A.2d 73, 1999 Pa. Super. 73, 1999 Pa. Super. LEXIS 356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roman-mosaic-tile-co-v-thomas-p-carney-inc-pasuperct-1999.