Eastern Steel Const. v. International Fidelity

2022 Pa. Super. 149, 282 A.3d 827
CourtSuperior Court of Pennsylvania
DecidedSeptember 1, 2022
Docket998 MDA 2020
StatusPublished
Cited by8 cases

This text of 2022 Pa. Super. 149 (Eastern Steel Const. v. International Fidelity) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Steel Const. v. International Fidelity, 2022 Pa. Super. 149, 282 A.3d 827 (Pa. Ct. App. 2022).

Opinion

J-A12017-21

2022 PA Super 149

EASTERN STEEL CONSTRUCTORS, INC IN THE SUPERIOR COURT OF PENNSYLVANIA Appellant

v.

INTERNATIONAL FIDELITY INSURANCE COMPANY

Appellee No. 998 MDA 2020

Appeal from the Judgment Entered July 23, 2020 In the Court of Common Pleas of Centre County Civil Division at No.: 2011-3233

EASTERN STEEL CONSTRUCTORS, INC IN THE SUPERIOR COURT OF PENNSYLVANIA Appellee

Appellant No. 1034 MDA 2020

Appeal from the Judgment Entered July 23, 2020 In the Court of Common Pleas of Centre County Civil Division at No.: 2011-3233

BEFORE: LAZARUS, J., STABILE, J., and MUSMANNO, J.

OPINION BY STABILE, J.: FILED SEPTEMBER 1, 2022

In this suretyship action, Appellant/Cross-Appellee, Eastern Steel

Constructors, Inc. (“Eastern” or “Claimant”), and Appellee/Cross-Appellant,

International Fidelity Insurance Company (“IFIC”), appeal and cross-appeal,

respectively, from the July 23, 2020 judgment entered in the Court of J-A12017-21

Common Pleas of Centre County (“trial court”). Following the prime contractor

Ionadi Corporation’s (“Ionadi”) failure to pay Eastern for work Eastern

performed under a subcontract, Eastern sought to recover the outstanding

payments from IFIC, Ionadi’s surety. Eastern secured an arbitration award

against Ionadi that was subsequently confirmed and reduced to a judgment.

Thereafter, Eastern unsuccessfully attempted to collect the judgment from

IFIC. Eastern filed suit and the case eventually proceeded to a jury trial, at

the conclusion of which the jury returned a verdict in favor of Eastern and

against IFIC. We now are called upon to decide, inter alia, whether a surety,

who had notice of and an opportunity to participate in arbitration proceedings

against its principal, is bound by an arbitration award rendered against the

principal and, separately, whether a surety is subject to the bad faith statute,

42 Pa.C.S.A. § 8371. After careful review, we have concluded, inter alia, that

IFIC, as surety, was bound by the arbitration award, but not subject to a bad

faith action under Section 8371. Accordingly, we affirm in part, reverse in

part, vacate in part, and remand for further proceedings.

I. BACKGROUND

In 2008, the Pennsylvania State University (“PSU”) entered into a prime

contract (the “Construction Contract”) with Ionadi for the erection of steel on

a project for the construction of the Millennium Science Center Complex at

PSU’s University Park Campus in Centre County, Pennsylvania (the “Project”).

-2- J-A12017-21

On October 29, 2008, IFIC issued a $10,125,000.00 payment bond

(“Payment Bond”) for Ionadi in connection with the Project.1 To do so, IFIC

utilized The American Institute of Architects (“AIA”) standard form AIA

Document A312, which the parties modified to suit their needs. In particular,

the Payment Bond provided:

1. The Contractor2 and the Surety3, jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to the Owner4 to pay for labor, materials and equipment furnished for use in the performance of the Construction Contract5, which is incorporated herein by reference.

2. With respect to the Owner, the obligation shall be null and void if the Contractor:

2.1 Promptly makes payment, directly or indirectly, for all sums due Claimants . . . .

3. With respect to Claimants, this obligation shall be null and void if the Contractor promptly makes payment, directly or indirectly, for all sums due.

4. The Surety shall have no obligation to Claimants under this Bond until:

4.1 Claimants who are employed by or have a direct contract with the Contractor have given notice to the Surety (at the address described in Paragraph 12) and sent ____________________________________________

1 On the same day, IFIC also issued a performance bond for Ionadi relating to

the Project, but that bond is not at issue in this appeal.

2 Bond references to the “Contractor” are to Ionadi.

3 Bond references to the “Surety” are to IFIC.

4 Bond references to the “Owner” are to PSU.

5 The “Construction Contract” under the bond is the prime contract between

Ionadi and PSU.

-3- J-A12017-21

a copy, or notice thereof, to the Owner, stating that a claim is being made under this Bond and, with substantial accuracy, the amount of the claim.

....

6. When the Claimant has satisfied the conditions of Section 4, the Surety shall promptly and at the Surety’s expense take the following actions:

6.1 Send an answer to the Claimant, with a copy to the Owner, within 60 days after receipt of the claim, stating the amounts that are undisputed and the basis for challenging any amounts that are disputed.

6.2 Pay or arrange for payment of any undisputed amounts.

6.3 The Surety’s failure to discharge its obligations under this Section 6 shall not be deemed to constitute a waiver of defenses the Surety or Contractor may have or acquire as to a claim. However, if the Surety fails to discharge its obligations under this Section 6, Surety shall indemnify the Claimant for the reasonable attorney’s fees the Claimant incurs to recover any sums found to be due and owing to the Claimant.

9. The Surety shall not be liable to the Owner, Claimants or others for obligations of the Contractor that are unrelated to the Construction Contract. . . .

11. No suit or action shall be commenced by a Claimant under this Bond other than in a court of competent jurisdiction in the location in which the work or part of the work is located or after the expiration of one year from the date (1) on which the Claimant gave the notice required by Subparagraph 4.1 . . ., or (2) on which the last labor or service was performed by anyone or the last materials or equipment were furnished by anyone under the Construction Contract, whichever of (1) or (2) first occurs.

15. DEFINITIONS

-4- J-A12017-21

15.1 Claimant: An individual or entity having a direct contract with the Contractor or with a subcontractor of the Contractor to furnish labor, materials or equipment for use in the performance of the contract. The intent of this Bond shall be to include without limitation in the terms “labor, materials or equipment” that part of [all utilities] . . . or rental equipment used in the Construction Contract, . . . and all other items for which a mechanic’s lien may be asserted in the jurisdiction where the labor, materials or equipment were furnished.

Payment Bond, 10/29/08, at 5-6 (emphasis added).

On November 11, 2008, Ionadi subcontracted (the “Subcontract”) with

Eastern, a family-owned commercial subcontractor, for installation services

relative to the steel reinforcing material. Specifically, Eastern agreed to,

among other things, “supply labor and trade hand tools for installation of

prefabricated reinforcing steel.” Subcontract, 11/11/08, at ¶ 1. For the

reinforcing steel installation, the Subcontract set the unit price of structure

rebar at $0.33/per pound. Id. The Subcontract also provided in pertinent

part:

18. Payment schedules to [Eastern] will be made on or before the calendar 25th of each month, of an amount equal to 90% of the total value of work placed or performed during the preceding month. There will be a 10% retention holding. Retention release shall occur no later than 60 days after [Eastern’s] reinforcing completion.

19. [Eastern] shall receive a copy of all delivery tickets for all material which [Eastern] will be installing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beton Holdings v. Summit Camp
Superior Court of Pennsylvania, 2026
Eastern Steel, Cross Aplt v. Int Fidelity Ins. Co.
Supreme Court of Pennsylvania, 2026
Borsari, D. v. Latrobe Area Hospital, Inc.
Superior Court of Pennsylvania, 2026
Mudra, M., Sr. v. Schlumberger Technology
Superior Court of Pennsylvania, 2023
Turnpaugh Chiropractic Health v. Erie Ins. Exch.
2023 Pa. Super. 99 (Superior Court of Pennsylvania, 2023)
Taylor, C. v. PA State Corrections Officers Assoc.
2023 Pa. Super. 44 (Superior Court of Pennsylvania, 2023)
Bukowski, J. v. Heim, W.
Superior Court of Pennsylvania, 2022
Eastern Steel Const. v. International Fidelity
2022 Pa. Super. 149 (Superior Court of Pennsylvania, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Pa. Super. 149, 282 A.3d 827, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-steel-const-v-international-fidelity-pasuperct-2022.