Eastern Steel, Cross Aplt v. Int Fidelity Ins. Co.

CourtSupreme Court of Pennsylvania
DecidedFebruary 18, 2026
Docket104 MAP 2023
StatusPublished
AuthorWecht, David N.

This text of Eastern Steel, Cross Aplt v. Int Fidelity Ins. Co. (Eastern Steel, Cross Aplt v. Int Fidelity Ins. Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Steel, Cross Aplt v. Int Fidelity Ins. Co., (Pa. 2026).

Opinions

[J-67A-2024 and J-67B-2024] IN THE SUPREME COURT OF PENNSYLVANIA MIDDLE DISTRICT

TODD, C.J., DONOHUE, DOUGHERTY, WECHT, MUNDY, BROBSON, McCAFFERY, JJ.

EASTERN STEEL CONSTRUCTORS, INC., : No. 103 MAP 2023 : Appellee : Appeal from the order of the : Superior Court at No. 998 MDA : 2020, entered on September 1, v. : 2022, Affirming, Reversing and : Vacating in part the Judgment of the : Centre County Court of Common INTERNATIONAL FIDELITY INSURANCE : Pleas, Civil Division, at No. 2011- COMPANY, : 3233, entered on July 23, 2020 and : Remanding. Appellant : : ARGUED: October 9, 2024

EASTERN STEEL CONSTRUCTORS, INC., : No. 104 MAP 2023 : Cross Appellant : Appeal from the Order of the : Superior Court at No. 998 MDA : 2020, entered on September 1, v. : 2022, Affirming, Reversing and : Vacating in Part the Judgment of the : Centre County Court of Common INTERNATIONAL FIDELITY INSURANCE : Pleas, Civil Division, at No. 2011- COMPANY, : 3233, entered on July 23, 2020 and : Remanding. Appellee : : ARGUED: October 9, 2024

OPINION

JUSTICE WECHT 1 DECIDED: February 18, 2026

1 This opinion was reassigned to this author. This appeal is the culmination of long and protracted litigation between Eastern

Steel Constructors, Inc. (“Eastern”), and International Fidelity Insurance Company

(“Fidelity”) regarding Fidelity’s obligations under a surety payment bond. Eastern asks us

to decide whether Pennsylvania’s insurance bad faith statute 2 applies to surety contracts

issued by insurance companies. We conclude that it does not, based upon that statute’s

plain language. Section 8371 plainly does not apply to Eastern’s suit against Fidelity

because that statute applies only to “insurance policies” and actions of an “insurer.” It

does not apply to surety bonds or actions of a surety.

In its cross-appeal, Fidelity asks us to determine the extent to which Fidelity, as

surety, is bound by an arbitration award against Ionadi Corporation, its principal, and the

extent to which Fidelity is liable for certain attorneys’ fees and prejudgment interest. We

conclude that the arbitration award against Ionadi as principal is conclusive and binding

upon Fidelity as surety. Fidelity agreed to be jointly and severally liable with Ionadi for all

sums due to Eastern, and had notice and opportunity to participate in the arbitration

proceedings. We further conclude that Eastern may recover, as part of all sums due,

attorneys’ fees incurred in connection with pursuing Ionadi in arbitration, as well as

prejudgment interest at the statutory rate of 6% per annum. 3 We affirm the Superior

Court’s decision in all respects.

I. Background

In 2008, the Pennsylvania State University (“PSU”) entered into a construction

contract with Ionadi Corporation to erect steel for the construction of the Millenium

Science Center Complex on campus (“Project”). To secure Ionadi’s solvency, Fidelity

issued a surety bond in the amount of $10.125 million. The payment bond identified

2 42 Pa.C.S. § 8371. 3 41 P.S. § 202.

[J-67A-2024 and J-67B-2024] - 2 Fidelity as “Surety,” Ionadi as “Contractor” and “Contractor as Principal,” and PSU as

“Owner” relative to the Project. 4

Section 1 of the payment bond provided that Ionadi and Fidelity “jointly and

severally” bind themselves as follows:

1. The Contractor and the Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to the Owner to pay for labor, materials and equipment furnished for use in the performance of the Construction Contract, which is incorporated herein by reference. 5 The payment bond also provided for Ionadi’s and Fidelity’s liability to

subcontractors, which the payment bond called “Claimants.”6 Sections 2 and 3 obligated

Fidelity and Ionadi, jointly and severally, to pay “all sums due” to Claimants as follows:

2. With respect to Owner, the obligation shall be null and void if the Contractor:

2.1 Promptly makes payment, directly or indirectly, for all sums due Claimants. . . .

3. With respect to Claimants, this obligation shall be null and void if the Contractor promptly makes payment, directly or indirectly, for all sums due.7 These provisions embodied the intent of Ionadi and Fidelity that Ionadi would enter into

subcontracts with subcontractors to complete the construction project and that, if Ionadi

was unable to pay the subcontractors, Fidelity would be there to ensure that those

subcontractors received “all sums due.” This is the purpose of a surety payment bond:

4 Payment Bond, 10/29/08, at 4; Reproduced Record (“R.R.”) at 34a. 5 Payment Bond, 10/29/08, at 5, ¶ 1; R.R. at 35a. 6 The Payment Bond defined “Claimant” as “[a]n individual or entity having a direct contract with [Ionadi] or with a subcontractor of [Ionadi] to furnish labor, materials or equipment for use in the performance of the [Construction] Contract.” Id. at ¶ 15; R.R. 36a. 7 Id. at ¶¶ 2, 2.1, 3; R.R. at 35a.

[J-67A-2024 and J-67B-2024] - 3 to protect against the risk that the principal becomes insolvent and unable to meet its

financial commitments.

In Section 11, the payment bond provided that “[n]o suit or action shall be

commenced by a Claimant under this Bond other than in a court of competent jurisdiction

in the location in which the work or part of the work is located or after the expiration of

one year from the date” on which the Claimant gave notice to Fidelity as required by the

payment bond, or on which the last of the obligations was performed under the

Construction Contract, whichever comes first. 8

After Fidelity issued the payment bond, Ionadi subcontracted with Eastern for

installation services for steel reinforcing material (“Subcontract”). The Subcontract

provided, in relevant part, that Eastern reserved the right to charge interest on late

payments at 1.5% monthly, that Eastern “shall be considered a direct obligee of [Ionadi’s]

bond assuring” the Subcontract, and that “[a]ny costs incurred, direct and indirect, for

which [Eastern] is subjected in pursuing any money, or consequential damages, legal

fees, and costs of any kind to [Eastern] for nonperformance [ ] will be . . . [Ionadi’s] and

its surities [sic] responsibility.” 9 The Subcontract also provided that disputes would be

resolved through arbitration with the American Arbitration Association (“AAA”). 10 Eastern

entered into a subcontract with Tinney Rebar Services, Inc., for the fabrication and supply

of reinforcing steel material. That subcontract also had a clause requiring arbitration

through AAA.

Eastern worked on the project from February 2009 through September 2010.

During this time, Eastern submitted monthly invoices to Ionadi for payment in accord with

8 Id. ¶ 11; R.R. at 35a. 9 Subcontract, 11/11/08, at 3, ¶ 23; R.R at 39a. 10 Id. at 3, ¶ 25; R.R. at 39a.

[J-67A-2024 and J-67B-2024] - 4 the Subcontract, which Ionadi paid for the first five months. After five months, Ionadi

began to default on payments, explaining to Eastern that Ionadi was having cash flow

problems. In April 2010, while work on the project was ongoing, Eastern notified Fidelity

that it was making a claim as a subcontractor under the Payment Bond for $622,182.90,

the amount it claimed it was owed by Ionadi. Fidelity made partial payment, tendering

the amount it did not dispute. 11 After receiving this partial payment, Eastern claimed that

Ionadi still owned $253,788.08 under the Subcontract, exclusive of interest, attorneys’

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pearlman v. Reliance Insurance
371 U.S. 132 (Supreme Court, 1962)
Commonwealth v. Bortz
909 A.2d 1221 (Supreme Court of Pennsylvania, 2006)
Foster v. Mutual Fire, Marine & Inland Insurance
614 A.2d 1086 (Supreme Court of Pennsylvania, 1992)
Thommen v. Aldine Trust Co.
153 A. 750 (Supreme Court of Pennsylvania, 1930)
Frederick Investment Co. v. American Surety Co.
169 A. 155 (Supreme Court of Pennsylvania, 1933)
Commonwealth v. Fidelity & Deposit Co. of Maryland
50 A.2d 211 (Supreme Court of Pennsylvania, 1946)
Frazier v. Workers' Compensation Appeal Board
52 A.3d 241 (Supreme Court of Pennsylvania, 2012)
Pisano v. Extendicare Homes, Inc.
77 A.3d 651 (Superior Court of Pennsylvania, 2013)
White's Executors v. Commonwealth
39 Pa. 167 (Supreme Court of Pennsylvania, 1861)
Jacob v. Weisser
56 A. 1065 (Supreme Court of Pennsylvania, 1904)
Conneaut Lake Agricultural Ass'n v. Pittsburg Surety Co.
74 A. 620 (Supreme Court of Pennsylvania, 1909)
Schoellhammer's Hatboro Manor, Inc. v. Local Joint Executive Board
231 A.2d 160 (Supreme Court of Pennsylvania, 1967)
Commonwealth ex rel. Fort Pitt Bridge Works v. Continental Casualty Co.
240 A.2d 493 (Supreme Court of Pennsylvania, 1968)
Eastern Steel Const. v. International Fidelity
2022 Pa. Super. 149 (Superior Court of Pennsylvania, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
Eastern Steel, Cross Aplt v. Int Fidelity Ins. Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-steel-cross-aplt-v-int-fidelity-ins-co-pa-2026.