United States of America, for the Use and Benefit of Skip Kirchdorfer, Inc. v. M.J. Kelley Corporation, Richard J. Kelley and Joseph E. Loconti

995 F.2d 656, 1993 U.S. App. LEXIS 13751, 1993 WL 205082
CourtCourt of Appeals for the Sixth Circuit
DecidedJune 15, 1993
Docket92-3714
StatusPublished
Cited by20 cases

This text of 995 F.2d 656 (United States of America, for the Use and Benefit of Skip Kirchdorfer, Inc. v. M.J. Kelley Corporation, Richard J. Kelley and Joseph E. Loconti) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for the Use and Benefit of Skip Kirchdorfer, Inc. v. M.J. Kelley Corporation, Richard J. Kelley and Joseph E. Loconti, 995 F.2d 656, 1993 U.S. App. LEXIS 13751, 1993 WL 205082 (6th Cir. 1993).

Opinion

RYAN, Circuit Judge.

Sureties Richard J. Kelley and Joseph Lo-Conti appeal from the district court’s enforcement of an arbitrator’s award against them in this Miller Act dispute arising from the breach of a government construction contract. Kelley and LoConti raise three issues:

1. Whether the district court erred in finding it had subject matter jurisdiction over this action under the doctrine of equitable tolling.
2. Whether the court erred in enforcing an arbitration judgment against Kelley and LoConti, who were not parties to the arbitration action involving the principal.
3. Whether the court erred in lifting a stay of a judgment against Kelley and LoConti.

Finding no error in the district court’s disposition of these issues, we shall affirm.

I.

This litigation arises from a subcontract for repairs made to the wharf area of the United States Navy installation at Guantanamo Bay, Cuba. The principal contract for improvements was between the federal government and M.J. Kelley Corporation, an Ohio corporation. The subcontract involved was between Kelley Corp., the general contractor, and Skip Kirchdorfer, Inc., a subcontractor.

The contract between Kelley Corp. and Kirchdorfer was a standard form contract developed by the American Institute of Architects. The contract contained, among other provisions, the following arbitration clause: “All claims, disputes and other matters in question arising out of, or relating to, this Contract, or the breach thereof, shall be decided by arbitration.... ”

As required by the Miller Act, see 40 U.S.C. § 270a, et seq., and the Department of the Navy, the Kelley Corp. put up a payment bond of $374,000 to insure availability of funds to pay Kirchdorfer and other contractors, and to guarantee the government that the contract would be performed. Two individuals, Richard Kelley and Joseph LoConti, then signed agreements in their individual capacities to be sureties on the bond. Kireh-dorfer performed the construction work at Guantanamo Bay, as provided in the contract. The last day on which Kirchdorfer supplied labor or materials for the project was October 1, 1989. Thereafter, arguing that it was owed money by the Kelley Corp., Kirchdorfer sought payment of $44,620, which was refused. Kirchdorfer also sought payment from sureties Kelley and LoConti, who likewise refused.

Pursuant to the contract’s arbitration clause, Kirchdorfer demanded arbitration of the payment disagreement. Kirchdorfer also filed suit in the United States District Court for the Western District of Kentucky. The district court dismissed that suit for lack of personal jurisdiction over Kelley Corp., finding that Kelley Corp. had insufficient contacts with the Western District of Kentucky.

*658 Kirchdorfer filed a new action in the Northern District of Ohio, naming the Kelley Corp., Kelley, and LoConti as defendants. This action was stayed pending the outcome of the arbitration.

Kirchdorfer asked the American Arbitration Association (AAA) to arbitrate the dispute in Louisville, Kentucky. Kelley Corp. did not timely object to the Louisville location, and AAA set the date for arbitration, to be held in Louisville. The day before the arbitration was to take place, Kelley Corp. filed a motion in district court for a stay of the arbitration proceedings. The Ohio district court granted a stay. Kirchdorfer later filed a motion to lift the stay. The parties briefed the relevant issues, and the court granted Kirchdorfer’s motion.

Three days before the arbitration proceeding, Kelley Corp. wrote to AAA stating:

[T]he M.J. Kelley Corporation consents to judgment against it in the [arbitration hearing].
The M.J. Kelley Corporation ceased operations shortly after completion of the project at Guantanamo Bay, has no funds and, thus, cannot pay for the transportation of witnesses, attorneys or attorney fees for the arbitration.
While the M.J. Kelley Corporation believes it has a valid defense against the claims of Skip Kirchdorfer, Inc., it is unable to present those defenses in this action.

In the arbitration proceedings, Kelley Corp. filed a response to Kirchdorfer’s claim and brought a counterclaim. However, Kelley Corp. did not attend the arbitration proceeding or present testimony. After the hearing, however, it did present évidenee to the arbitrator, which he considered. Apparently, neither Kelley nor LoConti, the individual sureties, attended the arbitration proceeding or presented evidence, although the Ohio district court later found that they were aware of the proceedings. The arbitrator eventually entered an award in favor of Kirchdorfer for $44,620.00, plus interest, fees, and expenses.

When the arbitration was concluded, Kirchdorfer filed a motion in the Ohio district court to reopen its previously-filed Miller Act lawsuit. It asked the court to enter an order directing Kelley Corp. and sureties Kelley and LoConti to pay Kirchdorfer in accordance with the arbitration award. The individual sureties made two arguments: (1) they contended the Miller Act action had not been commenced within the one-year statute of limitations; and (2) they argued that the arbitration award in favor of Kirchdorfer was not binding upon them since they were not parties to the arbitration. The district court rejected both arguments and ordered Kelley Corp. and the sureties to pay.

First, the court granted Kirchdorfer’s motion to lift the stay of the arbitration award. Second, it concluded that it had subject matter jurisdiction over the dispute, because Kirchdorfer had complied with the one-year deadline for Miller Act actions by filing its action, in good faith, in the United States District Court in Kentucky, thus triggering the doctrine of equitable tolling. Finally, the court determined that sureties Kelley and LoConti were individually liable under the Miller Act for the arbitration award rendered against the corporate defendant, Kelley Corp.

Following entry of judgment, Kelley and LoConti timely appealed to this court. They also sought a stay of the judgment pending appeal, which a panel of this court denied.

Kelley and LoConti now challenge the district court’s finding of jurisdiction, its order lifting the stay of the arbitration award, and its finding that the two were liable as sureties. Kelley Corp., the insolvent corporate defendant, is not a party to this appeal.

II.

A.

Kelley and LoConti argue that the district court erred in finding it had subject matter jurisdiction over this matter. They claim that since more than one year lapsed between October 1, 1989, the last time labor and materials were provided by Kirchdorfer, and September 9, 1991, the date this action was filed, the complaint was filed too late, thus depriving the district court of jurisdiction. Kelley and LoConti acknowledge that *659 Kirchdorfer filed suit in the Western District of Kentucky within the one-year period, but argue that this filing did not toll the statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eastern Steel Const. v. International Fidelity
2022 Pa. Super. 149 (Superior Court of Pennsylvania, 2022)
Dish Network v. Ghosh
Tenth Circuit, 2018
United States ex rel. Adams Steel, LLC v. Elkins Contractors, Inc.
225 F. Supp. 3d 351 (D. South Carolina, 2016)
Henney v. Rumfield (In Re Henney)
451 B.R. 724 (W.D. Michigan, 2011)
US for Use and Ben. of Wfi Georgia v. Gray Ins.
701 F. Supp. 2d 1320 (N.D. Georgia, 2010)
United States v. Gray Insurance
701 F. Supp. 2d 1320 (N.D. Georgia, 2010)
United States Ex Rel. Norshield Corp. v. E.C. Scarborough
620 F. Supp. 2d 1292 (M.D. Alabama, 2009)
United States v. St. Paul Fire & Marine Insurance
239 F.R.D. 404 (W.D. Pennsylvania, 2006)
Enterprise Group Planning, Inc. v. Elaine Falba
73 F.3d 361 (Sixth Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
995 F.2d 656, 1993 U.S. App. LEXIS 13751, 1993 WL 205082, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-skip-kirchdorfer-inc-ca6-1993.