United States ex rel. Walter Toebe Construction Co. v. Guarantee Co. of North America

66 F. Supp. 3d 925, 2014 WL 7211294, 2014 U.S. Dist. LEXIS 176760
CourtDistrict Court, E.D. Michigan
DecidedDecember 11, 2014
DocketCase No. 14-13398
StatusPublished
Cited by3 cases

This text of 66 F. Supp. 3d 925 (United States ex rel. Walter Toebe Construction Co. v. Guarantee Co. of North America) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Walter Toebe Construction Co. v. Guarantee Co. of North America, 66 F. Supp. 3d 925, 2014 WL 7211294, 2014 U.S. Dist. LEXIS 176760 (E.D. Mich. 2014).

Opinion

OPINION AND ORDER GRANTING IN PART AND DENYING IN PART DEFENDANT’S MOTION TO DISMISS

DAVID M. LAWSON, District Judge.

Walter Toebe Construction Company, an unpaid contractor on a government construction project, has filed suit against the Guarantee Company of North America USA (GCNA) to collect what is owing to it for Toebe’s part of the project. Toebe has alleged several theories of recovery, including a claim under the Miller Act. GCNA, which issued payment and performance bonds and also stepped in to complete the project, has filed a motion to dismiss the complaint alleging that (1) it was filed well outside the applicable statutory one-year limitations period under the Miller Act, 40 U.S.C. § 3133(b)(4); (2) the claim for “breach of duty” in count II asserts no legally cognizable cause of action; and (3) the claim for unjust enrichment is precluded as a matter of law due to the existence of an express contract on the same subject matter. The Court heard oral argument on December 9, 2014, and now concludes that all of the plaintiffs claims must fail, save the claim for unjust enrichment, as explained below. Therefore, the Court will grant in part and deny in part the motion to dismiss.

I.

According to the facts alleged in the complaint, some time before May 21, 2010, the United States Army Corps of Engineers entered into a contract with A/B Electrical & General Contracting Services, Inc. as the prime contractor for construction work relating to the Detroit Arsenal Vehicle Access Point Project in Warren, Michigan. A/B engaged Mavcon, Inc. as a subcontractor. As it was required to do by the terms of the prime contract, A/B obtained payment and performance bonds covering the project from defendant GCNA.

On May 21, 2010, Mavcon entered into a contract with Toebe under which Toebe was to perform certain work relating to [928]*928“drilled shaft foundations” involved in the project. Toebe, in turn, engaged Rohrs-cheib Sons Caissons, Inc. to perform excavation work required for the foundations. During the digging work, Rohrscheib uncovered a buried sewer line that had not been shown on the project plans and drawings provided to Toebe and Rohrscheib by the Corps of Engineers, A/B, and Mavcon. Rohrscheib stopped work and notified Mavcon of the problem, but the Corps of Engineers, A/B, and Mavcon jointly directed Rohrscheib to continue digging and complete the work. During a subsequent concrete pour for the foundations, the sewer line was filled with concrete. A/B and Mavcon did not consult with Toebe about the damage to the sewer line, but engaged a third-party contractor to clear and repair the filled sewer.

On January 25, 2011, Toebe submitted a bill to Mavcon for $365,418, which included amounts for the excavation work done by Rohrscheib. On February 4, 2011, Mav-con paid Toebe approximately $57,000 and informed Toebe that the balance of the amount due was being withheld to cover expenses required to clear and repair the sewer line. On July 28, 2011, Mavcon paid Toebe another $70,000 or so. Toebe submitted several subsequent applications for payment between March 10 and July 7, 2011, none of which were paid in full. Toebe alleges that A/B or Mavcon were paid by the Corps of Engineers for all of the work relating to the drilled shaft foundations.

On May 16, 2011, the Corps of Engineers terminated A/B as the prime contractor and directed GCNA to step in and complete the project under the performance bond. GCNA took over and entered into a contract with Mavcon to complete the work.

On March 23, 2011, Toebe submitted a claim for payment of amounts due to GCNA. Toebe submitted claim updates to GCNA on June 8, 2011 and September 6, 2011. On August 11, 2011, Toebe filed a demand for arbitration of the payment claims naming A/B, Mavcon, and GCNA as defendants, and seeking approximately $500,000 in unpaid amounts that it alleged it was due for its work on the project. GCNA filed an answer to the demand for arbitration on August 15, 2011. Toebe later stipulated to dismiss A/B from the arbitration proceedings. Toebe alleges that “GCNA fully participated in the Arbitration proceedings for almost two years, from August 15, 2011 through June 3, 2013, at no time challenging the jurisdiction of the Arbitration [panel].” A five-day arbitration hearing was held starting on June 10, 2013, at which GCNA' “fully participated ... including questioning witnesses.” On June 17, 2013, GCNA filed a motion to dismiss. On June 26, 2013, the last day of the hearing, the arbitrators heard oral argument on GCNA’s motion to dismiss for lack of jurisdiction. Subsequently, on July 8, 2013, the arbitrators granted the motion and dismissed GCNA from the arbitration.

On October 21, 2013, the arbitrators issued an award in Toebe’s favor against Mavcon in the amount of $320,573.97, plus $4,350.00 in arbitration fees. On July 3, 2014, the Macomb County, Michigan circuit court entered a judgment confirming the arbitration award and awarding Toebe $17,426.40 in attorney’s fees and costs. Mavcon failed to pay Toebe any of the awarded amount, and, on August 12, 2014, Toebe demanded payment from GCNA under the payment bond. GCNA refused, asserting that Toebe had failed to file suit within the one year limitations period allowed under the Miller Act.

On September 3, 2014, Toebe filed its complaint against GCNA in this Court asserting claims for (1) breach of contract [929]*929(count I); (2) breach of the duty to investigate and covenant of good faith and fair dealing (count II); (3) equitable estoppel or equitable tolling (count III); and (4) unjust enrichment (count IV). GCNA has moved to dismiss all the claims.

II.

A motion to dismiss under Federal Rule of Civil Procedure 12(b)(6) “allow[s] a defendant to test whether, as a matter of law, the plaintiff is entitled to legal relief if all the facts and allegations in the complaint are taken as true.” Rippy ex rel. Rippy v. Hattaway, 270 F.3d 416, 419 (6th Cir.2001) (citing Mayer v. Mylod, 988 F.2d 635, 638 (6th Cir.1993)). The Court reads the complaint in the light most favorable to the plaintiff, the allegations in-the complaint are accepted as true, and all reasonable inferences are drawn in favor of the plaintiff. Bassett v. Nat'l Collegiate Athletic Ass’n, 528 F.3d 426, 430 (6th Cir.2008). “[A] judge may not grant a Rule 12(b)(6) motion based on a disbelief of a complaint’s factual allegations.” Saglioccolo v. Eagle Ins. Co., 112 F.3d 226, 228-29 (6th Cir.1997) (quoting Columbia Nat’l Res., Inc. v. Tatum, 58 F.3d 1101, 1109 (6th Cir.1995)). “However, while liberal, this standard of review does require more than the bare assertion of legal conclusions.” Tatum, 58 F.3d at 1109; Tackett v. M & G Polymers, USA, L.L.C., 561 F.3d 478, 488 (6th Cir.2009). “To survive a motion to dismiss, [a plaintiff] must plead ‘enough factual matter’ that, when taken as true, ‘state[s] a claim to relief that is plausible on its face.’ Bell Atl. Corp. v. Twombly,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
66 F. Supp. 3d 925, 2014 WL 7211294, 2014 U.S. Dist. LEXIS 176760, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-walter-toebe-construction-co-v-guarantee-co-of-mied-2014.