United States ex rel. Bryant Electric Co. v. Aetna Casualty & Surety Co.

297 F.2d 665
Court of Appeals for the Second Circuit·Decided January 11, 1962·No. No. 42, Docket 27030·Published·Cited by 9 cases

Opinion

CLARK, Circuit Judge.

Bryant Electric Company, Ltd., use-plaintiff, appeals from an order and judgment dismissing its complaint. Defendant Colonial Sharp Co., a joint venture of Colonial Construction Company, Ltd., a Canadian firm, and Sharp Industries, Inc., a Missouri corporation, was awarded a contract by the United States to construct Stop Gap radar facilities at a United States Air Force Base in Labrador. As a condition of this award, Colonial Sharp furnished a bond under the Miller Act, 40 U.S.C. §§ 270a-270d, executed by defendant Aetna Casualty & Surety Company of Hartford, Conn., guaranteeing payment to all persons supplying labor or material in the prosecution of this Labrador project. Plaintiff Bryant subcontracted with Colonial Sharp Co. to provide the electrical work. Plaintiff alleges that after the execution of this contract it provided Colonial Sharp Co. with extra labor and materials for the project at the agreed price of $17,807.82, and that no part of this amount has been paid. To this complaint, defendants raised several defenses on the merits, together with the defense of want of jurisdiction over the subject matter under the Miller Act. On Colonial Sharp’s motion to dismiss for want of jurisdiction the district court found that, since the Miller Act requires all actions instituted under it to be brought “in the United States District Court for any district in which the contract was to be performed and executed and not elsewhere,” 40 U.S.C. § 270b (b), and this contract was to be performed in Labrador, the action could not be maintained in the Southern District of New York. Without deciding whether 40 U.S.C. § 270b (b) relates to venue or jurisdiction, the court granted Colonial Sharp’s motion to dismiss. D.C.S.D.N.Y., 196 F.Supp. 106.

[667] This appeal requires us to harmonize conflicting provisions of the Miller Act. If the lower court’s interpretation is correct, there is no district in the United States wherein this suit may be brought. Since 40 U.S.C. § 270b(b) vests exclusive jurisdiction over suits on Miller Act bonds in the federal courts, there can be no forum whatsoever for such a suit.1 Thus to follow the lower court’s construction would be to render the remedial protections of the statute nugatory for the vast amount of work performed under government contracts abroad.2 Moreover, it would conflict directly with other provisions of the statute. All contractors, regardless of where their work is to be performed, must post a bond. 40 U.S.C. § 270a. Every subcontractor and materialman not reimbursed for work done under a contract is given an unqualified right to sue on the payment bond. And the statute clearly envisions that overseas work is to be bonded, even if performed beyond the jurisdiction of the United States courts: 40 U.S.C. § 270a(b) provides that the contracting officer may waive the requirement of a payment bond for work to be performed in a foreign country if it would be impracticable for the contractor to furnish the bond.3 There was no such waiver here.

Subsection (b) of § 2 of the Miller Act, 40 U.S.C. § 270b(b), has a long history, and its purpose can best be understood by an examination of that history. The Miller Act was passed in 1935 and superseded the Heard Act, Act of August 13, 1894, ch. 280, 28 Stat. 278. Originally the Heard Act provided for one bond which was held to be for the protection of the United States and those furnishing labor or materials for the prosecution of the work. Under this provision subcontractors shared pro rata with the United States. See United States v. American Surety Co. of New York, 1 Cir., 135 F. 78. The Act was amended in 1905 to clarify its provisions and strengthen the position of the government. Act of Feb. 24, 1905, 33 Stat. 811. The amendment provided for a single bond covering both the contrac[668] tor’s obligation to the United States to perform and his liability to persons furnishing labor or materials. For six months after completion or final settlement, the sole right to sue was in the United States; the statute imposed no limitation on where the government might sue. Suppliers of labor and materials could intervene in such a suit and share pro rata in any balance remaining after the United States’ claim was satisfied. If no suit were brought by the United States within six months, any creditor could bring suit “in the name of the United States in the circuit court of the United States in the district in which said contract was to be performed and executed, irrespective of the amount in controversy in such suit, and not elsewhere.” 33 Stat. 812. Only one suit could be brought; all other creditors could intervene and share pro rata in any recovery. Obviously, the single forum was a necessity to this scheme.

The Miller Act worked two basic changes in this arrangement: the contractor was required to post two bonds, one protecting the government against failure to perform, the other protecting the subcontractor. The government, being safeguarded by the performance bond, had no direct interest on the payment bond. Each supplier of labor or material was permitted to institute a separate action to recover his claim; the pro rata provisions were dropped, creating a race among subcontractors until the bond was exhausted.4

Free access — add to your briefcase to read the full text and ask questions with AI

United States ex rel. Bryant Electric Co. v. Aetna Casualty & Surety Co., 297 F.2d 665 (2d Cir. 1962).

297 F.2d 665 (United States ex rel. Bryant Electric Co. v. Aetna Casualty & Surety Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related