United States Ex Rel. Tanner v. Daco Construction, Inc.

38 F. Supp. 2d 1299, 1999 U.S. Dist. LEXIS 2809, 1999 WL 141795
CourtDistrict Court, N.D. Oklahoma
DecidedMarch 9, 1999
Docket4:98-cv-00735
StatusPublished
Cited by12 cases

This text of 38 F. Supp. 2d 1299 (United States Ex Rel. Tanner v. Daco Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Tanner v. Daco Construction, Inc., 38 F. Supp. 2d 1299, 1999 U.S. Dist. LEXIS 2809, 1999 WL 141795 (N.D. Okla. 1999).

Opinion

ORDER

EAGAN, United States Magistrate Judge.

At issue before the Court is the Defendants’ Motion to Stay and Application for Order Directing Parties to Arbitration and Supporting Brief (Docket #2). This action arises out of a claim by plaintiffs, United States of America for the Use and Benefit of Dan E. Tanner, P.E., P.L.S. d/b/a Tanner Consulting, and Dan E. Tanner, P.E., P.L.S. d/b/a Tanner Consulting (collectively referred to herein as “Tanner”), for payment on a subcontract between Tanner and defendant Daco Construction, Inc. (“Daco”), the primary contractor on a public works construction project that the parties refer to as the “Mingo Creek Project.” Defendant Ohio Casualty Insurance Company (“Ohio Casualty”) issued a payment bond guaranteeing the payment of all claims for labor and materials on the Mingo Creek Project. Tanner provided surveying services on the Mingo Creek Project, and it seeks payment for those services in the amount of $31,710.30, together with interest, attorneys’ fees and costs. Tanner’s claims against Daco are equitable claims characterized as quantum meruit and unjust enrichment; its claim against Ohio Casualty arises pursuant to the Miller Act. 1

Defendants initially moved to stay all proceedings and to direct the parties to arbitrate in accordance with the arbitration clauses contained in the prime contract and subcontract. The subcontract contains the language of the Standard Form of Agreement Between Contractor and Subcontractor, 1987 Edition, of the American Institute of Architects (“AIA”). The subcontract provides, in relevant part:

6.1 Any controversy or claim between the Contractor and the Subcontractor arising out of or related to this Subcontract, or the breach thereof, shall be settled by arbitration, which shall be conducted in the same manner and under the same procedure as provided in the Prime Contract with respect to claims between the Owner and the Contractor. ...
6.5 This Article 6 shall not be deemed a limitation of rights or remedies which the Subcontractor may have under Federal law, under state mechanics’ lien laws, or under applicable labor or material payment bonds unless such rights or remedies are expressly waived by the Subcontractor.

(Daco - Tanner Subcontract, attached to Def. Motion to Stay, Docket # 2.)

*1301 The prime contract between Daco and the U.S. Army Corps of Engineers provides:

Any controversy or Claim arising out of or related to the Contract, or the breach thereof, shall be settled by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association, and judgment upon the award rendered by the arbitrator or arbitrators may be entered in any court having jurisdiction thereof....

(AIA Document A201, “General Conditions of the Contract for Construction,” § 4.5.1, attached to Def. Motion to Stay, Docket # 2.) Defendants initially contended that these clauses require the parties to arbitrate pursuant to the Federal Arbitration Act, 9 U.S.C. §§ 1-15, and the Oklahoma Uniform Arbitration Act, 15 O.S. § 801, et seq. (Def. Motion to Stay, Docket #2.) Defendants later clarified their position to request that the Court stay the Miller Act claim against Ohio Casualty and compel arbitration of the underlying dispute between Tanner and Daco'. (Def. Reply Br., Docket # 6, at 2-3, 5-6; Def.Supp.Br., Docket # 10, at 2-4.)

Tanner objects to defendants’ motion. First, Tanner contends that the arbitration clause is unenforceable as to the Miller Act claim because the parties did not agree to arbitrate Miller Act claims and, under Tanner’s interpretation of the law, Miller Act claims cannot be arbitrated in the Tenth Circuit. Further, Tanner argues that the Court should not sever the equitable claims and compel arbitration of those claims because they arise from the same set of facts as the Miller Act claim and, “in fact, represent the same claim.” (PL Resp.Br., Docket # 3, at 5). Finally, Tanner urges the Court not to stay the Miller Act claim in the event the Court determines to sever the equitable claims and compel arbitration of them.

I. The parties did not agree to arbitrate the Miller Act claims

The parties specifically excluded from arbitration any claim under the Miller Act by agreeing to paragraph 6.5 of the subcontract, which excludes, inter alia, rights and remedies under federal law. The Miller Act provides Tanner the right to sue in federal court on the payment bond for amounts owed to it by the contractor under the terms of the subcontract. 40 U.S.C. § 270b. 2 Given the language of the subcontract and the fact that Tanner has not expressly waived its right to proceed in federal court, the Court finds that the arbitration clause is unenforceable as to the Miller Act claim and the parties are not compelled to arbitrate the Miller Act claim.

The question of whether a Miller Act claim may be arbitrated under Tenth Circuit authority is not before the Court because Tanner did not agree to arbitrate that claim and defendants do not seek to compel arbitration of that claim. However, the Court notes that the Miller Act claim would be arbitrable if the parties had not agreed to paragraph 6.5 in the subcontract or otherwise had expressly agreed to arbitrate the claim. The Court does not read United States ex rel. B & D Mechanical Contractors, Inc. v. St. Paul Mercury *1302 Ins. Co., 70 F.3d 1115 (10th Cir.1995), cert. denied, 517 U.S. 1167, 116 S.Ct. 1568, 134 L.Ed.2d 667 (1996), cited by Tanner, to preclude arbitration of statutory claims. In B & D., the Tenth Circuit held that a forum selection clause is an invalid waiver of the Miller Act’s venue provisions. Id. at 1118. It did not hold that an arbitration clause is an invalid waiver of the Miller Act’s jurisdictional provisions. In fact, no arbitration clause was at issue. The B & D court found that the parties could alter the venue provisions of . Miller Act, but they could not change its jurisdictional requirements because the Miller Act grants exclusive jurisdiction to the federal courts. Id. at 1117. In other words, if the parties elect to adjudicate a Miller Act claim, they must do so in federal court, as opposed to state court. The case does not preclude the parties from electing to arbitrate instead of electing to litigate. 3

Similarly, the Court does not read Shankle v. B-G Maintenance Management of Colorado, Inc., 163 F.3d 1230 (10th Cir.1999), as discussed in Tanner’s Supplemental Brief (Docket # 9), to preclude arbitration of Tanner’s Miller Act claim. In Shankle,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
38 F. Supp. 2d 1299, 1999 U.S. Dist. LEXIS 2809, 1999 WL 141795, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-tanner-v-daco-construction-inc-oknd-1999.