Marine Development, Inc. v. Huffman Construction, LLC

CourtDistrict Court, N.D. Oklahoma
DecidedMay 1, 2020
Docket4:19-cv-00681
StatusUnknown

This text of Marine Development, Inc. v. Huffman Construction, LLC (Marine Development, Inc. v. Huffman Construction, LLC) is published on Counsel Stack Legal Research, covering District Court, N.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marine Development, Inc. v. Huffman Construction, LLC, (N.D. Okla. 2020).

Opinion

UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF OKLAHOMA MARINE DEVELOPMENT, INC., ) ) Plaintiff, ) ) v. ) Case No. 19-CV-0681-CVE-FHM ) HUFFMAN CONSTRUCTION, LLC and ) WESTERN SURETY COMPANY, ) ) Defendants. ) OPINION AND ORDER Now before the Court are Defendant Huffman Construction, LLC’s Motion to Dismiss and Brief in Support (Dkt. # 15) and defendant Western Surety Company’s (Western Surety) Motion to Stay Proceedings and to Compel Arbitration (Dkt. ## 21, 22). The parties do not dispute that plaintiff Marine Development, Inc. (Marine) and defendant Huffman Construction, LLC (Huffman) executed a subcontract containing an arbitration agreement. Western Surety argues that Marine’s claims against it are derivative of Marine’s claims against Huffman, and Western Surety claims that it is entitled to enforce the arbitration agreement in the same manner as Huffman. Marine responds that the arbitration agreement includes a carve-out provision that exempts its claims against Western Surety from the scope of the arbitration agreement and it never agreed to arbitrate claims arising under the payment bond issued by Western Surety. Huffman was the general contractor on a construction project to expand a water treatment plant in Sequoyah County, Oklahoma, and Huffman hired Marine as a subcontractor to perform certain work. Dkt. # 2-1, at 2. Western Surety issued a payment bond in the amount of $11,097,000 for the project. Id. Marine claims that it provided labor and materials for the project pursuant to a subcontract with Huffman, and Marine alleges that it sought payment in the amount of $233,504 for its work. Id. Huffman apparently did not pay Marine and, on August 15, 2019, Marine made a claim against Western Surety for payment under the bond. Id. Western Surety acknowledged receipt of Marine’s claim and requested additional information. Id. The petition does not allege whether

Marine provided the additional information requested by Western Surety. By October 2, 2019, Marine had not been paid by Huffman or Western Surety, and Marine made a written demand for payment through an attorney. Id. Marine alleges that Huffman and Western Surety have still not paid Marine for its work and, on November 15, 2019, Marine filed this case in Tulsa County District Court. Marine alleges claims of breach of contract and unjust enrichment against Huffman and claims of breach of contract and bad faith against Western Surety. Huffman and Western Surety filed motions asking the Court to enforce an arbitration

agreement contained in the subcontract between Huffman and Marine. Dkt. ## 15, 21, 22. Article 11 of the subcontract concerns the dispute resolution procedures that would be used in the event of a dispute between the contractor and subcontractor. Dkt. # 21-1, at 24-25. If the parties are unable to resolve their dispute by informal discussion or mediation, the parties agreed to submit their dispute to binding arbitration “using the current Construction Industry Arbitration Rules of the American Arbitration Association or the parties may mutually agree to select another set of arbitration rules.” Id. at 25. Section 11.2 of the subcontract states that “[n]othing in this Article shall limit any right or remedies not expressly waived by the Subcontractor which the Subcontractor

may have under lien laws or payment bonds.” Id. at 24. However, the parties also agreed that “all parties necessary to resolve a claim shall be parties to the same dispute resolution proceeding.” Id. at 24. Marine has filed notice (Dkt. # 27) that it has filed a demand for arbitration against Huffman, 2 and Huffman’s motion (Dkt. # 15) to compel arbitration is moot. Marine argues that it is not required to submit its claims against Western Surety to arbitration based on the “carve-out” provision of the arbitration agreement, and Marine claims that the provision requiring joinder of all parties in a single proceeding applies only in disputes involving the “Contractor” and the “Owner.”

Dkt. # 23, at 3. The Federal Arbitration Act (FAA) represents a strong public policy in favor of arbitration, and states that a “written provision in any . . . contract evidencing a transaction involving commerce to settle by arbitration a controversy thereafter arising out of such contract . . . shall be valid, irrevocable, and enforceable . . . .” 9 U.S.C. § 2; Stolt-Nielsen S.A. v. AnimalFeeds Int’l Corp., 559 U.S. 662 (2010); Vaden v. Discover Bank, 556 U.S. 49, 58 (2009). The FAA “requires a district court to stay judicial proceedings where a written agreement provides for the arbitration of the

dispute that is the subject of the litigation.” Coors Brewing Co. v. Molson Breweries, 51 F.3d 1511, 1514 (10th Cir. 1995). Agreements that require arbitration of statutory claims are generally enforceable. Gilmer v. Interstate/Johnson Lane Corp., 500 U.S. 20, 26 (1991). However, “a party cannot be required to submit to arbitration any dispute which he has not agreed so to submit.” Jacks v. CMH Homes, Inc., 856 F.3d 1301, 1305 (10th Cir. 2017). “Generally, courts ‘should apply ordinary state-law principles that govern the formation of contracts’ to determine whether a party has agreed to arbitrate a dispute.” Hardin v. First Cash Fin. Servs., Inc., 465 F.3d 470, 475-76 (10th Cir. 2006). The consideration of state law is limited to principles of contract law concerning the

enforceability of contracts in general, and state law cannot displace the strong federal policy in favor of arbitration of disputes. Nitro-Lift Technologies, LLC v. Howard, 568 U.S. 17, 20-21 (2012); Arthur Andersen LLP v. Carlisle, 556 U.S. 624, 630 (2009). 3 A motion to compel arbitration calls for a two-step inquiry concerning the arbitrability of the dispute: (1) whether there is a valid arbitration agreement, and (2) whether the particular dispute falls within the scope of that agreement. AT & T Techs., Inc. v. Commc’ns Workers of America, 475 U.S. 643, 649 (1986). Before reaching the issue of arbitrability, the Court will initially consider

whether Western Surety, a non-signatory, can enforce against Marine the arbitration agreement in the subcontract between Huffman and Marine. While not expressly stated in the FAA, federal courts have recognized that there are bases under which a non-signatory may compel arbitration of claims brought by a signatory to an arbitration agreement. Ragone v. Atlantic Video at Manhattan Center, 595 F.3d 115, 127 (2d Cir. 2010); Gibson v. Wal-Mart Stores, 181 F.3d 1163, 1170 n.3 (10th Cir. 1999). In Arthur Andersen, the Supreme Court stated that “‘traditional principles’ of state law allow a contract to be enforced by or against nonparties to the contract through ‘assumption, piercing the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ragone v. Atlantic Video at the Manhattan Center
595 F.3d 115 (Second Circuit, 2010)
At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
Gilmer v. Interstate/Johnson Lane Corp.
500 U.S. 20 (Supreme Court, 1991)
Arthur Andersen LLP v. Carlisle
556 U.S. 624 (Supreme Court, 2009)
Vaden v. Discover Bank
556 U.S. 49 (Supreme Court, 2009)
Gibson v. Wal-Mart Stores Inc.
181 F.3d 1163 (Tenth Circuit, 1999)
Hardin v. First Cash Financial Services, Inc.
465 F.3d 470 (Tenth Circuit, 2006)
Nitro-Lift Technologies, L. L. C. v. Howard
133 S. Ct. 500 (Supreme Court, 2012)
United States Ex Rel. Tanner v. Daco Construction, Inc.
38 F. Supp. 2d 1299 (N.D. Oklahoma, 1999)
Carter v. Schuster
2009 OK 94 (Supreme Court of Oklahoma, 2009)
Jacks v. CMH Homes, Inc.
856 F.3d 1301 (Tenth Circuit, 2017)
Coors Brewing Co. v. Molson Breweries
51 F.3d 1511 (Tenth Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Marine Development, Inc. v. Huffman Construction, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marine-development-inc-v-huffman-construction-llc-oknd-2020.