Blumenthal-Kahn Electric Ltd. Partnership v. American Home Assurance Co.

236 F. Supp. 2d 575, 2002 U.S. Dist. LEXIS 23732, 2002 WL 31777841
CourtDistrict Court, E.D. Virginia
DecidedDecember 5, 2002
DocketCIV.A. 02-743-A
StatusPublished
Cited by10 cases

This text of 236 F. Supp. 2d 575 (Blumenthal-Kahn Electric Ltd. Partnership v. American Home Assurance Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blumenthal-Kahn Electric Ltd. Partnership v. American Home Assurance Co., 236 F. Supp. 2d 575, 2002 U.S. Dist. LEXIS 23732, 2002 WL 31777841 (E.D. Va. 2002).

Opinion

MEMORANDUM OPINION

ELLIS, District Judge.

In this dispute arising out of a construction project at Ronald Reagan National Airport (“Project”), an electrical subcontractor sued on the general contractor’s bond to recover for the work and materials it expended on the Project. The matter came before the Court on defendant, American Home Assurance Co.’s (“AHAC”) motion to stay all further proceedings pending arbitration, pursuant to § 3 of the Federal Arbitration Act, 9 U.S.C. § 1, et seq. For the reasons that follow, AHAC’s motion was granted.

I.

On August 17, 1999, San Jose Construction Group (“San Jose”) entered into a contract (“Prime Contract”) with the Metropolitan Washington Airports Authority (“MWAA”) to complete a pedestrian tunnel as part of the Project. This contract in- *577 eludes an arbitration provision. 1 On or about August 12, 1999, AHAC provided a payment bond to San Jose for the Project. Paragraph 1 of the payment bond provides that the “Construction Contract,” ie. the Prime Contract, is “incorporated herein by reference.”

On November 12, 1999, following award of the Prime Contract, San Jose entered into a subcontract with City General, Inc. (“CGI”) to procure labor and materials to complete the electrical work for the project (“San Jose-CGI subcontract”). Article 11c of this subcontract states:

To the extent not resolved under Article 11a or b."..any dispute between San Jose and Subcontractor, shall, at San Jose’s sole option, be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. If San Jose elects to arbitrate, then the arbitration shall be in Washington, DC. The foregoing agreement to arbitrate shall be specifically enforceable in any court of competent jurisdiction. Upon its request, San Jose shall be entitled to consolidation or joinder of any arbitration involving Subcontractor with related ar-bitrations involving other parties.

Also pertinent here is Article 19a of this subcontract, which states:

All lower-tier subcontractors and purchase orders awarded by Subcontractor are subject to the provisions of this Subcontract, and Subcontractor shall insert in Subcontractor’s subcontracts' all provisions required by the Contract Documents or necessary to enable Subcontractor to comply with the terms hereof. Subcontracting by Subcontractor shall not abrogate any obligation of Subcontractor under this Subcontract.

On December 28, 1999, as required by the San Jose-CGI subcontract, CGI obtained a payment bond and performance bond from Gulf Insurance (“Gulf’). 2 Under the terms of the performance bond, in the event that CGI defaults, ie. fails to perform according to the terms of its subcontract with San Jose, Gulf is required to arrange for the completion of the subcontract. And further, should Gulf fail to *578 perform this obligation under the performance bond, Section 5 of that bond provides that San Jose is “entitled to enforce any remedy available to [itself]” against Gulf. Significantly, Section 1 of the performance bond incorporates, by reference, all of the terms of the San Jose-CGI subcontract, including the arbitration provision.

Thereafter, on March 20, 2000, CGI entered into a subcontract with Blumenthal-Kahn Electric Ltd. Partnership (“BKELP”), whereby BKELP would provide field engineering and administrative management in support of CGI’s electrical work on the Project (“CGI-BKELP subcontract”). 3 Article 6.1 of this subcontract also included a provision requiring that:

[a]ny controversy or claim between the Contractor [CGI] and Subcontractor [BKELP] arising out of or related to this Subcontract, or the breach thereof, shall be settled by arbitration, which shall be conducted in the same manner and under the same procedure as provided in the [San Jose-CGI subcontract] with respect to claims between [San Jose and CGI], except that a decision by the Architect shall not be a condition precedent to arbitration....

A helpful schematic of the parties and their relationships is attached as an Exhibit to this Memorandum Opinion.

During the course of the Project, CGI encountered difficulty completing its scope of work by the Project completion date. 4 As a result, San Jose halted payments to CGI in December 2000, and CGI, in turn, was unable to pay its subcontractors and suppliers, including BKELP. A month later, San Jose threatened to terminate CGI from the Project. In an effort to complete the Project in accordance with the original schedule and to avoid CGI’s termination, San Jose, in January 2001, directed BKELP to provide labor to perform additional electrical work on the Project, work BKELP claims was outside the scope of the CGI-BKELP subcontract. Additionally, on March 15, 2001, on San Jose’s demand, CGI issued an open purchase order to BKELP for additional labor to be directed by San Jose. Ultimately, BKELP provided the necessary labor, materials, and management that substantially completed its original contractual obligations to CGI and the additional work required by San Jose.

On May 23, 2002, BKELP filed this federal complaint against AHAC on the payment bond, alleging that both CGI and San Jose had failed to pay BKELP for work done on the Project and were therefore in breach of their agreements with BKELP. A substantial portion of BKELP’s claim against AHAC is for labor and materials supplied in accordance with the March 15, 2001 purchase order from CGI. The complaint alleged five counts, and sought damages in the amount of $785,199.03. 5

*579 On June 27, 2002, AHAC filed an answer to BKELP’s complaint. On the same day, it also filed a third-party claim against CGI, which CGI answered. On August 13, 2002, AHAC also filed a third-party complaint against Gulf, which Gulf, in turn, answered. On June 27, 2002, AHAC filed two motions to dismiss BKELP’s complaint, which the Court granted with respect to Counts I (Miller Act) and II (Little Miller Act) on September 4, 2002. See United States for the Use of Blumenthal-Kahn Electric, Ltd. Partnership v. American Home Assurance Co., 219 F.Supp.2d 710 (E.D.Va.2002). On September 12, AHAC filed a motion to dismiss for failure to join an indispensable party (San Jose), which the Court denied on September 27, 2002. See Blumenthal-Kahn Electric, Ltd. Partnership v. American Home As surance Co., No. 02-743-A (E.D.Va. September 27, 2002) (Order).

Although the matter has been pending in litigation for only six months, and no trial date set, discovery is largely completed, with the parties having exchanged documents and taken depositions of the various party representatives. Some additional depositions are scheduled for the near future.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SHEARLINE BOATWORKS, LLC v. Trost
820 F. Supp. 2d 695 (E.D. North Carolina, 2011)
Lemus v. CMH Homes, Inc.
798 F. Supp. 2d 853 (S.D. Texas, 2011)
Eldeco, Inc. v. Skanska USA Building, Inc.
412 F. Supp. 2d 556 (D. South Carolina, 2005)
Cason v. Conoco Pipeline Co.
280 F. Supp. 2d 1309 (N.D. Oklahoma, 2003)
Baker v. Conoco Pipeline Co.
280 F. Supp. 2d 1285 (N.D. Oklahoma, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
236 F. Supp. 2d 575, 2002 U.S. Dist. LEXIS 23732, 2002 WL 31777841, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blumenthal-kahn-electric-ltd-partnership-v-american-home-assurance-co-vaed-2002.