Eldeco, Inc. v. Skanska USA Building, Inc.

412 F. Supp. 2d 556, 2005 U.S. Dist. LEXIS 40229, 2005 WL 3728709
CourtDistrict Court, D. South Carolina
DecidedDecember 8, 2005
Docket2:05-2329-PMD
StatusPublished

This text of 412 F. Supp. 2d 556 (Eldeco, Inc. v. Skanska USA Building, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eldeco, Inc. v. Skanska USA Building, Inc., 412 F. Supp. 2d 556, 2005 U.S. Dist. LEXIS 40229, 2005 WL 3728709 (D.S.C. 2005).

Opinion

ORDER

DUFFY, District Judge.

This motion is before the court on Defendants Skanska USA Building, Inc. (“Skanska”), American Home 'Assurance Company (“AHA”), and Federal Insurance Company’s (“Federal”) motion for summary judgment. Defendants claim that, under the doctrine of res judicata, a final judgment in a state court case between Plaintiff and Skanska (“Eldeco I”) bars the instant action. Plaintiff Eldeco, Inc. (“Eldeco”) has timely objected to this motion. The court can only grant summary judgment if “the record taken as a whole could not lead' a rational trier of fact to find for the nonmoving party.” Teamsters Joint Council No. 83 v. Centra, Inc., 947 F.2d 115, 119 (4th Cir.1991); Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986).

BACKGROUND

Skanska served as the general contractor for the construction of the Wando High School in Mount Pleasant, SC (the “Project”). The Charleston County School District was the owner of the Project. Eldeco entered into a subcontract (the “Subcontract”) with Skanska to perform electrical work on the Project. Construction on the Project began in December of 2001 and was completed in the Summer of 2004.

Eldeco filed its first lawsuit against Skanska (“Eldeco I”) on November 12, 2002, naming as defendants Skanska, CCSC, and Mount Pleasant Mechanical, Inc. In April of 2003, Eldeco amended its complaint to allege a claim against Skanska for breach of the Subcontract and unfair and deceptive trade practices. Eldeco alleged that Skanska breached the Subcontract by wrongfully awarding a change work order to Mt. Pleasant Mechanical Inc. rather than to Eldeco, thereby entitling Eldeco to an award of lost profits.

In December of 2003, Eldeco sent a letter to Skanska cataloging the damages they would be requesting in the upcoming trial. The letter notes that “the above amount does not include costs associated with loss of productivity, delays, disruptions, inefficiencies, hostile work environment, etc. that were a direct result, of the inappropriate actions taken by the Defendants of our claim. As the project is nearing completion we are currently in the process of addressing and compiling the above subject costs and they will be incorporated into and become part of our claim.” On February 7, 2005, Eldeco informed Skanska that the amount due to it was $181, 203.47. On February 22, Skanska submitted a check for $89,834.54 in final paynient of its obligation to Eldeco. Eldeco formally rejected this offer of payment as payment in full on March 1st.

A trial in Eldeco I took place in April of 2005. Eldeco presented evidence only of its breach of the Subcontract claim, seeking lost profits for alleged change order work that was not awarded to Eldeco. Despite its threat to sue regarding lost profits in relation to the delay in completion, Eldeco did not amend its complaint to include this new claim. Judge Nicholson found that Skanska had not breached the Subcontract by assigning the change work order to another subcontractor and that Eldeco was not entitled to any damages. Final judgment as to Eldeco I was entered in favor of Skanska on April 29, 2005.

Eldeco filed the present action on July 6, 2005 in the Circuit Court for Charleston *558 County, South Carolina. Eldeco named Skanska, Federal and AHA as defendants. Federal and AHA were Skanska’s sureties on ■ the Project. In this action, Eldeco seeks $295,668.92, representing Eldeco’s contract balance, as well as $181,203.47, as damages arising from Skanska’s failure to complete the Project by the scheduled completion date. 1

Skanska now claims that the present action is barred under the doctrine of res judicata because Eldeco should have brought these claims in Eldeco I.

DISCUSSION

It is well settled under South Carolina law that the doctrine of res judicata requires three essential elements: “(1) the judgment must be final, valid and on the merits; (2) the parties in the subsequent action must be identical to those in the first; and (3) the second action must involve matter properly included in the first action.” Palmetto Homes, Inc. v. Bradley, 357 S.C. 485, 593 S.E.2d 480, 485 (2004); Town of Sullivan’s Island v. Felger, 318 S.C. 340, 457 S.E.2d 626, 628 (1995). “Under the doctrine of res judicata, ‘[a] litigant is barred from raising any issues which were adjudicated in the former suit and any issues which might have been raised in the former suit.’” Plum Creek Dev. Co., Inc. v. City of Conway, 334 S.C. 30, 512 S.E.2d 106, 109 (1999) (quoting Hilton Head Ctr. of South Carolina, Inc. v. Pub. Serv. Comm’n of South Carolina, 294 S.C. 9, 362 S.E.2d 176, 177 (1977)).

In this case, the court agrees with Defendants that the first and second elements are established. The judgment in Eldeco I was a final, valid judgment on the merits. On April 29, 2005, Judge Nicholson entered an “Order of Final Judgment In Favor Of Skanska USA Building, Inc.”, ruling that, as a matter of law, Skanska had not breached the Subcontract when it awarded the change work order to Mt. Pleasant Mechanical Inc. rather than to Eldeco. Also, the parties are identical as between Eldeco I and the instant case. Eldeco and Skanska are the parties in interest in both cases. The addition of Federal and AHA as defendants in the present action has no impact on party identity, as sureties stand in the principal’s shoes. Thus, a defense of res judicata, to the extent available to Skanska, is also available to Federal and AHA. Blumenthal-Kahn Elec. Ltd. v. Amer. Home As surance Co., 236 F.Supp.2d 575, 578 (E.D.Va.2002); South Carolina Highway Dep’t v. Ft. Fetterman, 148 F.Supp. 620, 624 (D.S.C.1956).

The court finds, however, that the subject matter element of res judicata has not been established. While Defendants acknowledge that the issues of this case were not decided in Eldeco I, they argue that, because both cases involve alleged breaches of the same subcontract, this matter should still be barred because it is an “issue which might have been raised in the former suit.” Plum Creek Dev. Co., Inc. v. City of Conway, 334 S.C. 30, 512 S.E.2d 106, 109 (1999).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hilton Head Center of South Carolina, Inc. v. Public Service Commission
362 S.E.2d 176 (Supreme Court of South Carolina, 1987)
Palmetto Homes, Inc. v. Bradley
593 S.E.2d 480 (Court of Appeals of South Carolina, 2004)
Plum Creek Development Co. v. City of Conway
512 S.E.2d 106 (Supreme Court of South Carolina, 1999)
Town of Sullivan's Island v. Felger
457 S.E.2d 626 (Court of Appeals of South Carolina, 1995)
Griggs v. Griggs
51 S.E.2d 622 (Supreme Court of South Carolina, 1949)
Garris v. Governing Board of the South Carolina Reinsurance Facility
511 S.E.2d 48 (Supreme Court of South Carolina, 1998)
Teamsters Joint Council No. 83 v. Centra, Inc.
947 F.2d 115 (Fourth Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
412 F. Supp. 2d 556, 2005 U.S. Dist. LEXIS 40229, 2005 WL 3728709, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eldeco-inc-v-skanska-usa-building-inc-scd-2005.