Palmetto Homes, Inc. v. Bradley

593 S.E.2d 480, 357 S.C. 485, 2003 S.C. App. LEXIS 224
CourtCourt of Appeals of South Carolina
DecidedFebruary 19, 2004
Docket3717
StatusPublished
Cited by5 cases

This text of 593 S.E.2d 480 (Palmetto Homes, Inc. v. Bradley) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Palmetto Homes, Inc. v. Bradley, 593 S.E.2d 480, 357 S.C. 485, 2003 S.C. App. LEXIS 224 (S.C. Ct. App. 2004).

Opinion

HOWARD, J.:

Palmetto Homes, Inc. (“Contractor”) sued Philip Bradley, Chad Summerall, B & S Masonry, Inc., Bradley and Summe-rall Masonry, Inc. (collectively “Subcontractor”), asserting causes of action for breach of contract, breach of contract accompanied by a fraudulent act, breach of warranty, and negligence. In response, Subcontractor pled a previously obtained arbitration award as a bar to Contractor’s causes of action, simultaneously moving to confirm the arbitration award. The circuit court confirmed the arbitration award and entered judgment in favor of Subcontractor. Contractor moved to vacate the award and compel another arbitration, arguing it had not been provided notice of the arbitration proceeding and thus had not appeared to defend it. The circuit court denied the motion to vacate the arbitration award, ruling Contractor had been provided notice. Additionally, the court granted Subcontractor’s motion to dismiss Contractor’s claims, ruling they were barred by res judicata. Contractor appeals. We affirm as modified.

FACTUAL/PROCEDURAL BACKGROUND

Contractor is a residential homebuilder. Contractor entered into a contract with Subcontractor, whereby Subcontractor agreed to provide the masonry work on a residential homebuilding project. The contract between the parties provided for the arbitration of disputes with the American Arbitration Association (“AAA”). Specifically it read:

ARBITRATION: SHOULD A DISPUTE ARISE BETWEEN THE CONTRACTOR AND SUB-CONTRACTOR AS TO AN? MATTER CONCERNING THE WITHIN SUB-CONTRACTOR AGREEMENT AND OR ANY WORK PERFORMED, MATERIALS FURNISHED ON PAYMENT MADE OR REQUESTED FOR SAME, SAID DISPUTE SHALL BE RESOLVED IN ACCORDANCE WITH THE RULES AND REGULATIONS OF THE AMERICAN ARBITRATION Association.

(emphasis as in'original).

Following Subcontractor’s completion of the masonry work, Contractor asserted there were defects in the masonry work *489 and refused to pay Subcontractor. Subcontractor then filed a demand for arbitration with the AAA, asserting a claim for a mechanic’s lien. Contractor never responded to the demand for arbitration.

After numerous notices were mailed and faxed to Contractor by the AAA, the arbitration took place without the participation of Contractor, and the arbitrator issued an award in favor of Subcontractor.

Following the arbitration award, Contractor brought this action asserting causes of action for breach of contract, breach of contract accompanied by a fraudulent act, breach of warranty, and negligence.

Subcontractor filed a Petition to Confirm Arbitration Award, and the circuit court issued an order confirming the arbitration award and entering judgment. Contractor then filed and served a motion to vacate the arbitration award and compel another arbitration of the dispute, arguing Rule 4, South Carolina Rules of Civil Procedure, applied, and Contractor never received proper notice of the arbitration proceedings. Subcontractor then filed and served its motion to dismiss Contractor’s action on the grounds that res judicata barred the suit.

The circuit court denied Contractor’s motion to vacate, ruling numerous attempts were made to serve and provide notice of the arbitration proceedings, but Contractor intentionally avoided service. Additionally, the circuit court granted Subcontractor’s motion to dismiss Contractor’s' causes of action on the grounds of res judicata.

LAW/ANALYSIS

I. Contractor’s Motion to Vacate the Arbitration Award

Contractor argues the circuit court erred by finding Contractor received service of process because the service did not comply with Rule 4, South Carolina Rules of Civil Procedure. 1 We hold Palmetto received sufficient service of process and affirm as modified.

*490 An appellate court may affirm the circuit court’s ruling using any sustaining grounds that are both raised by the respondent’s brief and found within the record. See I‘On, L.L.C. v. Town of Mt. Pleasant, 338 S.C. 406, 420, 526 S.E.2d 716, 723 (2000).

In the present case, the contract signed by the parties specifically stated the rules and regulations of the AAA apply to the arbitration. Thus, we analyze whether service of process was effected pursuant to the AAA rules. See Dowling v. Home Buyers Warranty Corp. II, 311 S.C. 233, 236, 428 S.E.2d 709, 710 (1993) (holding an agreement to arbitrate is a contract, and the parties are free to determine its terms); see also Simmons v. Lucas & Stubbs Assocs., Ltd., 283 S.C. 326, 332-33, 322 S.E.2d 467, 470 (Ct.App.1984) (holding arbitration is a matter of contract, and the range of issues that can be arbitrated is restricted by the terms of the agreement); Marolf Const. Inc. v. Allen’s Paving Co., 154 N.C.App. 723, 572 S.E.2d 861, 863 (2002) (holding parties may alter statutory service of process rules through valid arbitration agreements).

The AAA publication of the Construction Industry Dispute Resolution Procedures (1999) contains Rule R-40, which states:

Each party shall be deemed to have consented that any papers, notices, or process necessary or proper for the initiation or continuation of an arbitration under these rules; for any court action in connection therewith; or for the entry of judgment on any award made under these rules, may be served on a party by mail addressed to the party or its representative at the last known address or by personal service.

Additionally, the rule provides for the following methods of service: “The AAA, the parties, and the arbitrator may also use overnight delivery, electronic facsimile (fax), telex, and telegram.” Rule R-40.

The record indicates Subcontractor utilized regular mail as provided by the AAA rules for the service of the demand for arbitration. Subsequent notices sent by the AAA were sent by certified mail, regular mail, and facsimile. Sometimes the same notice was sent by more than one method.

The record also indicates the facsimiles were transmitted properly. Additionally, there is no evidence the regular mail *491 was returned as undeliverable or for any other reason. The certified mail was returned. However, it was returned because its acceptance was refused or it went unclaimed. 2

Given the facts of this case, we hold service of process was effected pursuant to the AAA rules. 3 Thus, Contractor received proper service of process. 4

II. Subcontractor’s Motion to Dismiss

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. Daniel Mahoney v. The Muhler Company, Inc. (2)
Court of Appeals of South Carolina, 2022
Simpson v. WORLD FINANCE CORP. OF SC
623 S.E.2d 877 (Court of Appeals of South Carolina, 2005)
Aiken v. WORLD FINANCE CORP. OF SC
623 S.E.2d 873 (Court of Appeals of South Carolina, 2005)
Eldeco, Inc. v. Skanska USA Building, Inc.
412 F. Supp. 2d 556 (D. South Carolina, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
593 S.E.2d 480, 357 S.C. 485, 2003 S.C. App. LEXIS 224, Counsel Stack Legal Research, https://law.counselstack.com/opinion/palmetto-homes-inc-v-bradley-scctapp-2004.