Wilder Corp. v. Wilke

497 S.E.2d 731, 330 S.C. 71, 1998 S.C. LEXIS 46
CourtSupreme Court of South Carolina
DecidedMarch 9, 1998
Docket24770
StatusPublished
Cited by637 cases

This text of 497 S.E.2d 731 (Wilder Corp. v. Wilke) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilder Corp. v. Wilke, 497 S.E.2d 731, 330 S.C. 71, 1998 S.C. LEXIS 46 (S.C. 1998).

Opinion

TOAL, Justice:

This case involves the foreclosure of a bond for title. Respondent, Wilder Corporation (“Seller”), brought this foreclosure action against petitioners, Klaus and Rita Wilke (“Buyer”), as a result of Buyer’s indebtedness arising out of the sale of property. The master-in-equity found in favor of Buyer. The Court of Appeals affirmed in part and reversed in part. Buyer appeals the Court of Appeals’ decision. We affirm.

Factual/Procedural Background

In 1979, Seller agreed to sell its mobile home park to Buyer in exchange for Buyer’s motel and the additional sum of $635,000. On January 25, 1980, the parties signed a bond for title memorializing the exchange and the $635,000 debt. The bond for title provided that Buyer would pay monthly payments of $5,658.80 to commence March 1, 1980, and to continue until February 1, 1995, when a balloon payment of the remaining balance would be due. However, the contract' reduced Buyer’s first twenty payments by $500, from $5,658.80 a month to $5,158.80 a month. Additionally, the bond for title allowed Buyer to defer a maximum of three months successive payments in the event occupancy at the mobile home park fell below 152 spaces. It also permitted the parties to set-off or add any claims or judgments arising under the terms of the agreement.

After Buyer took possession of the mobile home park on January 28, 1980, the parties executed a modification agreement which provided that Seller would pay Buyer a one-time payment of $6,000 and that the bond for title would be reduced by $500 per payment for the first twenty payments. 1 *74 Buyer began payment on the bond for title on March 1, 1980. However, in 1991, Buyer deferred payments for the months of September, October, and November due to low occupancy in the mobile home park.

Sometime during the repayment period, Buyer filed suit against Seller in federal district court concerning Seller’s failure to connect the mobile home park to a sewage treatment facility, as required by the bond for title. On July 12, 1994, a federal district court issued a judgment against Seller in the amount of $146,584.72. 2 The court further ordered post-judgment interest in the amount of 5.31% per annum.

After Buyer made the final monthly payment in January 1995, Seller sent Buyer a demand letter requesting $512,-557.61 for the balloon payment due February 1, 1995. Buyer tendered the sum of $280,990.33 to Seller. Seller refused the tender and brought this foreclosure action against Buyer. Subsequent to the filing of this action, Buyer paid $281,000 to Seller’s attorneys pursuant to a motion for appointment of receiver.

A hearing was conducted before a master-in-equity on July 6, 1995. Both Buyer and Seller provided amortization schedules reflecting their views of Buyer’s payment obligation. The master adopted Buyer’s amortization schedule and made four conclusions of law: (1) the modification agreement modified the bond for title insofar as it reduced the principal amount by $10,000; (2) Buyer properly credited the federal court judgment in the amount of $146,584.72 on July 12, 1994. Moreover, no attempt to levy or otherwise execute the judgment was required in order to offset debt under the bond for title, and there was no requirement that Buyer wait to offset such judgment until such time as all appeals had been exhausted; (3) Buyer made or was excused from making all scheduled payments under the bond for title, except for the final balloon payment; and (4) the court agreed with the assumptions Buyer used in constructing the amortization schedule. Accordingly, the master ordered Buyer to pay a residual amount of $811.72, plus interest accruing at 9.75%.

*75 The Court of Appeals affirmed the master’s order except on four points. See Wilder Corp. v. Wilke, 324 S.C. 570, 479 S.E.2d 510 (1997). First, the Court of Appeals held that interest began to accrue on the loan from the date of signing, January 25, 1980, rather than the date of the first payment, March 1, 1980. Second, since the interest accrual date was January 25, 1980, the court held that the master erred in applying Buyer’s first payment entirely toward principal. Third, the court found that the master incorrectly gave Buyer credit for 180 payments when the evidence supported only 179 payments. Finally, the Court of Appeals noted that Buyer’s amortization schedule gave credit for the federal court judgment in the amount of $147,289.53; the federal court judgment was $146,584.72, with post-judgment interest accruing at the rate of 5.31% per annum. The court held that the master should have only deducted the actual amount of the judgment, $146,584.72.

This Court granted Buyer’s petition for a writ of certiorari to consider the following questions:

1. Did the Court of Appeals err in holding that Seller preserved or did not waive any objections to the calculations in Buyer’s amortization schedule by stipulating to the accuracy of those calculations?

2. Did the Court of Appeals err in holding that interest began to accrue prior to the first payment?

3. Did the Court of Appeals err in holding that a payment had not been made or credited?

4. Did the Court of Appeals err in considering whether the trial court erred by adopting the figures in Buyer’s amortization schedule as to the amount of the federal court judgment?

Law/Analysis

A. Waiver/Preservation

Buyer argues that the following issues were not properly preserved for review by the Court of Appeals: (1) the date when interest started to accrue; (2) application of the first payment to principal; (3) the number of payments made by Buyer; and (4) accrual of interest on deferred payments. In a related argument, Buyer contends that the Court of Appeals *76 erred in holding that Seller, by its stipulation, did not waive any objections to the calculations in Buyer’s amortization schedule. It should be noted at the outset that Buyer has preservation problems of its own in that Buyer did not raise all of these issues to the Court of Appeals in its petition for rehearing. That said, we disagree with Buyer’s contention that Seller waived or failed to preserve its position on these issues.

At trial, Seller’s attorney made the following objection/stipulation when Buyer’s amortization schedule was introduced into evidence:

We have an objection to the theories considered by [the accountant] in doing the math, but we have no objection to the way he did the math. We presume that if your honor rules and sustains [Buyer’s] point on the theories, that the math will be correct.... [Buyer’s amortization schedule] is a mathematical run of payments with certain presumptions made on theories propounded by [the accountant]. [The accountant] has run those numbers. And if [his] points are sustained by you, then [his] run of the numbers is accurate.

It is axiomatic that an issue cannot be raised for the first time on appeal, but must have been raised to and ruled upon by the trial judge to be preserved for appellate review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Eugene Turner, Jr.
Court of Appeals of South Carolina, 2025
Martha Coleman v. Jeffrey Coleman
Court of Appeals of South Carolina, 2025
Paul David Hess v. Morphis Pediatric Group
Court of Appeals of South Carolina, 2025
Michel D. Haynes v. Saverne Haynes
Court of Appeals of South Carolina, 2025
Rose Bernard v. Lucas Green
Court of Appeals of South Carolina, 2025
Equinox, LLC v. Brandon Epps
Court of Appeals of South Carolina, 2025
State v. Shawn D. Custer
Court of Appeals of South Carolina, 2024
Renewable Water Resources v. Insurance Reserve Fund
Court of Appeals of South Carolina, 2024
George Moses v. State
Court of Appeals of South Carolina, 2024
Kevin Cox v. SCELC
Court of Appeals of South Carolina, 2023
Jamaine Holman v. SCELC
Court of Appeals of South Carolina, 2023
Jeffrey Fossett v. Melissa Fossett
Court of Appeals of South Carolina, 2023
Gleaton v. Orangeburg County
Court of Appeals of South Carolina, 2023
In the Matter of Francis A. Oxner
Supreme Court of South Carolina, 2023
State v. Sidney Moorer (2)
Court of Appeals of South Carolina, 2023
Glenn Odom v. McBee Municipal Election Commission
Supreme Court of South Carolina, 2023
Covil Corporation v. Pennsylvania National Mutual Casualty
Court of Appeals of South Carolina, 2022
State v. Jones
Supreme Court of South Carolina, 2021
Irvin v. City of Folly Beach
Court of Appeals of South Carolina, 2021

Cite This Page — Counsel Stack

Bluebook (online)
497 S.E.2d 731, 330 S.C. 71, 1998 S.C. LEXIS 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilder-corp-v-wilke-sc-1998.