United States Ex Rel. Blumenthal-Kahn Electric Ltd. Partnership v. American Home Assurance Co.

219 F. Supp. 2d 710, 2002 U.S. Dist. LEXIS 16683, 2002 WL 31005246
CourtDistrict Court, E.D. Virginia
DecidedSeptember 4, 2002
DocketCiv.A. 02-743-A
StatusPublished
Cited by2 cases

This text of 219 F. Supp. 2d 710 (United States Ex Rel. Blumenthal-Kahn Electric Ltd. Partnership v. American Home Assurance Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Blumenthal-Kahn Electric Ltd. Partnership v. American Home Assurance Co., 219 F. Supp. 2d 710, 2002 U.S. Dist. LEXIS 16683, 2002 WL 31005246 (E.D. Va. 2002).

Opinion

MEMORANDUM OPINION

ELLIS, District Judge.

In this dispute arising out of a construction project (“Project”) at Washington Reagan National Airport (“Airport”), an electrical subcontractor sues on the general contractor’s bond under the Miller Act, 1 or, alternatively, under its Virginia counterpart, 2 to recover for the work and materials it expended on the Project. At issue on a threshold dismissal motion is whether either statute applies to the Project, given that the Airport is operated and managed by the Metropolitan Washington Airports Authority (“MWAA”), which is neither a federal nor a state agency.

For the reasons that follow, it is clear that neither statute applies to construction projects at the Airport, and hence the motion to dismiss must be granted.

I. 3

Plaintiff Blumenthal-Kahn Electric Ltd. Partnership (“BKELP”), a Maryland limit *712 ed partnership with its principal place of business in Baltimore County, Maryland, is an electrical subcontractor that does business in Maryland, the District of Columbia, and Virginia. Defendant American Home Assurance Company (“AHAC”) is a New York corporation with its principal place of business in New York City. AHAC is in the business of writing insurance and issuing construction bonds throughout the United States, including Virginia.

Although not a party to this action, the MWAA is nonetheless central to the resolution of the issue presented, given its role as the Airport manager. The MWAA is an independent entity created in 1986 by acts of the Virginia General Assembly and the District of Columbia City Council. See Va.Code § 5.1-153 and D.C.Code Ann. § 7-1252. Since its inception, this hybrid regional agency has operated and managed the Airport under the terms of a 50 year lease agreement with the Secretary of Transportation. See 49 U.S.C.A. §§ 49102(a) & 49104. 4

This controversy grows out of an MWAA contract to construct a pedestrian tunnel at the Airport designed to connect an existing parking garage with historic Terminal A. The general contractor for the Project was San Jose Construction Group, Inc. (“San Jose”), a Maryland corporation with its principal place of business in Washington, D.C. In this connection, San Jose entered into a general contract for the Project with MWAA on August 12, 1999. Pursuant to this contract and the MWAA’s Contracting Manual, San Jose secured a Payment Bond (“bond”) from AHAC for the protection of Project subcontractors and materialmen. On November 12, 1999, San Jose entered into a subcontract with City General, Inc. (“CGI”), a Maryland corporation with its principal place of business in Washington, D.C., to provide labor and materials to complete the electrical work for the Project. Thereafter, on March 20, 2000, CGI entered into a subcontract with BKELP to provide field engineering and administrative management for the Project’s electrical scope of work.

During the course of the Project, it became apparent that MWAA’s engineering documents were incomplete and inaccurate, and could not be relied on to complete the Project. In response to CGI’s requests for clarification of the documents, MWAA made substantial changes to the original plans, but required San Jose and its contractors to adhere to the original Project completion date. While CGI had sufficient resources to perform the original contract in a timely manner, it was unable to accommodate MWAA’s changes to the plans, and still complete its scope of work in accordance with the original schedule. As a result, San Jose halted payments to CGI in December 2000, and CGI, in turn, was unable to pay its subcontractors and suppliers, including BKELP. A month later, San Jose threatened to terminate CGI from the Project.

In an effort to complete the Project in accordance with the original schedule and to avoid CGI’s termination, San Jose, in January 2001, required BKELP to provide labor to perform electrical work on the Project, outside the scope of CGI’s contract. Additionally, on March 15, 2001, on San Jose’s demand, CGI issued an open purchase order to BKELP for additional labor to be directed by San Jose. Ultimately, BKELP provided the necessary labor, materials, and management that substantially completed its original contractual obligations to CGI and the additional work required by San Jose.

*713 Also in January 2001, San.Jose agreed to make joint check payments to CGI’s subcontractors and suppliers to aid CGI in the completion of its work. Yet, San Jose did not follow through on this .agreement, and made no further payments to CGI. San Jose’s failure to make these payments caused CGI’s inability to maintain sufficiently skilled workers to meet San Jose’s schedule, as well as to secure the necessary materials.

BKELP claims that in completing both its contract with CGI and the work directed by San Jose, it incurred expenses totaling $813,221.53, of which only $28,022.50 has been paid, leaving $785,199.03 still due and owing to BKELP. After requesting payment from CGI without success, BKELP put San Jose and AHAC on notice of a claim against the AHAC bond. AHAC then requested submission of a proof of claim. BKELP responded to this request by submitting a proof of claim with supporting documentation. Work on the Project continued in November and December 2001. The last date BKELP supplied labor to the Project for which a claim has been made on the AHAC bond was December 7, 2001. The last date BKELP supplied materials to the Project for which a claim has been made on the AHAC bond was December 20, 2001.

BKELP’s five-count complaint in this case seeks recovery from AHAC under the Project payment bond in the amount of $785,199.03. AHAC’s motion to dismiss attacks only the first two counts. 5 Count I seeks recovery against the bond under the federal Miller Act for work done and materials supplied to the Project. Count II seeks the same relief under Virginia’s counterpart to the federal Miller Act, commonly referred to as the “Little Miller Act.”

il.

A.

AHAC argues that Count I, which is based on the Miller Act, should be dismissed as that Act has no applicability to the MWAA construction projects. Analysis of the Act’s applicability properly begins with the purpose and terms of the statute itself.

When subcontractors and materialmen working on private buildings and projects are’ not paid for work done or materials supplied, they may file mechanic’s liens under state láw to ensure collection of amounts due and owing. See Va.Code § 43-3 et seq. This remedy is not available to subcontractors and materialmen working on federal buildings or projects; mechanic’s liens on such buildings and projects are prohibited. See, e.g., United States for Use of Gen. Elec. Supply v. USF & G, 11 F.3d 577

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
219 F. Supp. 2d 710, 2002 U.S. Dist. LEXIS 16683, 2002 WL 31005246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-blumenthal-kahn-electric-ltd-partnership-v-american-vaed-2002.