UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA
UNITED STATES OF AMERICA for the use and benefit of MILESTONE TARANT, LLC,
and
HIGHLAND ORNAMENTAL IRON Civil Action 08-02186 (RCL) WORKS, INC.,
Plaintiffs,
v.
FEDERAL INSURANCE COMPANY,
Defendant.
MILESTONE TARANT, LLC,
HIGHLAND ORNAMENTAL IRON WORKS, INC., Civil Action 09-01941 (RCL) Plaintiffs,
MANHATTAN CONSTRUCTION COMPANY
MEMORANDUM OPINION
This matter is before the Court on several separate motions in two related actions which
the Court will consider together for the sake of expediency. In Milestone Tarant, LLC v. Federal
Insurance Company, Civ. No. 08-2186 (or “Miller Act case”), Milestone Tarrant, LLC/Highland Ornamental Iron Works, Inc., a Joint Venture (“Joint Venture”) filed suit against surety bond
issuer Federal Insurance Company (“FIC”) under the Miller Act, 40 U.S.C. § 3133 et seq. In
that action, Joint Venture seeks $7,791,475 that is allegedly owed to it by the Manhattan
Construction Corporation (“Manhattan”) for work Joint Venture engaged in to enhance the
Capitol Visitor Center in Washington, D.C. Manhattan later filed for arbitration with the
American Arbitration Association (“AAA”) and served its demand on Joint Venture. In
Milestone Tarant, LLC v. Manhattan Construction Co., Civ. No. 09-1941, Joint Venture filed a
motion for a preliminary injunction against Manhattan to halt the parties’ arbitration [#2]. In
response, Manhattan filed a motion to compel arbitration [#7] and a motion to dismiss Joint
Venture’s complaint pursuant to Federal Rules of Civil Procedure 12(b)(6) [#11]. Subsequent to
Manhattan’s demand for arbitration, FIC moved for a stay in the Miller Act case pending the
resolution of arbitration between Manhattan and Joint Venture [#8]. Upon consideration of the
motions, the oppositions thereto, and the records of these cases, the Court concludes that
Manhattan’s motions to dismiss and compel arbitration and FIC’s motion to stay must be granted
and Joint Venture’s motion for a preliminary injunction must be denied as moot.
I. FACTUAL BACKGROUND
In 2003, Manhattan awarded a subcontract to Joint Venture for the fabrication and
installation of bronze railings, windows, and doors at a construction project known as the
“Capitol Visitor’s Center.” 2008 Compl. ¶ 5, 7, Ex. 2 at 1-3 (Subcontract).1 Earlier that year,
1 Joint Venture filed two different complaints. For the sake of clarity, the Court will refer to the complaint filed against FIC on December 16, 2008, as the 2008 complaint (“2008 Compl.”) and the complaint filed against Manhattan on October 2009, as the 2009 complaint (“2009 Compl.”).
2 FIC had issued a payment bond naming Manhattan as the principal and the United States as the
obligee. 2008 Compl. ¶ 6, Ex. 1 at 1 (Bond). Under the payment bond and pursuant to the
Miller Act, FIC agreed to compensate any subcontractor for labor and materials furnished for the
subcontract in the event Manhattan was unable to pay. Id.
The payment due to Joint Venture under the original contract was $8.3 million, and the
work was to be completed by December of 2005. 2008 Compl. ¶ 7-8, Ex. 2 at 1, 7 (Subcontract).
For reasons that are disputed and not relevant to resolving the motions currently before the
Court, the project was not completed until late in 2008. 2008 Compl. ¶ 8. In total, Joint Venture
alleges that it spent over $16 million in completing the project as a result of the delay, id. ¶ 13,
but has only been paid $11 million by Manhattan, id. ¶ 14.
In December 2008, Joint Venture initiated a lawsuit against FIC pursuant to its rights
under the Miller Act. In Milestone Tarant, LLC v. Federal Insurance Company, Joint Venture
seeks to recover from FIC the reasonable value of its services performed but not yet paid by
Manhattan, 2008 Compl. ¶ 19, and has asked for a jury trial. Neither party has sought to join
Manhattan, the general contractor, to the case. Both parties have engaged in limited discovery
since the inception of the suit roughly 11 months ago.
On September 30, 2009, Manhattan, pursuant to what it contends were its rights under
the subcontract with Joint Venture, filed for arbitration with the AAA and served its demand on
Joint Venture. In its demand for arbitration, Manhattan asserts that Joint Venture’s delays and
defective performance constituted a breach of the subcontract, and that they are owed “no less
than $3 million” by Joint Venture. The “Settlement of Disputes” section of the subcontract
between Manhattan and Joint Venture contains the following provision:
3 All other disputes between the parties shall be resolved by litigation, in a court of competent jurisdiction, except that Manhattan may, at its sole option, require that any dispute be submitted to arbitration pursuant to the Construction Industry Rules of the American Arbitration Association except that all arbitrators shall be attorneys with at least ten (10) years experience in construction law. The election by Manhattan shall be made no later than thirty (30) days following receipt of service of process of any such litigation from Subcontractor or, if the claim is asserted by Manhattan, shall be made upon the filing of a demand for arbitration by Manhattan. Notwithstanding the above, Manhattan shall not be deemed to have waived any right it may have to arbitrate its dispute with Subcontractor by the filing of litigation against Subcontractor and its surety.
Def.’s Mot. to Stay at 4, Ex. A at 5, § 3.5 (Subcontract).
Subsequent to Manhattan’s demand for arbitration, FIC moved for a stay in Milestone
Tarant, LLC v. Federal Insurance Company pending the resolution of arbitration between
Manhattan and Joint Venture. Joint Venture then filed suit against Manhattan on October 14,
2009, seeking to stay the arbitration with Manhattan. 2009 Compl. at 9. On the same day, Joint
Venture filed a motion for a preliminary injunction against Manhattan to halt the parties’
arbitration. Manhattan thereafter filed a motion to compel arbitration on October 22, 2009 and a
motion to dismiss the complaint on October 28, 2009. Joint Venture seeks to resolve the
contract dispute through its Miller Act suit against FIC. Manhattan and FIC both seek to resolve
the dispute through arbitration between Manhattan and Joint Venture.
II. LEGAL STANDARD
When considering “a motion to stay proceedings and/or compel arbitration, the
appropriate standard of review for the district court is the same standard used in resolving
summary judgment motions” pursuant to Federal Rule of Civil Procedure 56(c). Brown v.
Dorsey & Whitney, LLP, 267 F. Supp. 2d 61, 67 (D.D.C. 2003) (internal quotation marks
omitted). Therefore, it is appropriate to grant such motions when the pleadings and the evidence
4 demonstrate that “there is no genuine issue as to any material fact and that the moving party is
entitled to a judgment as a matter of law.” Fed. R. Civ. P. 56(c).
The party seeking to compel or stay arbitration bears the initial responsibility of
demonstrating the absence of a genuine issue of material fact. See Celotex Corp. v. Catrett, 477
U.S. 317, 323 (1986). In determining whether there is a genuine issue of material fact sufficient
to preclude summary judgment, the non-movant's statements should be accepted as true and all
inferences should be drawn in his favor. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255
(1986). The non-moving party, however, must establish more than the “mere existence of a
scintilla of evidence” in support of its position. Id. at 252. “If the evidence is merely colorable,
or is not significantly probative, summary judgment may be granted.” Id. at 249-50 (internal
citations omitted).
II. MANHATTAN’s MOTION TO COMPEL ARBITRATION2
A. Legal Standard for Motion to Compel Arbitration
The Federal Arbitration Act (“FAA”) provides that “[a] written provision in . . . a
contract evidencing a transaction involving interstate commerce to settle by arbitration a
controversy thereafter arising out of such contract or transaction . . . shall be valid, irrevocable,
and enforceable, save upon such grounds as exist at law or in equity for the revocation of any
contract.” 9 U.S.C. § 2. The question of whether a particular dispute is arbitrable is “undeniably
an issue for judicial determination.” AT&T Techs. v. Commc’ns Workers of Am., 475 U.S. 643,
649 (1986) (citations omitted). The basis for judicial authority to make this determination lies in
2 Because the analysis of Manhattan’s motion to compel arbitration is crucial in resolving all the other motions, the Court will address this motion first.
5 the fact that arbitration agreements are separable from the agreements in which they are
incorporated. See Prima Paint Corp. v. Flood & Conklin Mfg. Co., 388 U.S. 395, 403–04
(1967); Buckeye Check Cashing, Inc. v. Cardegna, 546 U.S. 440, 445–46 (2006).
A strong policy favoring alternative means of dispute resolution through arbitration
supports a presumption of arbitrability. Moses H. Cone Mem’l Hosp. v. Mercury Constr.
Corp., 460 U.S. 1, 24–25 (1983); see also Buckeye Check Cashing, 546 U.S. at 440. However,
“the FAA does not require parties to arbitrate when they have not agreed to do so.” Volt Info.
Scis., Inc. v. Bd. of Trs. of Leland Stanford Jr. Univ., 489 U.S. 468, 478 (1989) (citation
omitted). Indeed, the overriding purpose of the FAA is not judicial economy or the expeditious
resolution of claims, but the enforcement of agreements into which parties have entered. Dean
Witter Reynolds, Inc. v. Byrd, 470 U.S. 213, 219–20 (1985). As articulated by the Supreme
Court, “arbitration is a matter of contract and a party cannot be required to submit to arbitration
any dispute which he has not agreed so to submit.” AT&T Techs., 475 U.S. at 648.
Relying on the language of the FAA, which states that arbitration agreements “shall be
valid, irrevocable, and enforceable, save upon such grounds that exist at law or in equity for the
revocation of any contract,” 9 U.S.C. § 2, federal courts have applied “ordinary state-law
principles that govern the formation of contracts” when determining arbitrability, First Options
of Chicago, Inc. v. Kaplan, 514 U.S. 938, 944 (1995). Thus, while mindful of the federal policy
favoring arbitration, it is the court’s task to determine the parties’ intent. Nat’l R.R. Passenger
Corp. v. Boston & Maine Corp., 850 F.2d 756, 760–61 (D.C. Cir. 1988).
Such questions of arbitrability are usually brought before the court pursuant to section 4
of the FAA, which allows a party to petition any United States District Court which would
6 otherwise have subject-matter jurisdiction “for an order directing that such arbitration proceed in
the manner provided for in such agreement.” 9 U.S.C. § 4. When deciding a motion to compel
arbitration, a district court must “determine the enforceability of the agreement [to arbitrate] and
decide whether arbitration should be compelled.” Nelson v. Insignia/Esg. Inc., 215 F. Supp. 2d
143, 146 (D.D.C. 2001). In determining whether arbitration should be compelled, the court
analyzes the arbitration agreement under the FAA and applicable state law to determine whether
(1) the parties entered into a valid and enforceable arbitration agreement and (2) whether the
arbitration agreement encompasses the claims raised in the complaint. Hughes v. CACI, Inc.,
384 F. Supp. 2d 89, 95 (D.D.C. 2005) (citing Nelson v. Insignia/ESG, Inc., 215 F. Supp. 2d 143,
149–50 (D.D.C. 2002)).
B. Legal Analysis
There is no dispute that Manhattan and Joint Venture entered into a binding arbitration
agreement. See Manhattan’s Mot. to Compel Arbitration (“Mot. to Compel”) at 5; Pl.’s Mot. for
Prelim. Inj. at 2-3. Both parties signed the Subcontract, which contained an arbitration clause,
and “a signature on a contract indicates mutuality of assent and a party is bound by the contract
unless he or she can show specific circumstances relieving him or her of such an obligation.”
Emeronye v. CACI Intern., Inc, 141 F. Supp. 2d 82, 86 (D.D.C. 2001) (applying District of
Columbia and Virginia law) (citations and internal quotation marks omitted). Nor do the parties
dispute that the underlying breach of contract claims are encompassed within the arbitration
agreement. The arbitration agreement is a broad one and covers “any dispute” between Joint
Venture and Manhattan. Mot. to Compel, Ex. 1 (Subcontract) at 4, § 3.5.2.
Instead, the parties dispute whether Manhattan complied with the requirements
7 enumerated in the arbitration agreement, and hence whether it was within Manhattan’s right to
invoke the arbitration agreement at all with respect to the parties’ breach of contract claims.
Whereas Joint Venture argues that Manhattan’s arbitration demand was untimely, and that it
therefore waived its right to arbitration, Manhattan contends that based on the language of the
arbitration clause its demand for arbitration was timely under the Subcontract. The arbitration
provision in the Subcontract provides that “[a]ll other disputes between the parties shall be
resolved by litigation . . . except that Manhattan may, at its sole option, require that any dispute
be submitted to arbitration. . . . The election by Manhattan shall be made no later than thirty (30)
days following receipt of service of process of any such litigation from subcontractor . . . .” Mot.
to Compel, Ex. 1 (Subcontract) at 4, § 3.5.2. As is often the case in contract disputes, the parties
disagree regarding the proper interpretation of this language. According to Manhattan, the 30-
day election period applies only when there is a dispute between Manhattan and the Joint
Venture and when Manhattan has received service of process. But, because Joint Venture has
never filed a complaint against Manhattan seeking to resolve “disputes between the parties
[Manhattan and the Joint Venture]” and because “Manhattan has never received ‘service of
process’ of the Joint Venture’s suit against Federal Insurance,” Manhattan claims that Joint
Venture’s suit against FIC did not trigger Manhattan’s 30-day election period. Mot. to Compel
(citing Exhibit A ¶ 3.5.2.) (alteration in original). Therefore, Manhattan argues that the
arbitration agreement covers Manhattan’s claims against Joint Venture.
Joint Venture claims that arbitration is not proper because the arbitration initiated by
Manhattan is plainly outside of the terms of the parties’ limited arbitration agreement.
According to Joint Venture, the Subcontract’s “‘Settlement of Disputes’ clause explicitly states
8 that litigation is the agreed form of dispute resolution” except under the following limited
circumstances: (1) Manhattan can elect arbitration after it initiates litigation against the Joint
Venture or (2) Manhattan can elect arbitration within 30 days after service if Joint Venture
initiates litigation. Pl.’s Mot. for Prelim. Inj. at 9. Because Manhattan waited ten months until
“after Manhattan’s attorneys (who also act as FIC’s attorneys) were served with the Joint
Venture’s complaint in the Miller Act case,” Joint Venture argues that it failed to make a timely
election of arbitration,” and therefore Manhattan and FIC waived their right to arbitration. Id.
Joint Venture further argues that the distinction made by Manhattan, namely that Joint
Venture sued FIC and not Manhattan, is irrelevant. According to Joint Venture, the entire basis
of FIC’s defense in the Miller Act case is that it stands in the shoes of Manhattan, and will assert
any defenses Manhattan has; their liability is intertwined, and FIC is liable only to the extent
Manhattan is liable. Therefore, under the same principle, FIC should have made the election of
arbitration within the 30-day time limit that was specified in the contract. Because both FIC and
Manhattan failed to do so, the Joint Venture contends that Manhattan cannot now elect to
arbitrate its claims.
Joint Venture’s arguments are unpersuasive. Joint venture provides no textual or legal
support for its proposition that Manhattan’s 30-day time limit was triggered by the service of
process on FIC, and its effort to arbitrate is therefore untimely. To the contrary, the plain
language of the arbitration clause provides that Manhattan’s 30-day time limit to elect arbitration
is triggered by (1) a “dispute between the parties” and (2) “receipt of service of process of any
such litigation from Subcontractor.” First, FIC is not a party to the Subcontract; therefore, any
disputes against FIC should not trigger the 30-day time limit. The language of the contract
9 makes this clear. Section 3.5.1 begins by describing what will happen “[i]n case of any disputes
between Manhattan and Subcontractor.” Mot. to Compel, Ex. 1 (Subcontract) at 4. Section
3.5.2 continues, “[a]ll other disputes between the parties shall be resolved by litigation . . .
except that Manhattan may, at its sole option, require that any dispute be submitted to arbitration
. . . . The election by Manhattan shall be made no later than thirty (30) days following receipt of
service of process of any such litigation from Subcontractor.” The phrase “[a]ll other disputes
between the parties” in section 3.5.2 refers back to the discussion of disputes between Manhattan
and Subcontractor, in section 3.5.1. Because Manhattan and the Joint Venture are the only
parties contemplated in sections 3.5.1 and 3.5.2, the disputes between Manhattan and the Joint
venture are the only disputes that can trigger Manhattan’s 30-day time limit to elect arbitration.
Furthermore, because Manhattan never received service of process, neither of the two triggering
factors can be said to have occurred.3
Furthermore, the Court is not convinced by the Joint Venture’s contention that FIC
should have made an election of arbitration when it was served with process. The Joint Venture
seems to argue that if a surety can assert the defenses of the general contractor when it is sued by
the subcontractor, it should also be bound by the specific terms of the Subcontract between the
3 In its opposition to Manhattan’s motion to dismiss the complaint, Joint Venture presents an additional argument that it did not raise in its opposition to compel arbitration or in its motion for preliminary injunction. It argues that because the arbitration clause states that “[t]he election by Manhattan shall be made no later than thirty (30) days following receipt of service of process of any such litigation from Subcontractor,” Manhattan has 30 days to elect arbitration if Joint Venture initiates “any litigation” – not just litigation against Manhattan. Pl.’s Opp’n to Def.’s Mot. to Dismiss at 2. This reading, however, is misplaced. The terms “any such litigation” seems to refer to the opening sentence of 3.5.2, which states “All other disputes between the parties shall be resolved by litigation . . . .” Mot. to Compel, Ex. 1 (Subcontract) at 4 (emphasis added). As mentioned above, however, FIC is not a party to the subcontract. Therefore, Joint Venture’s litigation against FIC does not trigger Manhattan’s 30 day time-limit.
10 general contractor and the subcontractor. Joint Venture, however, has provided no case support
for this argument and the specific terms of the Subcontract seems to refute such an assertion.
Section 1.1.2.2 states that “[t]he Subcontract may not be construed to create any contractual
relationship of any kind between . . . any persons or entities other than Manhattan and
Subcontractor.” Mot. to Compel, Ex. 1 (Subcontract) at 1. Further refuting Joint Venture’s
argument is the fact that many courts have found that an agreement to arbitrate in the
Subcontract does not by itself bind the surety to arbitration. See e.g., Employers Ins. of Wasusau
v. Bright Metal Specialties, Inc., 251 F.3d 1316 (11th Cir. 2001) (holding that surety for general
contractor could not be compelled to arbitrate subcontractor’s claims against it, where the surety
had not contractually agreed to arbitrate any claims arising out of its surety relationship with the
general contractor); U.S. for Use and Benefit of Capital Elec. Const. Co., Inc., v. Pool and
Canfield Inc., 778 F. Supp. 1088, 1090 (W.D.Mo. 1991) (stating that by issuing a bond, surety
did not agree to arbitrate claims despite arbitration agreement between contractor and
subcontractor).
Based on the foregoing interpretation of the arbitration clause, the Court finds that
Manhattan’s arbitration claim is timely and, therefore, is covered by the Subcontract’s arbitration
provision. The Court’s interpretation is reinforced by well-settled case law directing it to
construe the Subcontract “with a healthy regard for the federal policy favoring arbitration.”
Moses H. Cone Mem’l Hosp., 460 U.S. at 24. “An order to arbitrate [a] particular grievance
should not be denied unless it may be said with positive assurance that the arbitration clause is
not susceptible of an interpretation that covers the asserted dispute.” AT & T Technologies, Inc.
11 v. Communications Workers of America, 475 U.S. 643, 650 (1968) (quoting Steelworkers v.
Warrior & Gulf Navigation Co., 363 U.S. 574, 582-83 (1960)).
Accordingly, the Court concludes Manhattan’s motion to dismiss and motion to compel
arbitration should be granted and Joint Venture’s motion for preliminary injunction should be
denied as moot.
III. FIC’s MOTION TO STAY
Occurring simultaneously to the suit between Joint Venture and Manhattan is Joint
Venture’s suit against FIC, initiated in December of 2008. In that case, Joint Venture seeks to
recover money unpaid by Manhattan under the Miller Act. The Miller Act “requires contractors
doing work with the federal government to furnish payment bonds with a surety in order to
protect those who provide work or material on the government project.” United States ex rel.
Walker Seal Cos., Inc. V. Liberty Mutual Ins. Co., 356 F. Supp. 2d 1 (D.D.C. 2005) (citing 40
U.S.C. § 3131). Further, the Miller Act provides a civil cause of action against the surety for
subcontractors doing work on a government project who have not received payment within 90
days within completion of work. See Walker Seal Cos., 356 F. Supp. 2d at 1-2 (citing 40 U.S.C.
§ 3133). FIC has moved to stay the case, arguing that the court is obligated to grant such a stay
under the FAA. Def.’s Mot. to Stay at 4-5. By contrast, Joint Venture argues that a stay in a
case such as the instant one lies within the discretion of the court, and that the court should
utilize its discretion and refuse to grant a stay pending arbitration with Manhattan. Pl.’s Opp. at
6.
A. Whether to stay the instant case is a matter of judicial discretion
Under certain circumstances, the FAA requires a district court to stay a federal suit
12 pending arbitration. U.S. ex rel. MPA Const., Inc. v. XL Specialty Ins. Co., 349 F. Supp. 2d 934,
940 (D.Md. 2004). In pertinent part, the FAA reads:
If any suit or proceeding be brought in any of the courts of the United States upon any issue referable to arbitration under an agreement in writing for such arbitration, the court in which such suit is pending, upon being satisfied that the issue involved in such suit or proceeding is referable to arbitration under such an agreement, shall on application of one of the parties stay the trial of the action until such arbitration has been had in accordance with the terms of the agreement.
9 U.S.C. § 3. Where the issues are not “referable to arbitration,” however, the courts have
discretionary power to stay civil proceedings pending the resolution of arbitration. See DSMC,
Inc. v. Conerva Corp., 273 F. Supp. 2d 14, 30 (D.D.C. 2002) (citing Moses H. Cone Mem'l Hosp.
v. Mercury Constr. Corp., 460 U.S. 1, 21 n. 23 (1983) (“In some cases, of course, it may be
advisable to stay litigation among the non-arbitrating parties pending the outcome of the
arbitration. That decision is one left to the district court . . . as a matter of its discretion to control
its docket.”).
Whereas FIC urges the Court that a stay is mandatory in this case under the FAA, Def.’s
Mot. to Stay at 4-5, Joint Venture argues that the stay is discretionary because the underlying
issue is not “referable to arbitration.” Pl.’s Opp’n at 6. The Court agrees with Joint Venture. As
noted above, FIC was not a party to the agreement to arbitrate between Joint Venture and
Manhattan. Therefore, Joint Venture’s Miller Act suit against FIC is not an “issue referable to
arbitration under an agreement in writing for such arbitration,” and whether or not to stay such a
suit pending resolution of arbitration is within the court’s discretion. See DSMC, 273 F. Supp.
2d at 30 n. 5 (holding that it is within court’s discretion to grant stay because “[t]he mandatory
stay provision of the Act applies only to parties to the arbitration agreement” (citing IDS Life Ins.
Co. v. SunAmerica, Inc., 103 F.3d 524, 529-30 (7th Cir. 1996))).
13 In moving for a stay, FIC argues that because the factual and legal questions to be settled
in the arbitration between Joint Venture and Manhattan are the same questions that would be
litigated in Joint Venture’s present suit against FIC, allowing both to proceed simultaneously
would be an inefficient use of resources. Furthermore, they suggest, Joint Venture’s suit against
FIC on the surety bond was simply a way for it to avoid arbitrating the question of contractual
liability vis-à-vis Manhattan. Joint Venture counters that in fact its Miller Act suit is a separate
and distinct cause of action from its contractual claims against Manhattan, and therefore should
not be barred from pursuing a remedy against FIC. Moreover, they suggest, staying the instant
case would only delay further the resolution of the dispute.
In light of the concerns over judicial economy and the possibility of inconsistent results,
coupled with the strong federal presumption in favor of enforcing arbitration agreements and the
underlying purpose of the Miller Act, the Court finds in favor of FIC and stays Joint Venture’s
Miller Act claim against FIC pending the resolution of arbitration between Joint Venture and
Manhattan.
1. Staying plaintiff’s suit against the surety comports with judicial economy and consistency
As a matter of this Court’s discretion to “control its docket,” there are important
considerations of judicial economy and consistency involved in the claims and defenses at issue
here. As FIC points out, its liability to Joint Venture is dependent upon whether Manhattan is
liable under its contract with Joint Venture. See Def.’s Mot. to Stay at 4-5. Thus, FIC and Joint
Venture would be litigating substantially the same issues being arbitrated between Manhattan
and Joint Venture, namely the liability between Manhattan and Joint Venture under the
14 Subcontract.4 As one court stated, “It seems grossly inefficient to have the parties arbitrate and
litigate at the same time or bear unnecessary expense and the risk of inconsistent results.” United
States ex rel. MPA Constr., Inc. v. XL Specialty Ins. Co., 349 F. Supp. 2d 934, 941 (D. Md.
2004) (quoting United States ex rel. Tanner v. Daco Constr., Inc., 38 F. Supp. 2d 1299, 1304-05
(N.D. Okla. 1999). This Court agrees. It would be an inefficient use of both the Court’s and the
parties’ resources to simultaneously debate the same issues in two distinct forums.5
It is also true that issuing a stay in this case will not result in “indefinite delay,” as Joint
Venture suggests. Pl’s Opp’n at 10. If Joint Venture prevails at arbitration, its award will be
enforceable against Manhattan. Insofar as Joint Venture is unable to enforce against Manhattan,
Joint Venture need not reinstate its litigation against FIC because FIC has already agreed to be
bound by the arbitration.
In the opposite scenario, were Manhattan to prevail at arbitration, Joint Venture would
likely be bound by the result, foreclosing further litigation with FIC. At the very least, Joint
Venture would likely be bound by the doctrine of collateral estoppel, also known as issue
4 Presumably FIC would not seek to establish Joint Venture's liability under the Subcontract, as Manhattan seeks to do in arbitration. Nevertheless, Manhattan's liability would be at issue in both the litigation and arbitration proceedings. Manhattan could have moved to intervene pursuant Fed. R. Civ. Pro. 24(b), see United States ex. rel. MPA Constr., Inc. v. XL Specialty Ins. Co., 349 F. Supp. 2d 934, 938-39 (D. Md. 2004) (granting prime contractors 24(b) motion to intervene in Miller Act suit by subcontractor against surety), but instead chose to pursue its claims under the agreed upon arbitration provision in the Subcontract. This Court will not require Manhattan to intervene in the present suit to assert its claims against Joint Venture where the two parties have agreed such claims are arbitrable. To do so would cut against what the parties assented to, as well as the enunciated policy in favor of arbitration. See Moses H. Cone Mem'l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24 (1983). 5 It should also be noted, once again, that Manhattan is not a party to this suit because Joint Venture chose not to assert Manhattan as a defendant. As a result, unless Manhattan were to intervene in this suit, litigation of Joint Venture's claims under the subcontract would occur through FIC. Arbitration between Joint Venture and Manhattan, therefore, would be far more efficient.
15 preclusion. In federal court, a claimant may be barred from relitigating an issue decided in a
previous proceeding even where one of the parties in the new litigation was not a party in the
previous proceeding. See Blonder-Tongue Labs., Inc. v. Univ. of Ill. Found., 402 U.S. 313
(1971) (abolishing the requirement of mutuality when decideding whether a party is collaterally
estopped from relitigating an issue already decided). Where a plaintiff attempts to litigate an
issue already decided against a new party, the plaintiff is foreclosed from relitigating the issue if:
1) the issue was actually litigated with a full and fair opportunity to litigate, 2) the issue was
actually decided on the merits, 3) the disposition was sufficiently final, and 4) the resolution of
the issue was necessary to the disposition of the first action. Am. Train Dispatchers Ass’n v.
Burlington Northern R. Co., 784 F. Supp. 899, 903 (D.D.C. 1992) (citing Nat’l Post Office Mail
Handlers v. Am. Postal Workers Union, 907 F.2d 190, 192 (D.C. Cir. 1990)). The Court cannot
decide the issue here, but suffice it to say that FIC could likely preclude Joint Venture from
relitigating the issue of contractual liability after arbitration. First, “[t]he decisions of binding
arbitration proceedings are final decisions on the merits for the purposes of res judicata.” Cent.
Itn’l Arms, Ltd. v. Fed. State Unitary, 172 F. Supp. 2d 79, 95 (D.D.C. 2001) (citing Schattner v.
Girard, Inc., 668 F.2d 1366, 1368 (D.C. Cir. 1981)). Second, Joint Venture will have had a full
and fair opportunity to litigate the underlying issue between it and FIC in arbitration with
Manhattan, i.e. whether Manhattan is liable for Joint Venture’s contractual claims. Finally, the
resolution of the issue of liability will have been necessary to the disposition of the arbitration.
Thus, at the very least Joint Venture would likely be barred from relitigating in this suit the
underlying issue that will be decided in its arbitration with Manhattan. Even if Joint Venture
16 were to not prevail at arbitration, therefore, it is unlikely that any significant delay will result
from a stay in this suit.
2. Staying plaintiff’s suit against the surety accords with the federal policy favoring the enforcement of valid arbitration agreements and does not contravene the purpose of the Miller Act
Allowing litigation to proceed in this suit alongside arbitration would disserve the
“liberal federal policy favoring arbitration agreements.” See Moses H. Cone Mem’l Hosp. v.
Mercury Constr. Corp., 460 U.S. 1, 24 (1983). This is true for two interrelated reasons. First, as
previously noted, allowing this case to proceed would force prime contractors with claims
against subcontractors—who have agreed to arbitrate disputes with subcontractors—to join
litigation initiated by subcontractors against the surety. In effect, it would draw Manhattan into
litigation with Joint Venture despite the fact that the two parties agreed to settle disputes through
arbitration in certain circumstances. Second, as the court noted in Tanner, not staying litigation
under these circumstances would allow any public works subcontractor to “circumvent” its
agreements to arbitrate with the prime contractor simply by suing the surety in federal court. See
Tanner, 38 F. Supp. 2d at 1306. Thus, not staying the proceeding would render the arbitration
provision in the subcontract, and Manhattan’s resulting right to arbitrate with Joint Venture,
“meaningless.” Id. Such a negation of the agreement to arbitrate in the subcontract cannot be
allowed in light of the overriding purpose of the FAA to “enforce [arbitration] agreements into
which parties have entered.” Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. 213, 220 (1985).
Joint Venture also argues that “a payment bond claim under the Miller Act is a distinct
remedy and a distinct cause of action, and it is not simply an alternative form of a breach of
contract claim or a way of ‘circumventing’ an arbitration clause.” Pl.’s Opp’n at 9. Therefore,
17 Joint Venture asserts, it is not circumventing contract law or the arbitration clause but merely
utilizing the remedy Congress intended to provide through the Miller Act. Id. There are two
problems with Joint Venture’s argument.
First, although the Court is staying its Miller Act claim against FIC, Joint Venture will
not lose the benefit that the Miller Act was intended to provide. The Miller Act undoubtedly
provides subcontractors with a distinct cause of action by allowing subcontractors to sue sureties
on payment bonds, and is not simply an alternative to contract law claims. Joint Venture is
correct in so asserting, but recognizing that fact does not end the inquiry. The purpose behind
the Miller Act suggests a distinct reason for providing a separate cause of action. Because an
aggrieved subcontractor cannot secure a mechanic’s lien on public property, and therefore may
be unable to recover from the general contractor on a contract claim, the purpose of the Miller
Act was to “afford the subcontractor [working on public construction projects] the financial
protection of an action against the surety.” See United States ex. rel. Mariana v. Piracci Constr.
Co., Inc., 405 F. Supp. 904, 906 (D.D.C. 1975); see also F.D. Rich Co. v. United States ex. rel.
Indus. Lumber Co., Inc., 417 U.S. 116, 122 (1974) (“The Miller Act was intended to provide an
alternative remedy to protect the rights of these suppliers.” (emphasis added)). The Miller Act is
thus designed to ensure that subcontractors can secure a remedy against general contractors on
public projects.
Here, however, FIC has agreed to be bound by the result of arbitration. Were Joint
Venture to succeed at arbitration but be unable to secure its remedy against Manhattan, it could
still immediately collect on the bond against FIC. Stated differently, because FIC has agreed to
be bound by any arbitration award, Joint Venture has the protection Congress intended to
18 provide through the Miller Act. Although the Miller Act undoubtedly provides subcontractors
with a federal cause of action and remedy apart from a state law mechanic’s lien, that remedy is
not foreclosed by the arbitration the parties have agreed to in this case. In light of the purpose
behind the cause of action in the Miller Act, Joint Venture will not be harmed by staying that
cause of action pending arbitration.
Second, it is true that the Miller Act is not generally “a way of ‘circumventing’ an
arbitration clause.” Recognizing that circumvention is not the Miller Act’s purpose does not
negate the fact that that is undoubtedly what Joint Venture seeks to do in this case. Having
agreed to arbitrate contractual issues with Manhattan, Joint Venture cannot now avoid its
obligation by only suing the surety on the payment bond. Cf. United States ex. rel. Capolino
Sons, Inc. v. Electronic & Missile Facilities, Inc., 364 F.2d 705, 706-07 (2d Cir. 1966) (“Though
[the subcontractor] would otherwise be free . . . to sue the prime contractor and the surety on the
contractor’s payment bond, there is no inconsistency in requiring that an arbitration precede
resort to the courts if the [subcontractor] and the contractor had previously agreed to arbitrate
disputes.”).
Indeed, staying this case pending arbitration is in accord with the opinions of several
other courts faced with the task of resolving tensions between the Federal Arbitration Act and
the Miller Act. Tanner, 38 F. Supp. 2d at 1304 (stating that there is “a long history of Miller Act
cases which resolve the tension between the Miller Act and the Federal Arbitration Act by
staying the Miller Act claim pending arbitration of the underlying dispute”); see United States
ex. rel. Newton v. Neumman Caribbean Int’l, Ltd., 750 F.2d 1422, 1426-27 (9th Cir. 1985)
(holding the district court did not abuse its discretion where it granted subcontractor’s motion to
19 compel arbitration with contractor and surety and motion to stay pending arbitration); United
States ex. rel. Portland Constr. Co. v. Weiss Pollution Control Corp., 532 F.2d 1009, 1013 (5th
Cir. 1976) (staying Miller Act proceeding pending resolution of arbitration between prime
contractor and subcontractor); United States ex. rel. Capolino Sons, Inc. v. Electronic & Missile
Facilities, Inc., 364 F.2d 705, 709 (2d Cir. 1966) (holding Miller Act claims arbitrable and
affirming the district court’s decision to stay Miller Act proceeding pending arbitration);
Agostoni Bros. Building v. United States ex. rel. Virginia-Carolina Elec. Works, Inc., 142 F.2d
854, 855 (4th Cir. 1944) (reversing district court’s denial of stay pending arbitration in Miller
Act suit). But see United States ex. rel. Pensacola Constr. Co. v. St. Paul Fire & Marine Ins.
Co., 705 F. Supp. 306, 309 (W.D. La. 1988) (denying general contractor’s motion to stay
because the motion would not damage the general contractor but would harm the subcontractor
by stripping it of its Miller Act remedy).6
DSMC, Inc. v. Convera Corp., 273 F. Supp. 2d 14 (D.D.C. 2002), a case heavily relied
upon by plaintiffs, is factually distinct from the case at bar.7 The court’s reasoning in DSMC
6 The court’s holding in Pensacola is unpersuasive both generally and in the context of the instant case. In general, if a court grants a stay pending arbitration and the subcontractor prevails at arbitration, the subcontractor still retains the protection of the Miller Act. Where a subcontractor prevails at arbitration but the general contractor is unable to pay, the subcontractor can simply restart its Miller Act suit against the surety in federal court. Furthermore, in this case FIC has agreed to be bound by the outcome of the arbitration. Joint Venture, therefore, has not lost the protection the Miller Act was meant to provide and will not be harmed in the way the Pensacola court feared. 7 In DSMC, DSCMi contracted with National Geographic Television Library (NGTL) to provide digitizing and cataloguing services to organize NGTL's film footage archive. DSMC, Inc., F. Supp. 2d at 17. DSMCi initiated arbitration against NGTL, pursuant to their contract, alleging breach of the confidentiality agreement, and simultaneously sued a third party, Conerva, in federal court for state tort law and federal copyright violations. Id. at 17-18. NGTL moved to intervene in the federal court proceeding and stay the action pending its arbitration with DSMCi. Id.
20 does not apply in this case. Here, the concern is not that the issues could simply be narrowed by
arbitration. Rather, arbitration would decide the relevant issues completely. FIC’s liability is
completely dependent upon whether Manhattan breached its contract with the plaintiffs, the issue
currently pending in arbitration. FIC has also consented to be bound by the arbitration result.
Furthermore, whereas DSCMi would still have to litigate whether Convera violated federal
copyright laws if it prevailed at arbitration against NGTL, no litigation would be necessary in
this case after a final decision in arbitration. Thus, this is not a case where litigation would
simply be delayed, as in DSMC. Instead, the court is simply deferring to the arbitration which
both parties consented to in the subcontract.
To the extent that plaintiffs rely on the court’s decision in United States ex. rel. Walker
Seal Cos., Inc. v. Liberty Mut. Ins. Co., 356 F. Supp. 2d 1 (D.D.C. 2005), that case is inapposite
in two ways.8 First, the subcontractor in that case expressly reserved the right not to arbitrate
any Miller Act claims.9 Id. at 2. The court’s decision, therefore, did not offend the federal
presumption in favor of arbitration because the parties specifically agreed not to arbitrate such
claims. Second, the general contractor in Walker Seal had not initiated arbitration to assert its
own claims against the subcontractor, as Manhattan did in this case. Id. at 1-2. As a result,
8 Similar to the circumstances here, the contractor and subcontractor in Walker Seal agreed to arbitrate contractual claims prior to initiating suit in court. Id. at 2. Once a dispute arose, the subcontractor initiated suit in federal court against the surety pursuant to the Miller Act. Id. The surety then moved to dismiss, and in the alternative, stay the case pending arbitration of the matter. Id. The court denied the motions. Id. at 3. 9 An addendum to the contract stated that “[n]othing herein shall limited the Subcontractor’s rights under [the general contractor’s] payment bond or the Miller Act.” Id. at 2. The president of the subcontractor also submitted an affidavit stating that the intention behind the addendum was to nullify the general arbitration requirement with respect to the bond claim. Id.
21 there would have been no concurrent litigation and arbitration, and thus no potential for
duplicate proceedings and no concern about judicial economy.
Weighing the federal policy favoring the enforcement of arbitration agreements, taking
into consideration the purpose behind the Miller Act and the risk of inconsistency and inefficient
use of resources, the Court exercises its discretion to stay the Joint Venture’s Miller Act claim
pending the resolution of arbitration between Joint Venture and Manhattan.
V. CONCLUSION
For the foregoing reasons, in the case of Milestone Tarant, LLC v. Manhattan
Construction Co., Civ. No. 09-1941, Manhattan’s motions to compel arbitration [#7 ] and to
dismiss [#11] are GRANTED and Joint Venture’s motion for a preliminary injunction [#2] is
DENIED as moot. In Milestone Tarant, LLC v. Federal Insurance Company, Civ. No. 08-2186,
FIC’s motion to stay pending arbitration [#8] is GRANTED. Appropriate orders accompany
this memorandum opinion.
ROYCE C. LAMBERTH Chief Judge United States District Court