United States v. Pool and Canfield, Inc.

778 F. Supp. 1088, 1991 WL 263266
CourtDistrict Court, W.D. Missouri
DecidedDecember 14, 1991
Docket91-0596-CV-W-2
StatusPublished
Cited by11 cases

This text of 778 F. Supp. 1088 (United States v. Pool and Canfield, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Pool and Canfield, Inc., 778 F. Supp. 1088, 1991 WL 263266 (W.D. Mo. 1991).

Opinion

ORDER

GAITAN, District Judge.

Pending before the court is Safeco Insurance Company of America’s (hereafter defendant) motion for a preliminary injunction prohibiting Capital Electric from proceeding to arbitrate its claims against defendant. It is defendant’s contention that it cannot be compelled to arbitrate any claims arising in the above titled action because (1) it is not a party to any arbitration agreement with the plaintiff, and (2) as a Miller Act surety, the exclusive jurisdiction for plaintiff’s action is federal district court.

The defendant is seeking a preliminary injunction to prevent plaintiff from compelling defendant into arbitration. Both parties have correctly noted that whether a request for a preliminary injunction should be granted involves judicial consideration of: (1) the threat of irreparable harm; (2) the balance of hardships between this harm and the injury that granting the injunction will inflict on the other parties; (3) the chances the movant has of .success on the merits; and (4) the public interest. Data-phase Systems, Inc. v. CL Systems, Inc., 640 F.2d 109, 114 (8th Cir.1981). The court finds, after consideration of the above factors, that injunctive relief preventing defendant Safeco from being forced into compulsory arbitration is warranted.

The United States Court of Appeals, Eighth Circuit has held that a two-part analysis should be used to determine whether a party can be compelled into arbitration. “[T]he ‘first task ... is to determine whether the parties agreed to arbi *1090 trate that dispute. If so, the next step is to consider whether some external legal constraint forecloses arbitration of those claims.” Nordin v. Nutri/System, Inc., 897 F.2d 339, 344 (8th Cir.1990) (quoting Gans v. Merrill Lynch Futures, Inc., 814 F.2d 493, 495 (8th Cir.1987); see also Mitsubishi Motors Corp. v. Soler Chrysler-Plymouth, Inc., 473 U.S. 614, 105 S.Ct. 3346, 87 L.Ed.2d 444 (1985). In evaluating the first task, the Supreme Court has noted that “ ‘arbitration is a matter of contract and a party cannot be required to submit to arbitration any dispute which he has not agreed to submit.’ ” AT & T Technologies, Inc. v. Communications Workers of Am., 475 U.S. 643, 648, 106 S.Ct. 1415, 1418, 89 L.Ed.2d 648 (1986) (quoting United Steelworkers v. Warrior & Gulf Navigation Co., 363 U.S. 574, 582, 80 S.Ct. 1347, 1353, 4 L.Ed.2d 1409 (1960)); see also Nordin, 897 F.2d at 344. Further, “ ‘the question of whether the parties agreed to arbitrate is to be decided by the court, not the arbitrator.’ ” AT & T, 475 U.S. at 649, 106 S.Ct. at 1418 (quoting United Steelworkers, 363 U.S. at 582-83, 80 S.Ct. at 1352-53). The Eighth Circuit concluded in Nor-din that “it was for the district court, not an arbitrator, to determine whether there was in fact an agreement to arbitrate____” 897 F.2d at 344.

In the present case there is no dispute that the agreement to arbitrate exists only in the contract between the plaintiff/subcontractor, Capital Electric, and the defendant/general contractor, Pool & Can-field. There exists no agreement between plaintiff and defendant, Safeco, obligating Safeco to arbitrate plaintiff’s claims. Plaintiff argues that the arbitrator should be allowed to determine whether defendant Safeco can be compelled to arbitrate. However, this is clearly against the dictates of AT & T and Nordin. This court finds that Safeco has not contractually agreed to arbitrate any claims arising out of its surety relationship with Pool & Can-field, nor has plaintiff ever asserted otherwise. Accordingly, plaintiff has failed to met the “first task” set forth in Nordin. For this reason alone the court could find that defendant cannot be compelled into arbitration. However, even assuming defendant did agree to arbitrate claims arising out of its suretyship, there is an “external legal constraint foreclosespng] arbitration of those claims.” Nordin v. Nutri/System, Inc., 897 F.2d 339, 344 (8th Cir.1990).

The surety relationship existing between defendant and Pool & Canfield arises out of the Miller Act, specifically that portion of the act embodied in 40 U.S.C. § 270a (1988). Section 270a provides that any contract for public works of the United States shall be supported by “performance” and “payment” surety bonds which generally serve to protect “all persons supplying labor and material in the prosecution of the work provided for in said contracts____” 40 U.S.C. § 270a(a)(2) (1988). Defendant contracted with Pool & Canfield to act as a “performance” and “payment” surety to insure payment to subcontractors such as plaintiff. As a Miller Act surety, however, plaintiff’s legal recourse for seeking compensation from defendant is exclusively limited to federal district court. 40 U.S.C. § 270b states that every action initiated by a subcontractor such as plaintiff “shall be brought in the name of the United States for the use of the person suing, in the United States District Court for any district in which the contract was to be performed and executed and not elsewhere....” 40 U.S.C. § 270b(b) (1988).

While the Eighth Circuit has not specifically addressed the question of whether a Miller Act surety can be compelled into arbitration to the exclusion of federal jurisdiction, it has held that “as between a state court ... and a federal court ... the statute is jurisdictional in character and operation and places exclusive jurisdiction over Miller Act bond suits in the federal tribunal.” Koppers Co. v. Continental Casualty Co., 337 F.2d 499, 506 (8th Cir.1964). Others courts, however, have faced the precise issue before this court and determined that, barring waiver of the Miller Act, suits against Miller Act sureties must be adjudicated in federal court. In United States ex rel Portland Constr. Co. v. Weiss Pollution *1091 Control Corp., 532 F.2d 1009 (5th Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tiffany v. Ko Huts, Inc.
178 F. Supp. 3d 1140 (W.D. Oklahoma, 2016)
Edward E. Gillen Co. v. Insurance Co. of Pennsylvania
747 F. Supp. 2d 1058 (E.D. Wisconsin, 2010)
United States Ex Rel. Milestone Tarant, LLC v. Federal Insurance
672 F. Supp. 2d 92 (District of Columbia, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
778 F. Supp. 1088, 1991 WL 263266, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-pool-and-canfield-inc-mowd-1991.