Employers Insurance v. Bright Metal

CourtCourt of Appeals for the Eleventh Circuit
DecidedMay 22, 2001
Docket98-5404
StatusPublished

This text of Employers Insurance v. Bright Metal (Employers Insurance v. Bright Metal) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Employers Insurance v. Bright Metal, (11th Cir. 2001).

Opinion

[PUBLISH]

IN THE UNITED STATES COURT OF APPEALS FILED FOR THE ELEVENTH CIRCUIT U.S. COURT OF APPEALS ELEVENTH CIRCUIT MAY 22, 2001 ________________________ THOMAS K. KAHN CLERK No. 98-5404 ________________________

D. C. Docket No. 97-00410 CV-UUB

EMPLOYERS INSURANCE OF WAUSAU, a Mutual Company, Plaintiff-Counter- Defendant-Appellant,

versus

BRIGHT METAL SPECIALTIES, INC., Defendant-Counter- Claimant, Cross- Claimant-Cross- Defendant-Appellee,

ROGERS CONSTRUCTION COMPANY, Defendant-Cross- Defendant-Cross- Claimant-Third-Party Plaintiff-Appellee.

__________________________________________________________________ _

BRIGHT METAL SPECIALTIES, INC., Plaintiff-Cross- Defendant-Appellee,

EMPLOYERS INSURANCE OF WAUSAU, a Mutual Company, Defendant-Cross- Defendant-Appellant,

ROGERS CONSTRUCTION COMPANY, Defendant-Cross- Claimant.

________________________

No. 98-5405 ________________________

D. C. Docket No. 97-00410-CV-UUB

EMPLOYERS INSURANCE OF WAUSAU, a Mutual Company,

Plaintiff-Counter- Defendant-Appellee,

BRIGHT METAL SPECIALTIES, INC., Defendant-Counter- Claimant-Cross- Claimant-Cross- Defendant-Appellee,

ROGERS CONSTRUCTION COMPANY, Defendant-Cross- Defendant-Cross-

2 Claimant-Third-Party Plaintiff-Appellant.

__________________________________________________________________ _

BRIGHT METAL SPECIALTIES, INC., Plaintiff-Cross- Defendant-Appellee,

Defendant-Cross- Defendant-Appellee,

ROGERS CONSTRUCTION COMPANY, Defendant-Cross- Claimant-Appellant.

Appeals from the United States District Court for the Southern District of Florida _________________________

(May 22, 2001)

Before EDMONDSON, FAY and GARWOOD*, Circuit Judges.

______________________ *Honorable Will L. Garwood, U.S. Circuit Judge for the Fifth Circuit, sitting by designation.

3 FAY, Circuit Judge:

Appellants Employers Insurance of Wausau (“Wausau”) and Rogers

Construction Company (“Rogers”) appeal the district court’s order compelling

arbitration of a claim asserted by Appellee Bright Metal Specialties, Inc. (“Bright”)

arising from a dispute on a Government construction project in Everglades

National Park. The district court held that Wausau, a Miller Act surety, became a

party to

Bright’s subcontract and the arbitration provision therein by virtue of Wausau’s

Takeover Agreement with the Government, Wausau’s Completion Contract with

its completion general contractor, Rogers Construction Co. (“Rogers”), and the

Ratification Agreement with Bright. Wausau argues that it did not contractually

agree to arbitrate with Bright, that it is not bound by the arbitration provision in

Bright’s subcontract, and that the Miller Act precludes arbitration of a claim

against a Miller Act surety such as Wausau. Rogers concedes that it is bound by

Bright’s subcontract, but contends that Bright’s claim is excluded from arbitration

pursuant to an arbitration exception in the subcontract. Moreover, Bright contests

our jurisdiction to hear this appeal. We conclude that the district court’s order was

an appealable “final decision” and affirm the arbitration order with respect to both

Wausau and Rogers.

4 I. Background

The parties agree to the following facts, most of which are established by

contract. On or about July 16, 1993, the National Park Service (“Government”)

contracted with A-1 Construction/BellincCo. (“A-1") for the repair of roofs to

certain buildings located in the Everglades National Park (the “Project”). Wausau,

as contract surety, provided performance and payment bonds for the Project on

behalf of A-1, its principal, in favor of the Government, as required by the Miller

Act, 40 U.S.C. § 270, et seq. In September 1993, A-1 subcontracted a portion of

the Project work to Bright pursuant to a written agreement (the “Subcontract” or

“Bright/A-1 Subcontract”) that included an arbitration clause.

The Government subsequently terminated A-1 for its default on the Project,

and called upon Wausau to complete the work pursuant to the performance bond.

On or about May 20, 1994, the Government and Wausau entered into a Takeover

Agreement by which Wausau agreed to complete the prime contract for A-1. On

or about May 26, 1994, Wausau entered into a Contract for Completion and

Construction (the “Completion Contract”) with Rogers whereby Rogers became

the completing contractor for all remaining work under the prime contract.

Pursuant to the Completion Contract, Wausau agreed to assign to Rogers all of

5 Wausau’s right, title and interest in and to A-1's executory subcontracts for the

performance of Project work.

On or about June 14, 1994, Bright and Wausau entered into a Ratification

Agreement which resolved Bright’s payment bond claim and ratified the Bright/A-

1Subcontract. First, Wausau and Bright resolved claims relating to monies due

Bright for work performed prior to A-1's termination. Second, Bright agreed to

complete the Subcontract and agreed to start work on the Project within seven (7)

days after request by Wausau, its agent, “or assigns, including any completion

contractor engaged by [Wausau].” Third, the Ratification Agreement provided that

Wausau could “assign its rights under the [A-1] subcontract and this agreement” to

a completion contractor. Finally, the parties agreed that Wausau would pay Bright

the remaining retainage, as fulfillment of its obligations to Bright, if work did not

begin within a specified period. Thereafter, Wausau required Bright to complete

the Subcontract with Rogers as the completion contractor. Bright resumed work

on the Project in June 1994.

6 In December 1994, Bright and Wausau settled a payment bond claim

previously submitted by Bright for work, labor and/or materials performed and/or

furnished under its Subcontract with A-1.1

Near completion of the Project, Bright sought additional compensation for

delays and damages caused by the Government. Ultimately, Bright submitted to

Rogers a request for “equitable adjustment” (“REA”) under the Subcontract. As

required by the contract documents, Rogers submitted the request to Wausau for

presentation by Wausau to the Government. Bright, Rogers, Wausau and the

Government met in Denver, Colorado in February 1996 to address Project claims,

including Bright’s REA. At the meeting, the Government offered to settle Bright’s

REA for approximately $10,000, less than two percent (2%) of the amount sought

by Bright. Bright declined the settlement offer and left the meeting. After Bright

left the meeting, Wausau accepted the Government’s settlement offer without

Bright’s approval or consent. Bright did not submit any further claims against the

Government, directly or through Rogers or Wausau, regarding the amounts sought

in the REA.

1 Pursuant to this settlement agreement, Wausau paid Bright the agreed amount in exchange for a release signed by Bright of all claims of any nature which Bright might have against the Government or against Wausau under its surety bond.

7 In January 1997, Bright filed a Demand for Arbitration with the American

Arbitration Association (“AAA”) for alleged breach of contract by Rogers and

Wausau. Bright claimed losses in the amount of $944,000 plus interest, attorney’s

fees and costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Express Financial Advisors, Inc. v. Makarewicz
122 F.3d 936 (Eleventh Circuit, 1997)
Scott v. Prudential Securities, Inc.
141 F.3d 1007 (Eleventh Circuit, 1998)
Randolph v. Green Tree Financial Corp.
178 F.3d 1149 (Eleventh Circuit, 1999)
Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Catlin v. United States
324 U.S. 229 (Supreme Court, 1945)
At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
Perry v. Thomas
482 U.S. 483 (Supreme Court, 1987)
Green Tree Financial Corp.-Alabama v. Randolph
531 U.S. 79 (Supreme Court, 2000)
Larry Bonner v. City of Prichard, Alabama
661 F.2d 1206 (Eleventh Circuit, 1981)
Green v. Ford Motor Credit Co.
246 S.E.2d 721 (Court of Appeals of Georgia, 1978)
United States v. Pool and Canfield, Inc.
778 F. Supp. 1088 (W.D. Missouri, 1991)
Port Largo Club, Inc. v. Warren
476 So. 2d 1330 (District Court of Appeal of Florida, 1985)
Woodrow Wilson Const. v. Mmr-Radon Constr.
635 So. 2d 758 (Louisiana Court of Appeal, 1994)
Travelers Indemnity Co. v. United States
35 Cont. Cas. Fed. 75,607 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Employers Insurance v. Bright Metal, Counsel Stack Legal Research, https://law.counselstack.com/opinion/employers-insurance-v-bright-metal-ca11-2001.