Bowings & Huber, LLC v. Hartford Fire Insurance Co.

CourtDistrict Court, D. Maryland
DecidedSeptember 27, 2022
Docket1:21-cv-03090
StatusUnknown

This text of Bowings & Huber, LLC v. Hartford Fire Insurance Co. (Bowings & Huber, LLC v. Hartford Fire Insurance Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bowings & Huber, LLC v. Hartford Fire Insurance Co., (D. Md. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

BOWINGS & HUBER LLC, *

Plaintiff, *

v. * Civil Action No. GLR-21-3090

HARTFORD FIRE INSURANCE CO., * et al., * Defendants. *** MEMORANDUM OPINION THIS MATTER is before the Court on Defendant Facility Engineering Services Corporation’s (“FESC”) Motion to Compel Arbitration and Dismiss, or, in the Alternative, Stay (ECF No. 16). The Motion is ripe for disposition, and no hearing is necessary. See Local Rule 105.6 (D.Md. 2021). For the reasons outlined below, the Court will grant the Motion to Stay and deny the Motion to Dismiss. I. BACKGROUND A. Factual Background In this contractual dispute, the United States Army Corps of Engineers contracted with Clark Construction Group, LLC to build an airplane hanger at Joint Base Andrews (the “JBA project”). (Compl. ¶ 6, ECF No. 1). Clark then subcontracted with Kirlin Design Build, LLC (“KDB”) for the mechanical scope of work for the JBA project. (Id. ¶ 7). KDB, in turn, subcontracted with FESC for the electrical controls work. (Id. ¶ 8). As required under KDB’s contract with FESC, FESC secured payment and performance bonds for FESC’s subcontractors’ and suppliers’ good-faith performance of the subcontract. (Id.). FESC secured these bonds through Defendant Hartford Fire Insurance Company (“Hartford”). (Id. ¶ 9). The bonds, issued on July 15, 2019, named

FESC as the Principal and KDB as the Obligee. (Id.). In sum, the bonds insured the “benefit of all persons supplying labor or material in the prosecution of work provided for in said Subcontract.” (Id.). On January 11, 2021, FESC entered into the Master Subcontractor Agreement (the “MSA”) with Plaintiff Bowings & Huber, LLC d/b/a BoMark (“BoMark”), further subcontracting electrical labor for the JBA project. (Id. ¶ 10). FESC issued a purchase order

to BoMark under the terms of the MSA on February 18, 2021. (Id.). BoMark supplied labor to FESC from March 1, 2021 to July 8, 2021 and sent FESC three invoices for payment. (Id. ¶ 11). FESC did not pay two of the invoices and told BoMark that it would not make the payments. (Id. ¶ 12). Thus, BoMark filed a claim with Hartford on the payment bond. (Id.).

On September 1, 2021, Hartford responded to BoMark’s claim for to request additional information. (Id.). Hartford acknowledged receiving the information on September 22, 2021, but Bomark never received a response regarding its request for payment. (Id.). B. Procedural History

On December 3, 2021, BoMark filed suit against Hartford for claims arising out of the payment bond furnished by Hartford for labor and materials on the JBA project. (Compl. at 1).1 BoMark makes two claims against Hartford: (1) a common law payment bond claim for the amounts owed for BoMark’s work on the JBA project under its purchase

order with FESC for $242,336.54, including pre- and post-judgment interest; and (2) a request for a declaratory judgment stating that BoMark is a valid claimant under the payment bond and has a valid claim and therefore Hartford is obligated to pay BoMark the monies with interest. (Id. ¶¶ 14–20). Hartford filed its Answer on January 18, 2022. (ECF No. 5). One week later, FESC filed a Motion to Intervene. (ECF Nos. 8–9). BoMark filed its Opposition on February 4, 2022. (ECF No. 12). This Court granted the Motion in part

and denied the Motion in part. (ECF No. 14). Specifically, the Court granted FESC’s intervention as to the subject litigation regarding the JBA project but denied intervention with respect to a separate project, the Kaiser Permanente Nova (“KP Nova”) project. 2 (Id.). After FESC formally entered this lawsuit as a Defendant, it filed a Motion to Compel Arbitration and Dismiss, or, Alternatively, Stay. (See Def.’s Mot. Compel

Arbitration & Dismiss Alternatively Stay [“Mot.”] at 1, ECF No. 16). FESC asserts that BoMark’s claims in the subject lawsuit are based on the work BoMark rendered to FESC under FESC and BoMark’s MSA, which must be resolved through arbitration under the terms of the MSA. (Id. ¶¶ 3–7). BoMark filed its Opposition on March 1, 2022, and FESC filed its Reply on March 9, 2022. (ECF Nos. 17–18).

1 Citations to exhibit page numbers refer to the pagination assigned by the Court’s Case Management/Electronic Case Files (“CM/ECF”) system. 2 As mentioned in the Court’s prior Order, the parties are currently litigating the KP Nova Project in the Circuit Court for Baltimore County, Case No. C-03-CV-22-140 (Circ.Ct.Md.). (ECF No. 14). II. DISCUSSION A. Standard of Review

1. Applicable Law The scope of the Federal Arbitration Act, 9 U.S.C. § 1 et seq. (“FAA”), is broad, encapsulating any arbitration provision “included in ‘a contract evidencing a transaction involving commerce.’” Rota-McLarty v. Santander Consumer USA, Inc., 700 F.3d 690, 697 (4th Cir. 2012) (quoting 9 U.S.C. § 2). Rather than basing its Motion on the FAA, FESC cites the Maryland Uniform Arbitration Act, Md. Code Ann., Cts. & Jud. Proc. § 3- 201 et seq. (“MUAA”). (See Def.’s Mem. Supp. Mot. Compel Arbitration & Dismiss Alternatively Stay [“Mem.”] at 2, ECF No. 16-1). Thus, the Court must first determine whether the FAA or the MUAA applies.

The arbitration agreement in FESC and BoMark’s MSA does not contain a choice- of-law provision. The only mention of applicable standards and rules provides that any controversy or breach “shall be settled by arbitration in accordance with the construction Industry Arbitration Rules of the American Arbitration Association.” (Master Subcontract Agreement [“MSA”] at 3, ECF No. 1-1). This incorporation does not provide insight into

the parties’ intent for the applicable law in potential arbitration. Further, in its Memorandum, FESC fails to explain why the MUAA applies. (See generally Mem.). This Court previously examined whether the FAA or MUAA applied in a similar dispute. See generally Crim v. Pepperidge Farm, Inc., 32 F.Supp.2d 326 (D.Md. 1999). There, the agreements did not include a choice-of-law provision. Id. at 328 n.2. The Court

ultimately applied the FAA “[b]ecause the agreements were between citizens of different states, and involved interstate commerce.” Id. Similarly here, the Court notes that the agreement regarding the construction of an airplane hangar implicates interstate commerce,

a point the parties do not appear to dispute. Accordingly, the Court will apply the FAA. 2. Motion to Compel Arbitration The FAA governs the enforceability of arbitration agreements and provides procedures for arbitrating and enforcing arbitration awards. Stone v. Wells Fargo Bank, N.A., 361 F.Supp.3d 539, 546 (D.Md. 2019). Federal substantive law applies to issues concerning arbitrability, and state-law contract principles govern the formation of

arbitration provisions. Novic v. Midland Funding, LLC, 271 F.Supp.3d 778, 782 (D.Md. 2017), vacated on other grounds sub nom., Novic v. Credit One Bank, Nat’l Ass’n, 757 F.App’x 263 (4th Cir. 2019). A party can compel arbitration under the FAA, and, if so, a court “has no choice but to grant [the motion] where a valid arbitration agreement exists and the issues in [the] case fall within its purview.” Stone, 361 F.Supp.3d at 547 (quoting

Adkins v. Lab. Ready, Inc., 303 F.3d 496, 500 (4th Cir. 2002)). “[A] court must ‘engage in a limited review to ensure that the dispute is arbitrable . . . .’” Id. (quoting Murray v. United Food & Com.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Levin v. Alms and Associates, Inc.
634 F.3d 260 (Fourth Circuit, 2011)
United States Ex Rel. Tanner v. Daco Construction, Inc.
38 F. Supp. 2d 1299 (N.D. Oklahoma, 1999)
Crim v. Pepperidge Farm, Inc.
32 F. Supp. 2d 326 (D. Maryland, 1999)
R.J. Griffin & Co. v. Beach Club II Homeowners Ass'n
384 F.3d 157 (Fourth Circuit, 2004)
Novic v. Midland Funding, LLC
271 F. Supp. 3d 778 (D. Maryland, 2017)
Stone v. Wells Fargo Bank, N.A.
361 F. Supp. 3d 539 (D. Maryland, 2019)
Parr v. State ex rel. Cockey
17 A. 1020 (Court of Appeals of Maryland, 1889)
In re Titanium Dioxide Antitrust Litigation
962 F. Supp. 2d 840 (D. Maryland, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Bowings & Huber, LLC v. Hartford Fire Insurance Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/bowings-huber-llc-v-hartford-fire-insurance-co-mdd-2022.