Loyal Order of Moose, Lodge v. International Fidelity Insurance Co.

797 P.2d 622, 1990 Alas. LEXIS 94
CourtAlaska Supreme Court
DecidedAugust 17, 1990
DocketS-2874
StatusPublished
Cited by34 cases

This text of 797 P.2d 622 (Loyal Order of Moose, Lodge v. International Fidelity Insurance Co.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Loyal Order of Moose, Lodge v. International Fidelity Insurance Co., 797 P.2d 622, 1990 Alas. LEXIS 94 (Ala. 1990).

Opinion

OPINION

RABINOWITZ, Justice.

The Moose Lodge (“Lodge”) appeals the superior court’s grants of summary judgment and attorney’s fees to International Fidelity Insurance (“IFI”) on the Lodge’s tort claim of bad faith inaction by IFI as surety on performance and payment bonds covering a construction contract between Darling Enterprises (“Darling”), as princi *623 pal, and the Lodge, as obligee. 1 We reverse.

I. FACTS.

In May 1983 the Moose Lodge accepted Darling Enterprises’ proposal for the “[tjurnkey construction” of a new facility in Fairbanks. The price was $559,500. Pursuant to the parties’ contract, for included additional consideration, Darling obtained performance and payment bonds from IFI naming Moose Lodge as “obli-gee.”

The contract provided, inter alia, that “the entire construction shall be done ... to the complete satisfaction” of the Lodge; that such construction would be “subject to inspection at all times and approval by any duly authorized agent for the owner and in accordance with the laws of the State of Alaska and local city ordinances”; and that “all ... materials shall be furnished ... and all ... labor shall be done and performed, in every respect, to the satisfaction of [the Lodge] on or before September 15, 1983, or within 120 calendar days.” Liquidated damages would accrue at $150 per day after September 15, and $300 per day after October 1, 1983. Darling accepted “the prices set forth in the proposal as full compensation for ... all the materials and labor which may be required ... in the prosecution and completion of the whole work.” 2 Specifically, the contract provided that

no claim for additional work or materials, not specifically herein provided, done or furnished by the CONTRACTOR, will be allowed by the OWNER[,] nor shall the CONTRACTOR do any work or furnish any material not ordered in writing by the OWNER_ And such work or materials which may be done or furnished by the CONTRACTOR without order first being given shall be at the said contractor[’]s own risk, cost and expense and he hereby covenants and agrees that without such written order he shall make no claim for compensation for work or materials so done or furnished.

A Contract Addendum clarified that “both the Governor and Secretary of the Moose Lodge are the only signatures that can authorize a change order and must be signed by them both to be in effect.” The contract further required that;

all disputed questions of fact which may arise from or relative to the performance or nonperformance of, or compliance or non-compliance with any of the terms or provisions of this agreement by either of the parties hereto, or to the amount of loss or damages suffered by either ... by reason of the non-performance of, or compliance or non-compliance with any of the terms or provisions of this agreement ... shall be referred to an impartial arbitration board. The board shall consist of three impartial members unrelated to the OWNER, CONTRACTOR, or members thereof for determination, and the decision by the board shall be final, binding, and conclusive upon all parties hereto ..... [T]he referring of all such questions to the board and the determination thereof by them shall be a condition precedent to the bringing or filing of any ... court proceeding involving the determination of any such question.

The performance and payment bonds each incorporated the contract by refer *624 ence. The performance bond further provided that:

Whenever Contractor shall be, and declared by Owner to be in default under the Contract, the Owner having performed Owner’s obligations thereunder, the Surety may promptly remedy the default or shall promptly
1) Complete the Contract in accordance with its terms and conditions, or
2) Obtain a bid or bids for completing the Contract in accordance with its terms and conditions, and upon such determination by Surety of the lowest responsible bidder, or, if the Owner elects, upon determination by the Owner and the Surety jointly of the lowest responsible bidder, arrange for a contract between such bidder and Owner, and make available as Work progresses ... sufficient balance of the contract price, but not exceeding, including other costs and damages for which the Surety may be liable hereunder, [$559,500.00]. 3

The payment bond provided that Darling and IFI

jointly and severally agree with [the Lodge] that every claimant [subcontractor] ... who has not been paid in full ... within ninety (90) days after the date of such claimant’s ... labor was done or performed, or materials were furnished ..., may sue on this bond for the use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due ..., and have execution thereon.

The payment bond further required each claimant to file any “suit or action” within one year of “the date on which [Darling] ceased Work on said Contract,” unless (and insofar) such limitation were prohibited by controlling law.

Darling substantially completed the project by year’s end 1983, 4 receiving all but $13,921 of the contract price. At that time, in IFI’s words, “Darling declined to finish a punch list of items until he had been paid for other additional items installed at Moose Lodge’s request.” This list itemized $58,250 in costs — an air handling system ($35,300), lift station ($14,750), and “utility changes” of carrier and sewer easement ($8,200). The Lodge refused to pay, and Darling did not finish the project. The parties dispute whether the Certificate of Occupancy issued by the city of Fairbanks in October 1983 (and a supplement certificate issued in November) signified completion of the project under the terms of the contract.

On January 30, 1984 the Lodge’s attorney notified Darling by letter (with copy to IFI) that “numerous defects and failures in completion are substantially interfering with [the Lodge’s] partial occupancy of the premises.” The letter described defects in the new facility’s insulation, hydrant, air and heat systems, and the absence of written mechanical plans, which a subcontractor had withheld for alleged nonpayment. Darling forwarded this letter to Corroon and Black, the agent through whom the bonds were purchased. Darling’s response neither accepted nor denied liability; Darling obtained counsel, who suggested a meeting. On April 11, 1984 counsels’ letters apparently crossed in the mail: Darling’s attorney requested more specific information on unfinished items, while the Lodge’s attorney, again with copy to IFI, noted the continued accrual of liquidated damages, the “passage of time and the absence of any response,” and the “threat to life and safety” posed by a boiler- Darling had installed in an alleged unsafe and illegal manner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alpha Energy v. GEC, LLC
Virgin Islands, 2024
Ennen v. Integon Indemnity Corp.
268 P.3d 277 (Alaska Supreme Court, 2012)
Seybert v. Cominco Alaska Exploration
182 P.3d 1079 (Alaska Supreme Court, 2008)
Boldt Co. v. Thomason Electrical
820 F. Supp. 2d 703 (D. South Carolina, 2007)
Colorado Structures, Inc. v. Insurance Co. of the West
161 Wash. 2d 577 (Washington Supreme Court, 2007)
DADELAND DEPOT. v. St. Paul Fire and Marine
945 So. 2d 1216 (Supreme Court of Florida, 2006)
O'Connor v. Star Insurance Co.
83 P.3d 1 (Alaska Supreme Court, 2003)
Blood v. Kenneth Murray Insurance, Inc.
68 P.3d 1251 (Alaska Supreme Court, 2003)
Masterclean, Inc. v. Star Insurance
556 S.E.2d 371 (Supreme Court of South Carolina, 2001)
Federal Insurance v. Maine Yankee Atomic Power Co.
183 F. Supp. 2d 76 (D. Maine, 2001)
Cates Construction, Inc. v. Talbot Partners
980 P.2d 407 (California Supreme Court, 1999)
United States Ex Rel. Tanner v. Daco Construction, Inc.
38 F. Supp. 2d 1299 (N.D. Oklahoma, 1999)
Associated Indemnity Corp. v. CAT Contracting, Inc.
964 S.W.2d 276 (Texas Supreme Court, 1998)
Transamerica Premier Insurance Co. v. Brighton School District 27J
940 P.2d 348 (Supreme Court of Colorado, 1997)
Brighton School District 27J v. Transamerica Premier Insurance Co.
923 P.2d 328 (Colorado Court of Appeals, 1996)
Municipality of Anchorage v. Gentile
922 P.2d 248 (Alaska Supreme Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
797 P.2d 622, 1990 Alas. LEXIS 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/loyal-order-of-moose-lodge-v-international-fidelity-insurance-co-alaska-1990.