United States ex rel. Brown Minneapolis Tank Co. v. Kinley Construction Co.

816 F. Supp. 2d 1139, 2011 U.S. Dist. LEXIS 101699, 2011 WL 3935650
CourtDistrict Court, D. New Mexico
DecidedSeptember 2, 2011
DocketNo. CIV 11-0291 JB/LFG
StatusPublished
Cited by6 cases

This text of 816 F. Supp. 2d 1139 (United States ex rel. Brown Minneapolis Tank Co. v. Kinley Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. New Mexico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Brown Minneapolis Tank Co. v. Kinley Construction Co., 816 F. Supp. 2d 1139, 2011 U.S. Dist. LEXIS 101699, 2011 WL 3935650 (D.N.M. 2011).

Opinion

MEMORANDUM OPINION AND ORDER

JAMES 0. BROWNING, District Judge.

THIS MATTER comes before the Court on the Defendants’ Motion to Dismiss or, in the Alternative, to Transfer Venue, filed May 18, 2011 (Doc. 16)(“Motion”). The Court held a hearing on July 27, 2011. The primary issue is whether, pursuant to the Miller Act, 40 U.S.C. §§ 3131-3134, the United States District Court for the District of New Mexico is the proper venue for Plaintiff Brown Minneapolis Tank Co. (“BMT Co.”) to bring this action. The Court finds that venue is appropriate, because the Miller Act’s venue provision requires that claims must be brought in the location where the contract was performed, and the construction was done in New Mexico. The Court therefore denies the Motion.

FACTUAL BACKGROUND

“The basic facts and procedural history are not in dispute.” Motion at 2. See Use Plaintiff Brown Minneapolis Tank Co.’s Response to Defendants’ Motion to Dismiss Or, in the Alternative, to Transfer Venue at 1, filed May 31, 2011 (Doc. 20)(“Response”)(“For the most part, the background facts which are relevant to this issue are not disputed, and the parties have stipulated to the following facts.... ”). In April 2009, Kinley Construction entered into contract number W912PP-09-C-0025 (“Prime Contract”) with the Department of the Army, U.S. Army Corps of Engineers, for the construction of, among other things, two fuel storage tanks and related facilities at Kirtland Air Force Base, located within Bernalillo County, State of New Mexico (the “Project”). Response ¶ 1, at 2. See Motion ¶ a, at 2. In connection with execution of the Prime Contract, Kinley Construction, as principal, and Defendant Travelers Casualty and Surety Company of America, as surety, executed payment bond number 105246436. See Response ¶ 2, at 2.

In September, 2009, Kinley Construction and BMT Co. entered into the Agreement [1142]*1142between Contractor and Subcontractor, Contract No. 10-001-01, filed May 18, 2011 (Doc. 16-l)(“the Subcontract”), under which BMT Co. agreed to build the fuel storage tanks required for the Project under the Prime Contract. Motion ¶ b, at 2; Response ¶ 3, at 2. According to Kinley Construction, under the terms of the Subcontract, BMT Co. was to complete fabricating the tanks no later than April 13, 2010. See Motion 1Ib, at 2; Subcontract ¶ 7, at 4; id. Ex. B. Pursuant to the Subcontract, BMT Co. performed labor and supplied materials which were incorporated into the work required by the Prime Contract. See Response ¶ 4, at 2.

Because of high wind conditions at the job site, one of the tanks collapsed in April, 2009. Kinley Construction alleges that BMT Co. negligently failed to adequately protect its work from weather damage; BMT Co. denies that it was negligent and alleges that it went far beyond industry standards in its efforts to secure the tank. See Motion ¶ c, at 2-3. BMT Co. rebuilt the tank. BMT Co. also designed and installed a wind protection system intended to protect the tank from further damage. In June, 2010, however, a second high wind event caused the tank to collapse a second time. See Motion ¶ d, at 3. The final completion of the Project was delayed due to the two tank collapses. A dispute has arisen between BMT Co. and Kinley Construction regarding whether BMT Co.’s performance was timely under the Subcontract. See Response ¶ 6, at 2. Kinley Construction has taken the position that BMT Co. is responsible for the costs Kelly incurred from the delays, which BMT Co. denies. See Motion ¶ e, at 3. BMT Co. has issued, and Kinley Construction has refused to pay, invoices for labor and materials furnished to and incorporated into the work required by the Prime Contract. See Response ¶ 5, at 2.

PROCEDURAL BACKGROUND

Kinley Construction filed suit against BMT Co. in the 67th Judicial District Court, Tarrant County, Texas on March 8, 2011. See Kinley Constr. Co. v. Brown Minneapolis Tank Co., No. 67-251478-11, Plaintiffs Original Petition (Tex.D.Ct. March 8, 2011)(Doc. 16-2)(the “Texas Action”). Kinley Construction brought breach of the contract, negligence, indemnity, and unjust enrichment claims based on BMT Co.’s performance under the Subcontract, alleging that BMT Co. was at fault for the collapse of the fuel tanks and liable to the ensuing delays and the $336,138.75 in costs Kinley Construction incurred as a result of the delays. On April 8, 2011, BMT Co. removed the Texas Action to the United States District Court for the Northern District of Texas. See Kinley Constr. Co. v. Brown Minneapolis Tank Co., No. CIV 11-0231-01, Notice of Removal (N.D.Tex. Apr. 8, 2011).

On April 6, 2011, BMT Co. filed its Complaint for Violation of the Miller Act, Claim on Payment Bond and Breach of Contract in this action. See Doc. 1 (“Complaint”). BMT Co. commenced this action within one year of the date on which it last performed labor or supplied materials for the work required by the Prime Contract. See Response ¶ 8, at 2. BMT Co. brings Miller Act claim against the Defendants, a breach of contract claim against Kinley Construction, and a claim for payment on the bond against Travelers. See Complaint Counts I — III, at 3-4. BMT Co. alleges that, “[wjhile Brown was prosecuting its work under the Subcontract, the construction site experienced weather events which — through no fault of Brown’s — resulted in collapses of the partially erected tanks.” Complaint ¶ 10, at 1. BMT Co. alleges that it completed all work it was obligated to do under the contract, and that Kinley Construction refuses to [1143]*1143pay the $74,402.00 balance that remains due under the contract.

On April 27, 2011, BMT Co. filed a motion to transfer the Texas Action to this Court, to be consolidated with this action. See Kinley Constr. Co. v. Brown Minneapolis Tank Co., No. CIV 11-0231-08, Defendant’s Motion to Transfer Venue (N.D.Tex. April 27, 2011)(“Motion to Transfer Venue”). Kinley Construction opposes the motion. See Kinley Constr. Co. v. Brown Minneapolis Tank Co., No. CIV 11-0231-19, Plaintiffs Response and Opposition to Defendant’s Motion to Transfer Venue (N.D.Tex. May 18, 2011).

The Defendants now move to dismiss or, in the alternative, to transfer venue to the Northern District of Texas. The Defendants assert that, when related cases are pending before two federal courts, the court in which the case was last filed may refuse to hear it if the eases raise substantially overlapping issues. They argue that this case involves duplicative or substantially similar issues as the Texas Action, and that the two cases should be resolved together. They further argue that, because the Texas Action was filed first, the Northern District of Texas is the appropriate venue for adjudication. The Defendants also contend that BMT Co.’s claims arise from the same transaction or occurrence, and therefore must be brought, if at all, as compulsory counterclaims in the Texas action under rule 13 of the Federal Rules of Civil Procedure.

On May 31, 2011, BMT Co. filed its Response. BMT Co. does not dispute that the facts in this case involve identical or substantially overlapping issues as the Texas Action. Indeed, BMT Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
816 F. Supp. 2d 1139, 2011 U.S. Dist. LEXIS 101699, 2011 WL 3935650, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-brown-minneapolis-tank-co-v-kinley-construction-co-nmd-2011.