D.A. Hill Co. v. Clevetrust Realty Investors

573 A.2d 1005, 524 Pa. 425, 1990 Pa. LEXIS 93
CourtSupreme Court of Pennsylvania
DecidedApril 25, 1990
Docket6 and 7 W.D. Appeal Dockets 1989
StatusPublished
Cited by57 cases

This text of 573 A.2d 1005 (D.A. Hill Co. v. Clevetrust Realty Investors) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D.A. Hill Co. v. Clevetrust Realty Investors, 573 A.2d 1005, 524 Pa. 425, 1990 Pa. LEXIS 93 (Pa. 1990).

Opinion

OPINION OF THE COURT

FLAHERTY, Justice.

The issue raised by these cases is whether subcontractors who have furnished services on a construction project, but who have not been paid for all of their work, can recover on an unjust enrichment theory against a lending institution which foreclosed on the project after the owner defaulted on the construction loan.

*427 On March 22, 1974 CleveTrust Realty Investors entered into a construction loan agreement with Edinboro Development Company, the owner, in the amount of $2,200,000 for the construction of a shopping mall in Erie County, Pennsylvania, to be known as the Edinboro Mall. The loan was secured by mortgage and note in which CleveTrust held the first lien on the property.

On the same date, Edinboro entered into a contract with Drakes Mills Development Company, which was to act as general contractor for the project. Appended to the contract was a cost estimate prepared by the general contractor in which the cost to build the mall was divided into forty-eight different categories. After construction began, Drakes Mills submitted a monthly application for payment based upon invoices it received from subcontractors for work performed the prior month. An architect employed by CleveTrust verified that the work described on the applications for payment was actually performed.

The monthly applications for payment were divided into the same forty-eight categories as appeared in the cost estimate, and the general contractor placed the subcontractors in one or more of these categories. The subcontractors were hired by Drakes Mills, the general contractor, and CleveTrust had no knowledge of who the subcontractors were or which of the forty-eight categories any of them had been placed in. The subcontractors all executed waivers of mechanics’ liens.

The payment process involved the subcontractor’s submission of invoices to the general contractor, the architect’s approval, submission to Edinboro, the owner, and then submission to CleveTrust. Upon receipt of the application for payment, Clevetrust wired the requested amount to a title company, which would insure that CleveTrust’s lien on the property was primary, and then the title company would disburse the money to Edinboro, which would pay Drakes Mills, the general contractor. Drakes Mills, in turn, would pay the subcontractors.

*428 The first eight applications for payment were paid in full. In November of 1974, however, less than eight months after the execution of the loan documents, Edinboro failed to make a mandatory interest payment on the loan. In accordance with its rights under the loan agreement, CleveTrust refused to disburse any additional funds. At the time of default, CleveTrust had disbursed $1,903,891.13, not including retainage, as requested in applications for payment one through eight. Five days after the default, the ninth application for payment was submitted to CleveTrust, which declined to pay.

The general contractor then communicated to the subcontractors Edinboro’s default and CleveTrust’s refusal to release additional funds. Thé subcontractors then ceased work, although appellee Felheim Roofing had already completed its work. In January, 1975, several subcontractors filed mechanics’ liens against Edinboro for labor and materials. A complaint was subsequently filed, and Edinboro’s motion for summary judgment was granted by the Court of Common Pleas of Erie County because of the waivers of mechanics’ liens executed by the subcontractors. Superior Court affirmed.

From November 1974 through February 1975, Edinboro continued in default, failing to make required interest payments. On February .19, 1975, CleveTrust began foreclosure proceedings on its first mortgage. On March 7, 1975, an involuntary bankruptcy petition was filed by Edinboro’s creditors and a receiver was appointed to operate the business. CleveTrust’s foreclosure suit was stayed by a temporary restraining order and the automatic stay provisions of the Bankruptcy Act. On August 25, 1975, the bankruptcy court lifted the stay and CleveTrust continued with its foreclosure action. CleveTrust foreclosed on the mall and purchased it at sheriff’s sale on December 12, 1975 for taxes and costs in the amount of $120,921.05.

Five years after CleveTrust purchased the mall, following Superior Court’s decision in Gee v. Eberle, 279 Pa.Super. 101, 420 A.2d 1050 (1980), Hill, one of the appellees herein, *429 filed a complaint in equity against CleveTrust alleging that CleveTrust had been unjustly enriched. Felheim and Erie Flexlume Sign Corporation, the other appellees in this action, filed a joint complaint on January 8, 1981.

CleveTrust responded to these complaints by answering that it had not been unjustly enriched, since the value of the mall was less than the amounts disbursed to the owner, and that even if it were enriched, any enrichment was not unjust, for CleveTrust advanced funds to the owner adequate to pay for the work performed by each subcontractor.

A jury trial was conducted on June 15-17, 1982, and the Court of Common Pleas of Erie County found that the subcontractors were entitled to rely on the $2,200,000 loan commitment to the owner and that since the full amount of the commitment had not been paid, each subcontractor was entitled to the full amount of its claim. Exceptions were taken, and the court en banc remanded for further consideration of whether CleveTrust had been unjustly enriched. Specifically, on remand the trial court was to consider whether sufficient funds were advanced to satisfy the claims of each subcontractor. 1

Upon remand, the trial court determined that the subcontractors were not entitled to rely on CleveTrust’s initial loan commitment since they received no assurances from CleveTrust itself regarding the disbursement of funds. The court held that the “as-is” value of the mall was greater *430 than the amount advanced by CleveTrust at the time of default and that CleveTrust was, therefore, enriched. Further, the court determined that CleveTrust was enriched, but not unjustly, where the advances made were in excess of the amount claimed by the subcontractors and no other subcontractor performed work under the line item in question, but that CleveTrust was unjustly enriched by the amount of retainage (10% of the amount invoiced and held back by CleveTrust) where the advances made were not in excess of the amount claimed by certain subcontractors. Accordingly, the trial court awarded appellees Hill and Felheim Roofing a portion of their claims, but determined that sufficient funds had been distributed to satisfy the claim of appellee Erie Flexlume Sign Corporation, and that Erie Flexlume, therefore, was not entitled to any recovery. 2

*431 An appeal was taken to Superior Court, which affirmed the trial court, with Judge Wieand dissenting 364 Pa.Super. 169, 527 A.2d 1008.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SDSP v. Attias, M.
Superior Court of Pennsylvania, 2023
SALVITTI v. LASCELLES
E.D. Pennsylvania, 2023
IQVIA INC. v. BRESKIN
E.D. Pennsylvania, 2023
Artisan Builders, Inc. v. Jang, S.
2022 Pa. Super. 36 (Superior Court of Pennsylvania, 2022)
Bel Air Carpet v. Korey Homes Bldg Grp
249 Md. App. 109 (Court of Special Appeals of Maryland, 2021)
HICKEY v. UNIVERSITY OF PITTSBURGH
W.D. Pennsylvania, 2021
Clark Office v. MCM Capital Partners
245 A.3d 186 (Court of Special Appeals of Maryland, 2021)
Karden Construction Svcs., Inc. v. D'Amico, B.
2019 Pa. Super. 279 (Superior Court of Pennsylvania, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
573 A.2d 1005, 524 Pa. 425, 1990 Pa. LEXIS 93, Counsel Stack Legal Research, https://law.counselstack.com/opinion/da-hill-co-v-clevetrust-realty-investors-pa-1990.