CNX MIDSTREAM DEVCO I, LP v. APPLIED CONSTRUCTION SOLUTIONS, INC.

CourtDistrict Court, W.D. Pennsylvania
DecidedSeptember 2, 2021
Docket2:20-cv-00290
StatusUnknown

This text of CNX MIDSTREAM DEVCO I, LP v. APPLIED CONSTRUCTION SOLUTIONS, INC. (CNX MIDSTREAM DEVCO I, LP v. APPLIED CONSTRUCTION SOLUTIONS, INC.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CNX MIDSTREAM DEVCO I, LP v. APPLIED CONSTRUCTION SOLUTIONS, INC., (W.D. Pa. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF PENNSYLVANIA

CNX MIDSTREAM DEVCO I LP, ) ) Civil Action No. 20-0290 Plaintiff, ) ) v. ) Magistrate Judge Lenihan ) APPLIED CONSTRUCTION SOLUTIONS, )

INC., ) ) ECF Nos. 45, 48, 51 Defendant. )

MEMORANDUM OPINION ON THE PARTIES’ MOTIONS FOR SUMMARY JUDGMENT

Presently before the Court are three Motions for Summary Judgment: one filed by CNX Midstream Devco I LP (“CNX” or “Plaintiff”) requesting partial summary judgment on grounds that “the Purchase Order between the parties is a time and materials contract with a price not to exceed (‘T&M NTE’)”, and two filed by Defendant Applied Construction Solutions, Inc. (“ACS” or “Defendant”) requesting summary judgment on grounds of either (a) the contractual absence/inapplicability of an NTE term or (b) unjust enrichment in the alternative. For the reasons discussed below, all motions will be denied.1

1 As CNX notes, “initial discovery in this matter was limited . . . to ‘whether the contract is time and materials or time and materials with costs not to exceed,’ and ‘issues of whether the contract contained a not to exceed price term or what form of contract arose between the parties.’”). ECF No. 54 at 9 (citing ECF Nos. 35 and 41). Plaintiff’s substantive Response to the Motion for Summary Judgment on grounds of unjust enrichment was filed at ECF No. 55.

The Court observes ACS’ contention - within certain filings made with regarding to the parties’ motions for summary judgment - that its Requests for Admission directed to CNX were admitted by operation of law. It also notes CNX’s response noting, for example, this Court’s prior directions regarding the scope and time frames of I. FACTS Throughout October and November 2018, CNX Midstream Devco I LP (“CNX”, “Plaintiff” or “Company”) solicited bids for the construction of the Morris Natural Gas Compressor Station (“Morris Project”). On November 5, 2018, CNX posted a document (“NTE Q&A Document”), for all bidders to see, containing questions from bidders (without origination

information) along with answers to those questions. The relevant questions and answers are as follows: [Question:] Can you please clarify if this contract will be T&M or a Lump Sum contract? [Answer:] T&M [Question:] Do you want all [Schedule of Value] lines as T&M Not to Exceed? [Answer:] Yes [Question:] If it is T&M, is this T&M not to exceed amount based upon your submitted lump sum budget? [Answer:] Yes.

ECF No. 47 at 334. 2 One day after the Q&A document was posted (November 6, 2018), ACS submitted an initial bid. ECF No. 49 at 3. After some correspondence, ACS submitted,at CNX’s request, a revised bid (“Revised Bid”) that removed various “contingencies” in order to provide CNX a lower price as requested. ECF No. 49 at 4. The Revised Bid contained the following language: Our Original proposal of $14,108,760.00 . . . was a number that sought to mitigate all concerns . . . and other unforeseen issues. Essentially, we included contingencies and risk against tie-in delays and subsequent schedule delays and slippages. We included a contingency for inclement weather, snow or rain. Our goal was to take care of any makeup days. Basically, we tried to cover all possible issues to avoid any addition [sic] cost to CNX.

initial, limited discovery and motions; the parties’ discovery exchanges; the strong preferability of decisions on the merits; and other procedures under Fed. R. Civ. P. 36. The Court is in general accord with CNX’s response and deems it unnecessary to address this contention further in ruling on the motions before it. See ECF No. 54 at 6-9; see also ECF No. 64.

2 The documents appended with ECF No. 47 are not designated as 47-1, 47-2 etc., so the PDF’s running page number is designated. When asked we responded that our number was a Plus Minus 10% Number and after further review of the documents that were provided since the bid due day. That statement is true still. After reviewing the documents, we feel we have a viable number that provides a budget to CNX that they can be used [sic] for budgeting purposes. It allows for construction activities, weather delays, equipment and material delays, schedule slips regarding tie ins. If ACS removes the 10% contingency our number is $12,826,145.50 and obviously removes the mitigation controls mentioned above. Also when removing delays related to tie ins included our number the total further reduces. ACS management has had several rounds of discussion and feel that with in depth planning, and holding agreed upon dates for equipment & tie-ins, our number would be closer to $11.5 million than to $12 million. Obviously at this level any change or deviation from scope as it stands now, or schedule would be addressed very transparently between ACS and CNX. ECF No. 59-1 at 62-63. CNX then awarded the contract to ACS, and in early December, CNX electronically issued a purchase order (“Purchase Order”) to ACS through their electronic system, “HUBWOO”. ECF No. 53 at ¶¶ 9, 10. Article 2 of the Purchase Order incorporates about 150 documents by reference, including both ACS’s Revised Bid and the NTE Q&A Document. ECF No. 48-1 at 3. ACS acknowledged the Purchase Order, but there are no signed copies.3 The project designs were incomplete at the time that ACS was awarded the contract and were not finalized until seven months after the bid was accepted. ECF No. 49 at 11. During the course of construction, ACS submitted requests for Change Orders, and the parties kept track of the work that was approved in these orders in a “Not in Contract Log.” (ECF No. 47 at 337–38. Based on the second page adding the totals, ACS calculated $3,554,977.74 in out-of-scope work, and CNX calculated $2,807,312.13; this brought the total contract price to $15,225,857.13 in CNX’s view and $15,973,522.74 in ACS’s view. ECF No. 47 at 338. ACS

3 ACS asserts that it “checked a box” acknowledging the Purchase Order, but disputes that this was true acceptance, instead now questioning who checked the box and whether that person had the power to bind ACS. ECF No. 49 at 5; ECF No. 60 at ¶ 11. The Purchase Order provides that the method of acceptance must be saving the Purchase Order and sending it back through HUBWOO. The Court notes the parties’ performance to date, the litigation motions and rulings to date, and that is denying all motions for summary judgment presently before it. invoiced a total of $19,578,615.76 based on certain costs incurred or price increases, and CNX refused to pay any amount over $15,225,857.13. ECF No. 52 at 9. CNX brought suit in January 2020 “seeking declaratory relief to prevent ACS from exercising its statutory rights to place a lien on the Morris Station.” ECF No. 49 at 1. As noted, there are three Motions for Summary Judgment before the Court. The first was filed by CNX on

the issue of whether there is a T&M NTE contract. The other two motions were filed by ACS, first asking the court to hold that the contract does not contain an NTE term, and the second asking the court to hold that ACS is entitled to compensation under a theory of unjust enrichment in the alternative. I. LEGAL STANDARD Summary judgment is appropriate if, drawing all inferences in favor of the nonmoving party, the pleadings, documents, electronically stored information, depositions, answers to interrogatories and admissions on file, together with any affidavits or declarations, show “that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a

matter of law.” Fed. R. Civ. P. 56 (a), (c).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Sovereign Bank v. BJ's Wholesale Club, Inc.
533 F.3d 162 (Third Circuit, 2008)
Great American Insurance v. Norwin School District
544 F.3d 229 (Third Circuit, 2008)
Greene v. Oliver Realty, Inc.
526 A.2d 1192 (Supreme Court of Pennsylvania, 1987)
Allied Fire & Safety Equipment Co. v. Dick Enterprises, Inc.
972 F. Supp. 922 (E.D. Pennsylvania, 1997)
Meehan v. Cheltenham Township
189 A.2d 593 (Supreme Court of Pennsylvania, 1963)
Hutchison v. Sunbeam Coal Corp.
519 A.2d 385 (Supreme Court of Pennsylvania, 1986)
Capek v. Devito
767 A.2d 1047 (Supreme Court of Pennsylvania, 2001)
Burns Manufacturing Co., Inc. v. Boehm
356 A.2d 763 (Supreme Court of Pennsylvania, 1976)
Atlantic Richfield Co. v. Razumic
390 A.2d 736 (Supreme Court of Pennsylvania, 1978)
Murphy v. Duquesne University of Holy Ghost
777 A.2d 418 (Supreme Court of Pennsylvania, 2001)
Lauren W. Ex Rel. Jean W. v. Deflaminis
480 F.3d 259 (Third Circuit, 2007)
Trinity Industries Inc v. Greenlease Holding Co
903 F.3d 333 (Third Circuit, 2018)
Adirondack Classic Design, Inc. v. Farrell
2020 NY Slip Op 2298 (Appellate Division of the Supreme Court of New York, 2020)
Braun v. Wal-Mart Stores, Inc.
24 A.3d 875 (Superior Court of Pennsylvania, 2011)
Roethlein v. Portnoff Law Associates, Ltd.
81 A.3d 816 (Supreme Court of Pennsylvania, 2013)
Vantage Learning (USA), LLC v. Edgenuity, Inc.
246 F. Supp. 3d 1097 (E.D. Pennsylvania, 2017)
Tallmadge Bros. v. Iroquois Gas Transmission System, L.P.
746 A.2d 1277 (Supreme Court of Connecticut, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
CNX MIDSTREAM DEVCO I, LP v. APPLIED CONSTRUCTION SOLUTIONS, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cnx-midstream-devco-i-lp-v-applied-construction-solutions-inc-pawd-2021.