Adirondack Classic Design, Inc. v. Farrell

2020 NY Slip Op 2298, 182 A.D.3d 809, 122 N.Y.S.3d 790
CourtAppellate Division of the Supreme Court of the State of New York
DecidedApril 16, 2020
Docket527434
StatusPublished
Cited by19 cases

This text of 2020 NY Slip Op 2298 (Adirondack Classic Design, Inc. v. Farrell) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adirondack Classic Design, Inc. v. Farrell, 2020 NY Slip Op 2298, 182 A.D.3d 809, 122 N.Y.S.3d 790 (N.Y. Ct. App. 2020).

Opinion

Adirondack Classic Design, Inc. v Farrell (2020 NY Slip Op 02298)
Adirondack Classic Design, Inc. v Farrell
2020 NY Slip Op 02298
Decided on April 16, 2020
Appellate Division, Third Department
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
This opinion is uncorrected and subject to revision before publication in the Official Reports.


Decided and Entered: April 16, 2020

527434

[*1]Adirondack Classic Design, Inc., Respondent,

v

Harry Farrell, Appellant.


Calendar Date: February 18, 2020
Before: Egan Jr., J.P., Lynch, Mulvey, Devine and Colangelo, JJ.

Hurwitz & Fine, PC, Lake Placid (Earl K. Cantwell of counsel), for appellant.

Fischer, Bessette, Muldowney & McArdle, LLP, Malone (John J. Muldowney of counsel), for respondent.



Mulvey, J.

Appeal from a judgment of the Supreme Court (Ellis, J.), entered August 28, 2018 in Franklin County, upon a verdict rendered in favor of plaintiff.

Beginning in 2013, defendant started working with Nils Luderowski, an architect, to design a great camp for defendant's property located on Upper Saranac Lake. Luderowski presented defendant with two different project delivery methods: the design/bid/build method — in which the owner and architect develop complete design and work drawings, present them to potential contractors for bids, then select a contractor and begin building — and the fast track method — in which preliminary designs and drawings are prepared and construction begins based thereon, with the design concept developing as the construction progresses. Defendant selected the fast track method, which permitted construction to begin more quickly. In February 2014, defendant stated that his budget would be $1.1 million to obtain an enclosed structure and whatever was necessary to obtain a certificate of occupancy, not a completed house. Plaintiff indicated that this figure appeared to be a fairly accurate baseline and the costs would be honed as the design developed. The parties then entered into a contract for plaintiff to demolish the existing structure on the property and build a new camp. They signed a written contract stating that the construction would be completed for a stipulated sum, but a blank was left where the sum should be listed. The parties conceded at trial that they proceeded on a time and materials basis, rather than a stipulated sum basis. Plaintiff billed defendant twice monthly, sending invoices and billing worksheets, and defendant made regular payments. In the spring of 2015, defendant applied for and received a construction loan from a bank, which required completion to specifications, not just the minimum required for a certificate of occupancy. In September 2015, a certificate of occupancy was issued and the bank approved release of the final funds from the construction loan. The house was not complete, but the construction was much more than the minimum required for a certificate of occupancy, with many interior finishes added. Although defendant had paid approximately $1.7 million, plaintiff sent an invoice for $169,646.29 for work that had been done. Defendant refused to pay, and plaintiff ceased construction.

Plaintiff commenced this action asserting a breach of contract. Defendant asserted various counterclaims, including that plaintiff breached their contract. At trial, Supreme Court dismissed most of defendant's other counterclaims. The jury rendered a verdict in favor of plaintiff, finding that defendant breached the contract and awarding damages in the amount of $169,646.29. Defendant appeals from the judgment entered thereon.

Supreme Court properly denied defendant's motion for a directed verdict. "A trial court may grant a CPLR 4401 motion for judgment as a matter of law only when, viewing the evidence in the light most favorable to the nonmoving party and affording [it] the benefit of every inference, there is no rational process by which a jury could find in favor of the nonmoving party" (D.Y. v Catskill Regional Med. Ctr., 156 AD3d 1003, 1005 [2017] [citations omitted]; see O'Connor v Shultz, 166 AD3d 1104, 1104 [2018]). To recover for a breach of contract, a party must establish the existence of a contract, the party's own performance under the contract, the other party's breach of its contractual obligations, and damages resulting from the breach (see Carroll v Rondout Yacht Basin, Inc., 162 AD3d 1150, 1151 [2018], appeal and lv dismissed 32 NY3d 1035 [2018]; WFE Ventures, Inc. v Mills, 139 AD3d 1157, 1160 [2016]). Plaintiff offered testimony from, among others, its co-owners, Luderowski, and Paul Carr, a construction expert, as well as emails, invoices and photographs of the construction at different stages. Viewed in a light most favorable to plaintiff, the evidence would support a finding that the parties entered into a contract, plaintiff performed by constructing a building according to the design approved by Luderowski and defendant, and defendant breached the contract by failing to pay the final invoice amount. Contrary to defendant's argument that plaintiff failed to prove that it provided "workmanlike" quality, plaintiff's evidence supports an inference that it performed in a satisfactory manner. Accordingly, the court properly denied defendant's motion for a directed verdict.

We will not disturb the jury's verdict finding that defendant breached the parties' contract but plaintiff did not. "A verdict may be set aside as against the weight of the evidence if the evidence so preponderated in favor of the [losing party] that the verdict could not have been reached on any fair interpretation of the evidence" (Kennedy v Nimons, 178 AD3d 1302, 1303 [2019] [internal quotation marks, ellipsis, brackets and citations omitted]). "It is not enough to show that a different verdict would be reasonable since the jury's verdict will be accorded deference if credible evidence exists to support its interpretation" (Maksuta v Heitzman, 165 AD3d 1550, 1551 [2018] [internal quotation marks and citations omitted]).

Initially, we reject defendant's argument that the construction contract was a stipulated sum contract. Defendant selected the fast track method to allow construction to begin quickly, so plaintiff began billing on a time and materials basis — in which the contractor bills periodically for labor, materials, subcontractor costs and a mark-up for overhead. Although defendant attempts to hold plaintiff to the terms of the written construction contract, evidence demonstrated that the parties signed that document with a blank left for the fixed price, originally contemplating that they would convert the contract into a stipulated sum contract once the design development process was done, but it was never converted because no final working drawings were ever completed. At trial, the parties agreed, and defendant conceded, that this was a time and materials contract (compare Birk Iron Works v Van Tulco, Inc., 178 AD2d 137, 137-138 [1991], lv denied 79 NY2d 975 [1992]). "[B]ecause the parties had agreed to proceed on a time and materials basis," there was no fixed price and the original estimates were not determinative or binding (CIR Elec. Constr. Corp. v Black Cr. Integrated Sys. Corp., 8 AD3d 999, 1000 [2004]).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tatum v. Fairstead Affordable LLC
Court of Chancery of Delaware, 2025
Archer v. Parlman
2025 NY Slip Op 01145 (Appellate Division of the Supreme Court of New York, 2025)
GCM Prime, LLC v. MM Dynamic of NY, Inc.
2024 NY Slip Op 51678(U) (New York Supreme Court, Albany County, 2024)
Gb-sp Holdings LLC v. Wayne R. Walker
Court of Chancery of Delaware, 2024
State of New York v. Oren-Pines
2024 NY Slip Op 50958(U) (New York Supreme Court, Albany County, 2024)
U.W. Marx, Inc. v. Dorrough Constr., Inc.
2024 NY Slip Op 30966(U) (New York Supreme Court, Saratoga County, 2024)
Rogers v. NYCM
2023 NY Slip Op 06778 (Appellate Division of the Supreme Court of New York, 2023)
White Knight Constr. Contrs., LLC v. Haugh
189 N.Y.S.3d 792 (Appellate Division of the Supreme Court of New York, 2023)
Carroll v. Rondout Yacht Basin, Inc.
187 N.Y.S.3d 854 (Appellate Division of the Supreme Court of New York, 2023)
Please Me, LLC v. State of New York
215 A.D.3d 1149 (Appellate Division of the Supreme Court of New York, 2023)
State of New York v. Oren-Pines
New York Supreme Court, 2023
Ironwoods Troy, LLC v. Optigolf Troy, LLC
204 A.D.3d 1130 (Appellate Division of the Supreme Court of New York, 2022)
Suchow v. Suchow
2021 NY Slip Op 07041 (Appellate Division of the Supreme Court of New York, 2021)
Davis v. Zeh
2021 NY Slip Op 06905 (Appellate Division of the Supreme Court of New York, 2021)
Edw Drywall Constr., LLC v. U.W. Marx, Inc.
2020 NY Slip Op 07255 (Appellate Division of the Supreme Court of New York, 2020)
Lapenna Contr., Ltd. v. Mullen
2020 NY Slip Op 06183 (Appellate Division of the Supreme Court of New York, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2020 NY Slip Op 2298, 182 A.D.3d 809, 122 N.Y.S.3d 790, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adirondack-classic-design-inc-v-farrell-nyappdiv-2020.