U.W. Marx, Inc. v. Dorrough Constr., Inc.

2024 NY Slip Op 30966(U)
New York Supreme Court, Saratoga County·Decided March 26, 2024·Unpublished

Opinion

U.W. Marx, Inc. v Dorrough Constr., Inc.

2024 NY Slip Op 30966(U)

March 26, 2024

Supreme Court, Saratoga County Docket Number: Index No. EF20194437 Judge: Richard A. Kupferman Cases posted with a "30000" identifier, i.e., 2013 NY Slip Op 30001(U), are republished from various New York State and local government sources, including the New York State Unified Court System's eCourts Service. This opinion is uncorrected and not selected for official publication.

SUPREME COURT OF THE STATE OF NEW YORK COUNTY OF SARATOGA

U.W. MARX, INC., Plaintiff, DECISION, JUDGMENT, & ORDER AFTER TRIAL

-against- Index# EF20194437

DORROUGH CONSTRUCTION, INC. and WILLIAM DORROUGH,

Defendants.

Appearances:

John P. Mastropietro, Esq. Mastropietro Law Group PLLC 63 Franklin Street Saratoga Springs, New York 12866 Attorneys for Plaintiff

Frank M. Putorti, Esq. Frank M. Putorti, Jr., P.C. 1338 Union Street Schenectady, New York 12308 Attorneys for Defendants

KUPFERMAN, J., The plaintiff contractor ("Marx") hired the defendant subcontractor ("Dorrough") to frame

a 140,000 square foot apartment building in Rensselaer, New York. Dorrough performed work on the project for several months until a dispute arose over payment, resulting in the souring of the ·

parties' relationship and Marx hiring another subcontractor to complete the work. Both sides are now seeking to recover monetary damages against the other for breach of contract. Dorrough alternatively seeks to recover in quantum meruit and unjust enrichment for the value of additional services performed beyond the original scope of work.

In September 2023, the Court conducted a three-day non-jury trial. The Court heard testimony from three witnesses and received numerous exhibits into evidence. A summary of the credible trial evidence is set forth below.

Summary of the Credible Trial Evidence The parties' contract is dated August 31, 201 7. Marx prepared the document using a standard subcontract agreement form (AJA Document A401-2007). The contract price was for $773,354 and included all the wood framing and sheathing work outlined in the scope of work (Contract, at§§ 8.1, 10.1). This scope of work expressly excluded items required for the project such as anchor bolts, a tie system, wood framing material, and certain strapping/bracing at shear walls (Contract, at § 8.1; Trial Transcript, at pp. 10-11, 25, 81-82). The contract further provided a procedure for Marx to make changes in the work and required Dorrough to submit a claim for additional costs or an extension of time (Contract, at Article 5; see also Contract, at§§ 9.6, 9.7). The general conditions of AJA Document A201-2007 ("General Conditions") also applied to the contract, except to the extent thata conflict existed (Contract, at§ 1.2).

The contract specified that time was "of the essence" and attached a work schedule as an exhibit (Contract, at§ 9.4 & Exhibit M). Based on the contract schedule, the framing work was expected to begin on July 25, 2017 (before the date of the contract) and continue for approximately 4.5 months (Contract, at§ 9.4 & Exhibit M). 1 The starting date, however, was delayed for several months based on a problem with the foundation, which was caused by another subcontractor. Dorrough therefore could not commence work until November 13, 2017.

1 Under the contract, the building framing was scheduled to occur from July 25, 2017 to October 17, 2017 (Area 1) and from August 10, 2017 to December 6, 2017 (Area 2) (Contract, Exhibit M).

Marx does not attribute any of the initial delay to Dorrough. Marx, however, expected that the durations in the contract work schedule would remain the same and that only the starting/ending dates would change. On November 29, 2017, Marx's project manager emailed a revised work schedule, explaining that the dates were "hard and fast" and that "we need to do everything we can to meet them" (Exhibit J-24). 2 Dorrough, in contrast, did not share this same expectation. The parties' contract was never modified to include a revised schedule. The parties also conducted weekly meetings to discuss scheduling issues, and they further updated the anticipated deadlines throughout the project as circumstances changed. Marx, for example, required Dorrough to perform extra work during the project, including additional framing for 3,340 square feet, tie downs, strapping, and anchor bolts. 3 Dorrough also encountered several circumstances outside its control that delayed its performance. Among other things, the slab and foundation were not completed when Dorrough started framing; the foundation was larger than planned; the trusses had to be rebuilt; the steel was not timely installed; some of the steel had to be refabricated; the schedule failed to account for the winter weather; design changes were made; and Marx failed to make arrangements for someone else to complete necessary work that was expressly excluded from the parties' contract (i.e., tie downs, strapping, and anchor bolts).

By February 21, 2018, the parties disconnect on the timing of the work manifested itself.

On that date, Marx issued a notice of intent to supplement Dorrough's work force pursuant to

2 Under the revised schedule, the building framing was scheduled to occur from December 1, 2017 to May 11, 2018 (Area 1) and from.December 6, 2017 to July 27, 2018 (Area 2). 3 No dispute exists that the tie downs, strapping, and anchor bolts were out-of-scope work; that Marx directed Dorrough to perform it; that Dorrough performed the work; and that the additional 3,340 square feet of framing constituted extra work (Trial Transcript, at pp. 74, 77-78, 86, 109- 111, 192, 331-332, 379-381, 418, 559-560).

Section 3.4.1 of the contract (Exhibit J-2; J-34). The notice asserted generally that Dorrough had failed to prosecute its work and that Marx.would supplement the forces on February 23, 2018 if Dorrough did not "sufficiently progress ... the wood framing installation."

Dorrough's owner testified that he was caught off guard by the February notice. This was the first time that Marx had informed Dorrough that it was behind schedule. Dorrough's owner believed that a disconnect existed between Marx's management and its field workers. In response to the notice, Dorrough's owner added additional workers to satisfy Marx and discussed the reasons for the delay. As a result, Marx elected not to supplement Dorrough's work force.

In May 2018, Marx again took issue with the progress of the work. By email dated May 18, 2018, Marx's project manager emailed its operations manager a list of alleged deficiencies, which included both in-scope and out-of-scope work (Exhibit J-47). Marx's project manager explained in his email that they have been asking Dorrough to complete some of these items for an.extended period of time and other. items were "simply things that need[ed] to be completed for · [Dorrough's] scope to be complete" (Exhibit J-47).

By notice dated May 30, 2018, Marx issued another notice of intent to supplement Dorrough's work force due to Dorrough's alleged "failure to timely prosecute its work" (Exhibit J-3). The notice set forth the list of the specific items that Marx considered as incomplete, including the out-of-scope work that Dorrough had been performing (i.e., tie downs and strapping). In response to the list, Dorrough's owner emailed Marx's project manager, explaining that he was making his "best effort to finish all things [they] spoke about" and that "hopefully [they] both [would] fulfill [their] agreement to do all available work and to pay [him] for such work" (Exhibit J-50). Dorrough then diverted its attention to the items on Marx's list and again made sure that sufficient workers were available to perform available tasks. As a result, Marx again elected to

not supplement Dorrough's work force and further paid Dorrough for all the in-scope work it had performed during that pay period (Trial Transcript, at pp. 97,468; Exhibit J-14).

Free access — add to your briefcase to read the full text and ask questions with AI

U.W. Marx, Inc. v. Dorrough Constr., Inc., 2024 NY Slip Op 30966(U) (N.Y. Super. Ct. 2024).

2024 NY Slip Op 30966(U) (U.W. Marx, Inc. v. Dorrough Constr., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

U.W. Marx, Inc. v. Koko Contracting, Inc.
124 A.D.3d 1121 (Appellate Division of the Supreme Court of New York, 2015)
Johnson v. Robertson
131 A.D.3d 670 (Appellate Division of the Supreme Court of New York, 2015)
Smith v. . Wetmore
60 N.E. 419 (New York Court of Appeals, 1901)
Adirondack Classic Design, Inc. v. Farrell
2020 NY Slip Op 2298 (Appellate Division of the Supreme Court of New York, 2020)
Saeteros v. Seven Up Realty, LLC
2020 NY Slip Op 05836 (Appellate Division of the Supreme Court of New York, 2020)
Walter D. Watson & Co. v. Graves Elevator Co.
202 A.D. 10 (Appellate Division of the Supreme Court of New York, 1922)
Hadden v. Consolidated Edison Co.
312 N.E.2d 445 (New York Court of Appeals, 1974)
Schenectady Steel Co. v. Bruno Trimpoli General Construction Co.
316 N.E.2d 875 (New York Court of Appeals, 1974)
Norberto & Sons, Inc. v. County of Nassau
16 A.D.3d 642 (Appellate Division of the Supreme Court of New York, 2005)
Paul F. Vitale, Inc. v. Parker's Grille, Inc.
23 A.D.3d 1147 (Appellate Division of the Supreme Court of New York, 2005)
City of New York v. State
27 A.D.3d 1 (Appellate Division of the Supreme Court of New York, 2005)
O'Connor v. Sleasman
37 A.D.3d 954 (Appellate Division of the Supreme Court of New York, 2007)
Walter Sign Corp. v. State
31 A.D.2d 729 (Appellate Division of the Supreme Court of New York, 1968)
Alpine Courts, Inc. v. Wiedermann
34 A.D.2d 951 (Appellate Division of the Supreme Court of New York, 1970)
Rusciano Construction Corp. v. State
37 A.D.2d 745 (Appellate Division of the Supreme Court of New York, 1971)
Farrell Heating, Plumbing, Air Conditioning Contractors, Inc. v. Facilities Development and Improvement Corp.
68 A.D.2d 958 (Appellate Division of the Supreme Court of New York, 1979)
Janowitz Bros. Venture v. 25-30 120th Street Queens Corp.
75 A.D.2d 203 (Appellate Division of the Supreme Court of New York, 1980)
Michael G. Buck & Son Construction Corp. v. Poncell Construction Co.
217 A.D.2d 925 (Appellate Division of the Supreme Court of New York, 1995)
Merritt Meridian Construction Corp. v. Old Country Iron Works, Inc.
229 A.D.2d 661 (Appellate Division of the Supreme Court of New York, 1996)
Tridee Associates, Inc. v. New York City School Construction Authority
292 A.D.2d 444 (Appellate Division of the Supreme Court of New York, 2002)