CIGNEX Datamatics Inc v. LAM Research Corp

CourtCourt of Appeals for the Third Circuit
DecidedSeptember 27, 2021
Docket20-2121
StatusUnpublished

This text of CIGNEX Datamatics Inc v. LAM Research Corp (CIGNEX Datamatics Inc v. LAM Research Corp) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CIGNEX Datamatics Inc v. LAM Research Corp, (3d Cir. 2021).

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _____________

No. 20-2121 _____________

CIGNEX DATAMATICS, INC.

v.

LAM RESEARCH CORPORATION, Appellant _____________

On Appeal from the United States District Court for the District of Delaware (D.C. No. 1:17-cv-00320) District Judge: Maryellen Noreika _____________

Submitted Pursuant to Third Circuit L.A.R. 34.1(a) September 20, 2021 _____________

Before: CHAGARES, HARDIMAN, and MATEY, Circuit Judges.

(Filed: September 27, 2021)

_____________________

OPINION* _____________________

* This disposition is not an opinion of the full Court and pursuant to I.O.P. 5.7 does not constitute binding precedent. CHAGARES, Circuit Judge.

Defendant-appellant Lam Research Corporation appeals from the District Court’s

judgment following a bench trial in favor of plaintiff-appellee CIGNEX Datamatics, Inc.

(“Cignex”) and against Lam on its counterclaims. For the reasons we explain below, we

will affirm.

I.

Because we write only for the parties, our summary of the facts is brief. Lam

provides equipment to semiconductor manufacturers. It uses its MyLam.com document

database to support its customers over the internet. In 2014, Lam began searching for a

vendor to upgrade the MyLam website. It soon selected Cignex, an open-source software

consulting company.

On October 28, 2014, Cignex and Lam entered into a Master Services Agreement

(the “MSA”). The MSA was a form contract that provided broadly for the “services that

[Cignex would] perform and the fees which [Lam would pay] in return.” Appendix

(“App.”) 155. More specifically, it provided that “[Cignex] shall render such services as

may be necessary to complete in a professional manner the project described as follows:

Software integration, and [proof of concept], for MyLam/PK Redesign Project.” App.

159. Lam further agreed to pay Cignex for “all undisputed [Cignex] invoices within

thirty . . . days” from the date the invoice was received. App. 155. Finally, the MSA had

an integration clause incorporating all exhibits and future written modifications.

Cignex successfully completed its proof of concept for the MyLam project after

the parties signed the MSA. The parties then executed a second statement of work

2 (“SOW 2”) that laid out the various tasks Cignex would need to perform for the project.

SOW 2 specified that its “Terms & Conditions” were “Time and Material,” App. 179,

contained “[t]ime and [m]aterials” staffing and cost estimates based on the number of

professional hours Cignex anticipated would be worked, App. 190-91, and provided that

the “staffing, schedule and cost estimates” in the document were premised on

assumptions that, if changed, would “affect the overall cost and delivery schedule[]” of

the tasks, App. 188. The statement of work further provided that any changes to its scope

would be made through a formal “change request” procedure. SOW 2 was integrated

into the MSA and reconfirmed that Cignex would be paid “[a]s defined by [the] MSA.”

App. 192.

The MyLam project then proceeded rockily, experiencing several delays and

complications, until the summer of 2016. Cignex issued numerous invoices to Lam

during this time. Lam paid Cignex on all the invoices it issued between February and

June 2015. But as Lam discovered ongoing technical problems with Cignex’s

implementation of the MyLam project, it informed Cignex in August 2015 that it no

longer would pay any until Cignex could demonstrate that it could complete project

milestones. Cignex continued to work on the project and approached Lam about starting

payment once again at the start of August 2016. Instead, Lam issued a stop-work order to

Cignex. Cignex never completed the MyLam project, but by September 2016, had issued

four invoices since August 2015 that Lam never paid.

Cignex filed this lawsuit against Lam for breach of contract in March 2017,

alleging that Lam failed to pay the amount due for the work that Cignex billed on the

3 unpaid invoices. Lam answered with, inter alia, breach of contract counterclaims seeking

recovery of all the fees it had paid to Cignex. The parties proceeded to a bench trial. The

District Court held that the MSA and its integrated documents constituted a “time and

materials” contract requiring Lam to pay Cignex for the professional services and

expenses it had rendered, but which did not require delivery of a completed project to

trigger Lam’s obligation to pay. The District Court therefore largely ruled in Cignex’s

favor on its breach of contract claim, and against Lam on its breach of contract

counterclaim. Having concluded that Lam breached the MSA by failing to pay for

services rendered under the first three change requests, the District Court entered a

$232,039.71 judgment against Lam, which was later amended to $292,604.27. Lam

timely appealed.

II.

Although the parties both assert that the District Court had federal diversity

jurisdiction over Cignex’s claim under 28 U.S.C. § 1332(a), Cignex did not adequately

allege federal subject matter jurisdiction in its complaint. Cignex pleaded that Lam “is a

Delaware corporation,” while Cignex “is a Michigan limited liability company that is a

subsidiary of Datamatics Global Technologies Limited (Mauritius).” App. 110. Because

diversity jurisdiction requires complete diversity of citizenship between the parties and

“the citizenship of a limited liability company is determined by the citizenship of each of

its members,” Johnson v. SmithKline Beecham Corp., 724 F.3d 337, 348 (3d Cir. 2013)

(quoting Zambelli Fireworks Mfg. Co. v. Wood, 592 F.3d 412, 418 (3d Cir. 2010)),

4 Cignex could not rely on diversity jurisdiction as a limited liability company without

alleging none of its members were Delaware or California citizens.

We therefore asked the parties to make supplemental submissions clarifying

Cignex’s identity and citizenship. Having reviewed the parties’ submissions, it is

undisputed that Cignex is a Michigan corporation with its principal place of business in

Michigan, not a limited liability company, and thus a citizen of Michigan. 28 U.S.C. §

1332(c)(1). Pursuant to 28 U.S.C. § 1653, Cignex’s complaint is deemed amended such

that diversity jurisdiction exists. We have jurisdiction over this appeal from a final

decision under 28 U.S.C. § 1291. “On appeal from a judgment entered after a non-jury

trial, we review findings of fact for clear error, Fed. R. Civ. P. 52(a), and conclusions of

law de novo.” Hooven v. Exxon Mobil Corp., 465 F.3d 566, 572 (3d Cir. 2006) (quoting

Henglein v. Colt Indus. Operating Corp., 260 F.3d 201, 208 (3d Cir. 2001)). Contract

Free access — add to your briefcase to read the full text and ask questions with AI

Related

EBC, Inc. v. Clark Building System, Inc.
618 F.3d 253 (Third Circuit, 2010)
Glenda Johnson v. SmithKline Beecham Corp
724 F.3d 337 (Third Circuit, 2013)
Zambelli Fireworks Manufacturing Co. v. Wood
592 F.3d 412 (Third Circuit, 2010)
Hooven v. Exxon Mobil Corp.
465 F.3d 566 (Third Circuit, 2006)
Adirondack Classic Design, Inc. v. Farrell
2020 NY Slip Op 2298 (Appellate Division of the Supreme Court of New York, 2020)
DLJ Mortgage Capital, Inc. v. Ana Sheridan
975 F.3d 358 (Third Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
CIGNEX Datamatics Inc v. LAM Research Corp, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cignex-datamatics-inc-v-lam-research-corp-ca3-2021.