Maverick Steel Co. v. Dick Corporation

CourtSuperior Court of Pennsylvania
DecidedDecember 27, 2017
Docket236 WDA 2016
StatusUnpublished

This text of Maverick Steel Co. v. Dick Corporation (Maverick Steel Co. v. Dick Corporation) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maverick Steel Co. v. Dick Corporation, (Pa. Ct. App. 2017).

Opinion

J-A12007-17

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

MAVERICK STEEL COMPANY L.L.C. IN THE SUPERIOR COURT OF PENNSYLVANIA Appellant

v.

DICK CORPORATION/BARTON MALOW, A JOINT VENTURE; DICK CORPORATION AND BARTON MALOW COMPANY

Appellees No. 236 WDA 2016

Appeal from the Judgment Entered March 9, 2016 In the Court of Common Pleas of Allegheny County Civil Division at No(s): GD 02-005580

BEFORE: OLSON, J., SOLANO, J., and RANSOM, J.

MEMORANDUM BY SOLANO, J.: FILED DECEMBER 27, 2017

Appellant Maverick Steel Company L.L.C. (“Maverick”), the corporate

successor to Wilhelm & Kruse, Inc. (“W&K”), appeals from the judgment in

favor of Appellees Dick Corporation/Barton Malow, Dick Corporation, and

Barton Malow Company (collectively, “DBM”) that was entered following a

non-jury trial. W&K was the steel fabricator for construction of the PNC

Stadium in Pittsburgh (“the Stadium Project”). Maverick claims that DBM

interfered with W&K’s contractual relations with W&K’s bonding company,

United States Fidelity & Guaranty (“USF&G”), causing W&K to suffer financial

ruin and bankruptcy. After a careful review of the record and of Maverick’s

claims, we affirm.

This is the second time this case has been before us. See Maverick

Steel Co. v. Dick Corp./Barton Malow, 54 A.3d 352 (Pa. Super. 2012), J-A12007-17

appeal denied, 65 A.3d 415 (Pa. 2013). We state the facts in a light

favorable to DBM, the verdict-winner. See Nicholas v. Hofmann, 158 A.3d

675, 688 (Pa. Super. 2017).

On August 2, 1999, W&K entered into a structural steel subcontract

(“the Contract”) with DBM to provide steel for the Stadium Project. The

Contract required W&K to obtain a performance bond, which USF&G issued

to W&K on August 2, 1999 (“the Performance Bond”). Maverick claims that

prior to the Stadium Project, W&K had “the highest rating which USF&G

gives to its potential contractors.” Maverick’s Brief at 13 (citing N.T. Trial

644).

W&K was required to provide schedule information to DBM by late

August. It faxed that information on September 30, 1999. There also was a

delay of the date when W&K began erecting steel. During trial, Jeffrey

Klinefelter, a scheduling expert and consultant retained by USF&G, opined

that the postponements were caused by delays by the piling contractor in

creating the building foundation and by delays and changes to the design

documents. N.T. Trial at 1112-13, 1133-34, 1163. However, John Reich, a

Barton Malow employee and DBM’s project director in charge of daily site

operations for the Stadium Project, testified that W&K never provided any

scheduling analysis to DBM explaining the reasons for its delays and never

submitted any quantification of how many days W&K was allegedly delayed.

Id. at 2575-76.

-2- J-A12007-17

W&K had problems fabricating and delivering steel for the Stadium

Project throughout the remainder of 1999 and into 2000. In February 2000,

W&K submitted a “recovery” schedule — that is, a modified schedule which

accelerated the fabrication and erection process in an attempt to offset the

delays that had already occurred. By early March 2000, W&K’s problems —

particularly its fabrication and delivery delays — became a major concern for

DBM’s management team. DBM therefore met numerous times with W&K in

an effort to assist W&K in resolving its problems, wrote to W&K (without

including USF&G) about its concerns, and reminded W&K that “[p]roper

notice and justification must be provided to our office for any deviation from

the dates in your schedule[.]” DBM’s Ex. 214. DBM’s Reich later testified:

“[W]e brought [W&K] in and had a lot of meetings with them to find out

what the issues were and how we could help.” N.T. Trial at 2499. George L.

Harakal, Dick Corporation’s chief operating officer, testified that he arranged

the meetings between USF&G and DBM but that the meetings were not

productive. Id. at 3285.

On March 3, 2000, DBM faxed W&K a list of the problems that its

engineer had observed at W&K’s facility. Among other things, DBM

complained that it could not “obtain[] reliable information concerning

deliveries” and that “pieces” were being fabricated and “delivered out of

order” (that is, they were not delivered in accordance with prescribed

sequences for fabrication and assembly). DBM’s Ex. 41.

-3- J-A12007-17

DBM was concerned that W&K was failing to adhere to the recovery

schedule and unable to manage its work properly and that W&K’s problems

were negatively impacting the schedule for the entire Stadium Project. See

DBM’s Exs. 74 & 77. In May 2000, DBM sought a meeting with W&K and

USF&G to discuss this issue. A May 17, 2000, letter from DBM to Stephen

Cacali, W&K’s bonding agent and insurance broker, stated:

[USF&G] is aware that timely construction of PNC Park has been threatened by delays to [W&K]’s structural steel work. While [W&K] is of the opinion that responsibility for the delay rests with the [Stadium] Project[’]s Structural Engineers, please be advised that responsibility for the delay has not been finally determined or apportioned. It is also important to recognize that the financial exposure for late completion of the [Stadium] Project is severe with potential liquidated damages running as high as $6,000,000.00.

. . . [I]t is critical that all efforts be made to mitigate delays so that the [Stadium] Project can be completed consistent with the Contract[’]s requirements. To date, [DBM] has been extremely frustrated with [W&K]’s responses to the delay. Our review of the facts indicates that [W&K] may not have the proper procedures in place to manage a contract of this magnitude. Our concern has been heightened by [W&K]’s failure to adhere to its own revised Project schedule . . . .

[DBM] is committed to providing [W&K] with all necessary assistance to ensure the timely and satisfactory performance of its work. To this end, we request a meeting with authorized representatives of USF&G and [W&K] to ensure that both of you are equally committed to taking all the necessary steps to ensure [W&K]’s satisfactory and timely performance of its obligations. The failure to do so will have grave financial consequences for all parties.

Accordingly, upon receipt of this letter, please confirm that authorized representatives of USF&G and [W&K] will attend a jobsite meeting scheduled for May 23, 2000.

DBM’s Ex. 76.

-4- J-A12007-17

At trial, the court asked Anthony Phillips, an USF&G underwriter, to

clarify whether USF&G “at least temporarily stopped bonding W&K” after

receiving this letter of May 17, 2000. N.T. Trial at 644 (citing DBM’s Ex. 76).

Phillips answered, “Yes, because it was required by the rules and regulations

by USF&G . . . that bonding would have to be temporarily cut off.” Id. He

continued that, “if it became more serious, like a Notice of Default, then

bonding would be permanently cut off.” Id.

At the meeting on May 23, 2000, DBM told Phillips that “USF&G as

surety possibly need[ed] to step to the table when the funds run out.”

Maverick’s Ex. 229 (e-mail from Phillips, 5/24/00). On May 25, 2000, Cacali

wrote a memorandum to Barbara Henry at Kemper Insurance Company,

which had extended a conditional surety offer to W&K, stating that “[n]either

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allied Fire & Safety Equipment Co. v. Dick Enterprises, Inc.
972 F. Supp. 922 (E.D. Pennsylvania, 1997)
Commonwealth v. A.W. Robl Transport
747 A.2d 400 (Superior Court of Pennsylvania, 2000)
Walnut Street Associates, Inc. v. Brokerage Concepts, Inc.
982 A.2d 94 (Superior Court of Pennsylvania, 2009)
Chicarella v. Passant
494 A.2d 1109 (Supreme Court of Pennsylvania, 1985)
Nicholas, J. v. Hofmann, D.
158 A.3d 675 (Superior Court of Pennsylvania, 2017)
Bank of New York Mellon v. Bach, S.
159 A.3d 16 (Superior Court of Pennsylvania, 2017)
Maverick Steel Co. v. Dick Corporation/Barton Malow
54 A.3d 352 (Superior Court of Pennsylvania, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Maverick Steel Co. v. Dick Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maverick-steel-co-v-dick-corporation-pasuperct-2017.