Alstom Power, Inc. v. RMF Industrial Contracting, Inc.

418 F. Supp. 2d 766, 2006 U.S. Dist. LEXIS 8019, 2006 WL 519766
CourtDistrict Court, W.D. Pennsylvania
DecidedMarch 2, 2006
Docket2:03CV627, 2:03CV1050
StatusPublished
Cited by2 cases

This text of 418 F. Supp. 2d 766 (Alstom Power, Inc. v. RMF Industrial Contracting, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alstom Power, Inc. v. RMF Industrial Contracting, Inc., 418 F. Supp. 2d 766, 2006 U.S. Dist. LEXIS 8019, 2006 WL 519766 (W.D. Pa. 2006).

Opinion

MEMORANDUM OPINION AND ORDER OF COURT

MCVERRY, District Judge.

Before the Court for consideration and disposition is PLAINTIFF ALSTOM POWER, INC.’S MOTION FOR PARTIAL SUMMARY JUDGMENT, with attached brief in support (“Motion” and “Brief’) (Document No. 37). The issues have been fully briefed, and the matter is ripe for disposition. See Document Nos. 44 & 49. For the reasons which follow, the Motion will be granted in part and denied in part.

*768 Background,

Plaintiff Alstom Power, Inc. (“Alstom”) entered into a consortium with Duke/ Flour Daniel (“DFD,” and collectively “the Consortium”) to submit a bid to Reliant Energy for the construction of a coal-fired power plant at the site of the existing Seward Power Plant in Indiana County, Pennsylvania (the “Project”). Pltfs Stmt, of Facts at ¶ 1. Reliant Energy accepted the Consortium’s bid. Id. at ¶ 2. On January 17, 2001, Reliant Energy and the Consortium entered into an engineering, procurement and construction contract (the “EPC Contract”). Id. The guaranteed completion date for the Project was May 1, 2004. Id. Under the EPC Contract, the Consortium agreed to provide engineering, procurement, construction, startup, demonstration and testing for the repowering of the existing Seward Power Plant. Id. at ¶ 3. The repowering of the Seward Power Plant was to be accomplished by constructing a new power plant adjacent to the existing facility which would incorporate the existing exhaust stack from the old plant. Id. at ¶ 4.

Under the EPC Agreement, Alstom was responsible for designing, procuring and constructing two new Circulating Fluidized Bed Boilers (“CFB Boilers”) and other ancillary components. Pltfs Stmt, of Facts at ¶ 5. Alstom decided to subcontract the actual erection of the CFB Boilers, the ancillary equipment and the structural steel to other entities. Id. at ¶ 6. On August 3, 2001, Alstom sent a “Request for Quotation for the Mechanical Erection of Circulating Fluidized Bed Steam Generators and Ancillary Equipment” (the “RFQ”) to defendant RMF Industrial Contracting, Inc. (“RMF”) and other companies. Id. at ¶ 7. The RFQ solicited bids for the erection of the CFB Boilers and ancillary components. Id. The RFQ contained an Equipment Summary Sheet which identified the various components and the approximate quantities and weights of the components. Id. On August 24, 2001, Al-stom sent to RMF and others an addendum (“the Addendum”) to the RFQ which included a revised Equipment Summary Sheet. Pltfs Stmt, of Facts at ¶ 8.

RMF submitted a bid in response to the RFQ and the Addendum on September 20, 2001. Id. at ¶ 9. RMF’s bid included the erection of the CFB Boilers and ancillary equipment for the price of $48,039,896.00. Id. According to John Miehle, RMF’s lead estimator, RMF estimated the man hours necessary to complete its scope of work on the Project based on the quantities and weights listed in the revised Equipment Summary Sheet. Id. at ¶¶ 10-11. On November 2, 2001, Alstom issued a letter of award to RMF in which Alstom stated its intention to award a purchase order to RMF for the mechanical erection, i.e. the erection of the CFB Boilers and ancillary equipment, for the price of $45,888,000.00. Id. at ¶ 12. On January 15, 2002, 1 RMF and Alstom executed Purchase Order No. 73060 (the “Purchase Order” or “Agreement”), which provided that RMF would erect the two CFB Boilers and ancillary equipment for the price of $46,168,000.00. Pltfs Stmt, of Facts at ¶ 14. 2 Additionally, Philip Services Corporation (“PSC”), RMF’s parent company, provided a $5,000,000.00 letter of credit (the “Letter of Credit”) to Alstom. Id. at ¶ 14.

The Purchase Order provided that RMF’s work was to be completed by *769 March 1, 2004, but also provided that “said date may be adjusted by this Agreement.” RMF’s Stmt, of Facts at ¶ 15. In the absence of any adjustments, RMF was required to achieve certain “milestones” by certain dates: 25% complete by October 25, 2002; 50% complete by January 3, 2003; 75% complete for Unit 2 by May 1, 2003; and 75% complete for Unit 1 by May 27, 2003. 3 Pltfs Stmt, of Facts at ¶ 16.

RMF personnel arrived at the site of the Project in January of 2002. Pltfs Stmt, of Facts at ¶ 19. However, according to RMF the site was not properly prepared for RMF to proceed with construction. RMF’s Stmt, of Facts at ¶ 19. RMF contends that conditions at the site were generally not good and did not improve, and that performance of its duties under the Purchase Order was hampered by various problems. Some of the problems were allegedly caused by Alstom (ie., insufficient laydown area, lack of site maintenance, schedule delay and scope growth), while others (ie., an extremely harsh winter) were beyond the control of anyone involved with the Project. See RMF’s Brief at 2-3; RMF’s Stmt, of Facts at ¶¶ 53-134 (describing RMF’s difficulties with the Project).

It is undisputed that RMF experienced difficulties in the achievement of the “milestones” described above. RMF missed the 50% completion date (January 3, 2003), but contends that it was generally not at fault due to the problems encountered as mentioned above. Pltfs Stmt, of Facts at ¶ 21; RMF’s Stmt, of Facts at ¶ 21. Additionally, William Harrington, RMF’s Project Executive, testified that based upon “a certain scope of work” RMF was not on schedule in the Spring of 2003. RMF’s Stmt, of Facts at ¶ 22.

An issue in this case is whether RMF properly followed the notice provisions established by the Purchase Order when alleged needs arose regarding additional work, additional costs, expenses and the like. During the course of RMF’s performance, it submitted various letters to Alstom stating that it would request an extension of time to meet certain milestone dates. Pltfs Stmt, of Facts at ¶ 20. According to Alstom, there is no evidence that RMF ever submitted anything more than said letters with no supporting documentation which is not in conformance with the express requirements of the Purchase Order. Id. RMF, on the other hand, contends that it “provided Alstom with substantial notice and documentation of the problems it experienced on site.” RMF’s Stmt, of Facts at ¶ 20.

On February 20, 2003, after having experienced numerous problems and delays, RMF submitted an “as-impacted” schedule to Alstom which indicated that RMF would complete its scope of work on the Project six months later than contractually required. Pltfs Stmt, of Facts at ¶ 23. The “as-impacted” schedule was not meant to be a detailed schedule analysis, but RMF expected that submission to “start a dialogue” with Alstom regarding the problems that RMF had experienced. Id. at ¶ 33. On March 11, 2003, in response to RMF’s “as-impacted” schedule, Alstom dispatched correspondence to RMF which stated, in part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Renee Marie Thorpe v.
Third Circuit, 2018

Cite This Page — Counsel Stack

Bluebook (online)
418 F. Supp. 2d 766, 2006 U.S. Dist. LEXIS 8019, 2006 WL 519766, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alstom-power-inc-v-rmf-industrial-contracting-inc-pawd-2006.