collins/snoops Associates, Inc. v. Cjf, LLC

988 A.2d 49, 190 Md. App. 146, 2010 Md. App. LEXIS 8
CourtCourt of Special Appeals of Maryland
DecidedJanuary 27, 2010
Docket2273, September Term, 2007
StatusPublished
Cited by14 cases

This text of 988 A.2d 49 (collins/snoops Associates, Inc. v. Cjf, LLC) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
collins/snoops Associates, Inc. v. Cjf, LLC, 988 A.2d 49, 190 Md. App. 146, 2010 Md. App. LEXIS 8 (Md. Ct. App. 2010).

Opinion

MEREDITH, J.

This appeal presents the question of whether a judge who hears a bench trial in a case in which two parties each claim the other breached a contract may deny both claims on the ground that neither party carried its burden of persuading the court that the other party breached the contract. Under the peculiar circumstances of this case, we shall affirm a judgment that denied relief to both the plaintiff and the counterplaintiff.

The case arose from a dispute between a contractor and its subcontractor on a project that involved renovations to three Baltimore County school buildings. The general contractor that won the bid for the project was CJF, LLC (hereinafter “Contractor”), the appellee/cross-appellant. It engaged Collins/Snoops Associates, Inc. (hereinafter “Subcontractor”), appellant/cross-appellee, as a subcontractor to perform over $2.69 million worth of plumbing, heating and air conditioning *150 mechanical work as part of the renovations. After Subcontractor had completed only a portion of the specified mechanical work, Contractor asserted that Subcontractor was not making acceptable progress in order to meet the strict deadlines required by the County. Contractor terminated Subcontractor and engaged a replacement firm to take over the mechanical work on the schools. Subsequently, Contractor itself was terminated by the County because the County was not satisfied with Contractor’s progress.

Subcontractor sued Contractor, its president, and its bonding company, in the Circuit Court for Baltimore County, claiming that Subcontractor was owed $409,720 for the work and materials it had provided prior to the time it was terminated. Contractor filed a counterclaim against Subcontractor, claiming damages that Contractor alleged it had incurred as a consequence of Subcontractor’s failure to properly perform the obligations under the subcontract. After a bench trial on the merits, the trial court filed a written opinion in which it stated that “the court finds itself in equipoise as to each party’s claim for breach of contract against the other.” The trial court continued: “In brief, this court concludes that neither has [Contractor] proved by a preponderance of the evidence that [Subcontractor] failed to perform nor has [Subcontractor] proved by a preponderance of the evidence that it was wrongfully terminated from the school renovation project by [Contractor].” Accordingly, the trial court granted judgment in favor of the defendants—i.e., Contractor, its president, and its bonding company—“for all claims brought against [them] by [Subcontractor],” and the court granted judgment in favor of the counterdefendant, the Subcontractor, “for all claims brought against it by [Contractor].”

Subcontractor and Contractor have both appealed, each seeking to overturn the trial court’s denial of their respective claims for damages. As appellant, Subcontractor raises the following questions:

I. Having found that [Subcontractor] provided $409,720 in labor and materials to [Contractor] on the County project, and having further found that [Subcontractor] had not *151 “failed to perform,” was it error for the trial judge not to have awarded [Subcontractor] at least the $409,720 for the labor and materials it provided?
II. Having found that [Contractor] did not prove [Subcontractor] had failed to perform, did the trial judge impermissibly shift the burden to [Subcontractor] to show that its termination was “wrongful”?
III. Having found that [Contractor] did not prove [Subcontractor] had failed to perform, was it error for the trial judge not to have awarded [Subcontractor] its lost profits on the job?

As appellee, Contractor rephrases the appellant’s questions as one issue:

Whether the trial court sitting as finder of fact correctly held that [Subcontractor] failed to meet its burden of proving breach of contract where the court found the evidence to be in equipoise.

Additionally, as cross-appellee, Contractor raises the following issue:

Whether the trial court erred in finding that [Contractor] failed to prove its damages.

We conclude that the trial court did not err in entering judgment for the respective defendants as to all claims and counterclaims. Accordingly, we shall affirm the judgments entered by the circuit court.

FACTS AND PROCEDURAL HISTORY

In 2001, the County entered into a contract with Contractor to renovate three public elementary schools: Chase, Victory Villa, and Hawthorne Elementary. Appellee Carolina Casualty Insurance Company (“Carolina”) issued a payment bond to guarantee that Contractor’s subcontractors would be paid in the event Contractor wrongfully failed to pay amounts due the subcontractors for supplying labor and materials on the project.

*152 Contractor engaged Subcontractor to perform plumbing and mechanical work on the heating and air-conditioning systems at the three schools. Contractor asked Subcontractor to sign Contractor’s “standard” form subcontract agreement, but Subcontractor refused to sign. Nevertheless, the trial court found that Subcontractor, by its conduct, adopted or assented to the terms in the document that it refused to sign. Citing Porter v. General Boiler Casing Co., 284 Md. 402, 410-12, 396 A.2d 1090 (1979), the trial court concluded that the Contractor’s form subcontract agreement “constitutes the contract between [Contractor] and [Subcontractor],” despite not being signed by Subcontractor. That finding is not challenged by either party on appeal.

The subcontract agreement contains numerous references to the Contractor’s need for timely performance, including a statement that “[i]t is UNDERSTOOD AND AGREED by and between the parties that time is and shall be considered the essence of the contract on the part of the said Subcontractor. ...” The subcontract further required Subcontractor to “promptly begin said work” and “complete said work as rapidly as said Contractor may judge that the progress of the structure will permit.” Similarly, the subcontract called for diligent and uninterrupted performance by Subcontractor:

The Subcontractor agrees to cooperate with the Contractor and with other Subcontractors in the diligent performance of the work and to prosecute regularly, diligently and uninterruptedly at such rate of progress in such a manner as to enable the Contractor to complete the entire structure within the time specified.

The subcontract called for Contractor to compensate Subcontractor as follows:

IN CONSIDERATION WHEREOF, the said Contractor agrees that he will pay to the said Sub-contractor, in monthly payments, the sum of TWO MILLION SIX HUNDRED NINETY SIX THOUSAND EIGHT HUNDRED SIXTY DOLLARS. PRICE FIRM—NOT SUBJECT TO ESCALATION
*153 $2,696,860.00 DOLLARS for said materials and work, said amount to be paid as follows: Ninety per cent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maryland Indoor Play v. Snowden Investment
Court of Appeals of Maryland, 2025
Gables Constr., Inc. v. Red Coats, Inc.
207 A.3d 1220 (Court of Special Appeals of Maryland, 2019)
Gables Construction v. Red Coats
Court of Special Appeals of Maryland, 2019
White Marlin Open, Inc. v. Heasley
262 F. Supp. 3d 228 (D. Maryland, 2017)
Bontempo v. Lare
90 A.3d 559 (Court of Special Appeals of Maryland, 2014)
Jay Dee/Mole Joint Venture v. Mayor & City Council
725 F. Supp. 2d 513 (D. Maryland, 2010)
Board of Education v. Beka Industries, Inc.
989 A.2d 1181 (Court of Special Appeals of Maryland, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
988 A.2d 49, 190 Md. App. 146, 2010 Md. App. LEXIS 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/collinssnoops-associates-inc-v-cjf-llc-mdctspecapp-2010.