This text of Sunbelt Rentals, Inc. v. Verticon Inc. (Sunbelt Rentals, Inc. v. Verticon Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sunbelt Rentals, Inc. v. Verticon Inc., (D. Md. 2019).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND Northern Division

* SUNBELT RENTALS, INC., * Plaintiff, * v. * Case No.: DLB-18-3134 VERTICON CONSTRUCTION, INC., * Defendant. *

* * * * * * * * * * * * * *

MEMORANDUM OPINION Sunbelt Rentals, Inc. (“Sunbelt”) initiated this litigation after Verticon, Inc. (“Verticon”) failed to pay for construction equipment that it rented from Sunbelt. Compl., ECF No. 1. In its Complaint, it sought $152,165.22 from Verticon for breach of contract. Id. It moved for partial summary judgment in the amount of $142,410.16, arguing that the lesser sum was undisputed. Pl.’s Mot., ECF No. 31; Pl.’s Mem. 4, 6, ECF No. 32.1 The parties then asked the Court to defer resolution of the motion, ECF No. 39, and they entered into an agreement (“Settlement Agreement”) to settle the claim for $135,920.92, with payments to come from Verticon and three sureties, Sett. Agr., ECF No. 54-1. Two months later, after receiving only $68,952.92, Sunbelt renewed its dispositive motion, stating that it still sought $73,457.24, the unpaid balance of the $142,410.16 it originally sought on summary judgment. Pl.’s Supp., ECF No. 53. Verticon concedes that payments under the Settlement Agreement are incomplete. Def.’s Resp., ECF No. 54. But in its view, the Court should not enter

1 Sunbelt voluntarily dismissed its claim against Aegis Security Insurance Co. (“Aegis”), ECF No. 53, leaving only the claim against Verticon. judgment against it; rather, the Court should enforce the Settlement Agreement, obligating Verticon to pay the remainder of the $135,920.92 it agreed to pay in settlement of the case (that is, $6,489.24 less than Sunbelt seeks). Id. In its response, Verticon asked for an extension of time to complete its payments. Id. I construed Verticon’s request as a motion to enforce the Settlement Agreement. ECF No. 58. The parties fully briefed Sunbelt’s motion for partial summary judgment and Verticon’s motion

to enforce the Settlement Agreement. ECF Nos. 31, 32, 53, 54, 57, 59. A hearing is not necessary. See Loc. R. 105.6. Because Verticon has neither performed all of its material contractual obligations nor shown that its performance should be excused, it cannot enforce the Settlement Agreement. See Hubler Rentals, Inc. v. Roadway Exp., Inc., 637 F.2d 257, 260–61 (4th Cir. 1981). Further, Sunbelt is entitled to judgment as a matter of law because the material facts are undisputed. Therefore, I will grant Sunbelt’s motion for partial summary judgment and enter judgment in Sunbelt’s favor for the unpaid balance of the $142,410.16 it originally sought on summary judgment. Factual Background

Pursuant to the Settlement Agreement, Verticon agreed to pay Sunbelt $135,920.92 “in full on [or] before June 30, 2019, time being of the essence.” Sett. Agr. ¶ 1. Three sureties were expected to make payments toward this total, with Fidelity & Deposit Co. of Maryland/Cooper Material Handling Co. (“Cooper”) paying $66,968.00; FCCI Insurance Co. (“FCCI”) paying $48,348.34; and Aegis Security Insurance Co. (“Aegis”) paying $5,604.58. Id. ¶ 2. Verticon was responsible for securing these payments and paying $15,000.00 itself. Id. ¶¶ 1–2. In exchange for “timely payment in full,” Sunbelt agreed to dismiss all of its claims in this litigation with prejudice. Id. ¶ 2. Sunbelt received $15,000.00 from Verticon, $48,348.34 from FCCI, and $5,604.58 from Aegis

before the June 30, 2019 deadline. Checks, ECF No. 54-1, at 3, 6, 9. To secure payment from Cooper in satisfaction of the Settlement Agreement, the parties extended the deadline repeatedly, first to July 8, 2019, then to July 15, 2019, and then to July 22, 2019, ECF Nos. 45–50. Yet, as of August 8, 2019, Sunbelt still had not received Cooper’s payment. Pl.’s Supp. 1. The parties did not agree to extend the deadline beyond July 22, 2019, and therefore Verticon’s timely payment totaled only $68,952.92, or just over half of the $135,920.92 due.

On August 22, 2019, Verticon asked the Court for “an additional fifteen (15) days to tender the remaining payments to Sunbelt.” Def.’s Resp. ¶ 7. According to Verticon, Cooper had “rescinded its agreement to make the payment,” and Verticon had “been negotiating a resolution to this dispute within a dispute” with Cooper. Id. ¶¶ 4–5. Verticon and Cooper “reached a compromise” on August 22, 2019, under which Cooper would “issue a payment for $35,000 to be tendered to Sunbelt Rentals, Inc.” Id. ¶ 5. Notably, if Cooper remitted a payment of $35,000.00 to Sunbelt, Verticon still would be responsible for the remaining $31,968.00 due under the Settlement Agreement. See Sett. Agr. ¶ 2. The Court did not address the request for additional time, and Verticon did not complete its

payments due under the Settlement Agreement within fifteen days of its August 22, 2019 request. Indeed, it is unclear whether Sunbelt ever received the $35,000.00 payment from Cooper following the August “compromise.” See Status Rept., ECF No. 56; Pl.’s Reply & Opp’n, ECF No. 57; Def.’s Reply, ECF No. 59. On October 18, 2019, almost two months after Cooper was supposed to have paid $35,000.00, Sunbelt reported that Verticon was “scheduled to receive a sign off on the final punch list October 22, 2019, which [would] trigger Cooper Materials to release to Sunbelt an additional $35,000.” Status Rept. (emphasis added). The status report did not state whether Cooper already had made a payment to Sunbelt, or whether the anticipated payment was simply “additional” to the payments Sunbelt had received from the other sureties and Verticon. I directed Verticon to address its authority to enforce the Settlement Agreement and to notify the Court of the amount paid to Sunbelt to date. Ltr. Order, ECF No. 58. In its November 13, 2019 reply, Verticon stated that it had “been attempting to conclude a newly arisen punch list in order to get its prime contractor to release additional funds to Sunbelt” and that when Verticon “finish[ed] the punch list on Thursday, November 14, 2019, . . . Cooper Materials will authorize another check for $35,000 directly to Sunbelt.” Def.’s Reply ¶¶ 2–3 (emphasis added). As noted, Sunbelt’s October 18, 2019 status report similarly referenced an “additional $35,000” it expected Cooper to pay. It is unclear to the Court from either filing whether Cooper had remitted an

earlier payment of $35,000.00 pursuant to the August 22, 2019 compromise, or whether Sunbelt only had received other checks from the other sureties and Verticon. Of course, if Cooper had submitted two $35,000.00 checks, then Sunbelt would have received almost $2,032.00 more than was due under the Settlement Agreement, which is highly unlikely. Regardless, it is clear that Sunbelt received only a little more than half of the amount due by the July 22, 2019 deadline and, more than four months later, it still has not received the entirety of the $73,457.24 it seeks in its summary judgment motion, as supplemented. Pl.’s Supp. Motion to Enforce Settlement Agreement

Verticon asks the Court to enforce the Settlement Agreement instead of entering judgment against it, so that it will have to pay the remainder of the $135,920.92 due under the Settlement Agreement, but not the remainder of the greater amount Sunbelt seeks in its motion for partial summary judgment. Def.’s Resp. ¶ 8. Sunbelt counters that Verticon, as the defaulting party, cannot ask the Court to enforce the Settlement Agreement. Pl.’s Reply & Opp’n 2. Verticon insists that it can, given that “Ageis, FCCI, and Verticon all made their proportionate payments under the agreement” and Verticon has diligently sought to spur its co-payor into action and has been attempting to conclude a newly arisen punch list in order to get its prime contractor to release additional funds to Sunbelt.” Def.’s Reply ¶¶ 1, 2; see id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Roanoke Properties Ltd. Partnership v. Dewberry & Davis
30 F. App'x 121 (Fourth Circuit, 2002)
Regal Savings Bank v. Sachs
722 A.2d 377 (Court of Appeals of Maryland, 1999)
RaceRedi Motorsports, LLC v. Dart MacHinery, Ltd.
640 F. Supp. 2d 660 (D. Maryland, 2009)
collins/snoops Associates, Inc. v. Cjf, LLC
988 A.2d 49 (Court of Special Appeals of Maryland, 2010)
Taylor v. NationsBank, N.A.
776 A.2d 645 (Court of Appeals of Maryland, 2001)
Maslow v. Vanguri
896 A.2d 408 (Court of Special Appeals of Maryland, 2006)
Bank of America, N.A. v. Jill P. Mitchell Living Trust
822 F. Supp. 2d 505 (D. Maryland, 2011)
Sachs v. Regal Savings Bank, FSB
705 A.2d 1 (Court of Special Appeals of Maryland, 1998)
Barufaldi v. Ocean City
7 A.3d 643 (Court of Special Appeals of Maryland, 2010)
Weichert Co. v. Faust
19 A.3d 393 (Court of Appeals of Maryland, 2011)
Publish America, LLP v. Stern
84 A.3d 237 (Court of Special Appeals of Maryland, 2014)
Charity Swift v. Frontier Airlines, Incorporated
636 F. App'x 153 (Fourth Circuit, 2016)
Speed v. Bailey
139 A. 534 (Court of Appeals of Maryland, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
Sunbelt Rentals, Inc. v. Verticon Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/sunbelt-rentals-inc-v-verticon-inc-mdd-2019.