Aarow Equipment & Services, Inc. v. Travelers Casualty & Surety Co. of America

417 F. App'x 366
CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 18, 2011
Docket10-1375
StatusUnpublished
Cited by2 cases

This text of 417 F. App'x 366 (Aarow Equipment & Services, Inc. v. Travelers Casualty & Surety Co. of America) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aarow Equipment & Services, Inc. v. Travelers Casualty & Surety Co. of America, 417 F. App'x 366 (4th Cir. 2011).

Opinion

Vacated and remanded by unpublished PER CURIAM opinion.

Unpublished opinions are not binding precedent in this circuit.

PER CURIAM:

This appeal concerns an action brought by a subcontractor against a surety under the Miller Act (the Act), 40 U.S.C. §§ 3131 through 3134. Under the Act, before a general contractor is awarded a contract by the federal government in an amount greater than $100,000, the general contractor is required to obtain a “payment bond” “for the protection of all persons supplying labor and material in carrying out the work provided for in the contract.” 40 U.S.C. § 3131(b)(2). The Act provides a cause of action, such as the one asserted here, permitting a subcontractor to file suit seeking payment from a surety on a payment bond when the subcontractor has not been paid by the general contractor within 90 days of completing the subcontractor’s work. 40 U.S.C. § 3133(b)(1). For the reasons that follow, we vacate the district court’s award of summary judgment in favor of the surety and remand the case for further proceedings.

I.

We review the facts in the light most favorable to Aarow, the non-moving party in the district court. Hooven-Lewis v. Caldera, 249 F.3d 259, 265 (4th Cir.2001). In 2007, Syska Hennessy Group Construction, Inc. (Syska) was awarded a contract (the prime contract) by the United States government (the government) to construct a training facility for the District of Columbia Army National Guard at Fort Belvoir, Virginia (the project). Syska served *368 as the general contractor on the project and obtained a payment bond, as required by the Miller Act, from Travelers Casualty and Surety Company of America (Travelers). Syska awarded Aarow Equipment & Services, Inc. (Aarow) a subcontract, which set forth the “work” that Aarow was required to perform on the project.

Section 11.1 of the subcontract stated that Syska may “make changes in the [w]ork covered by this [subcontract,” and that any changes must be made in writing. The subcontract also provided that Aarow must submit in writing to Syska any claims for changes in the price or payment due under the contract. According to the subcontract, any such change in price or payment to Arrow “shall be made” “only to the extent that” Syska is entitled to relief from the government, and payment to Aarow shall be equal to Aarow’s share of any adjustment to the prime contract.

When changes to the “work” under the subcontract were made, Aarow generally submitted the proposed cost of the change to Syska, and Syska issued a “change order” to the subcontract. Aarow’s “work” described in the subcontract included several categories of responsibilities, including “earthwork” relating to water distribution and drainage. During Aarow’s performance of this “earthwork,” the government determined that the “erosion control plan” Aarow was implementing was “not up to standard[s].” Aarow ceased working until it received new erosion plan “drawings,” which required the construction of sedimentary ponds and other water management measures (the pond work).

Aarow and Syska agreed that the pond work was not included in the “work” defined in the subcontract. In September 2007, Aarow submitted a proposal of $402,500 to Syska for the pond work. Syska directed Aarow to perform the pond work, but did not issue a “change order” for the pond work at that time. Aarow completed the pond work, with the understanding that Syska would issue a “change order” at some point in the future.

Upon Syska’s determination that the pond work was not included in the scope of the prime contract, 1 Syska asked that the government agree to a “modification” of the prime contract. 2 Syska requested that Aarow wait to submit its invoice for the pond work until after the government issued a “modification” to the prime contract and Syska issued a “change order” to the subcontract.

Several months later, neither a “modification” nor a “change order” had been issued. Nevertheless, Aarow submitted an invoice to Syska for the completed pond work. Syska instructed Aarow to use a billing procedure that would allow Syska to pay Aarow for the pond work even though a “change order” had not been issued. This billing procedure required Aarow to list the pond work under a “line item” designated for certain “finishing” work on the project that had not yet been completed. 3 According to Syska, the government had authorized this billing procedure while Syska’s “modification” request was pending.

*369 After Aarow complied with this different billing procedure in accordance with Syska’s directions, Syska submitted a similar invoice to the government identifying the pond work as “finishing” for a “three-story building.” The government paid Syska $484,980, which included the invoice in the amount of $402,500 submitted by Aarow, plus a fee representing Syska’s “normal markup.” Syska, in turn, paid Aarow $402,500 for the pond work. Syska advised Aarow that after Syska received a “modification” and issued a “change order,” Aarow could reallocate the funds received for the pond work to the proper “line item.” Shortly after the government paid Syska the requested amount of $484,980, the government determined that the pond work was included in the prime contract. Accordingly, the government denied Syska’s request for a “modification” of the prime contract based on the government’s construction of the prime contract’s terms.

The government later withheld several payments to Syska to recover the funds previously paid for the pond work. In response, Syska withheld payment from Aarow for other work completed by Aarow between May 2009 and June 2009.

On July 1, 2009, Aarow sent Syska a letter stating that Syska had a “significant outstanding and past balance due,” and that Aarow would stop work on the project at the end of the week unless payment was made. When Syska did not submit payment to Aarow under the terms of the demand, Aarow ceased work on the project.

On July 17, 2009, Syska sent Aarow a letter notifying Aarow that it was in default of the subcontract for failing “to proceed with the work” according to the project schedule. In that letter, Syska instructed Aarow to correct and complete specific alleged defaults. Aarow did not return to work on the project or otherwise attempt to cure the alleged defaults. On July 23, 2009, Syska sent another letter to Aarow stating that because Aarow had not cured the defaults, Syska was terminating the subcontract as provided in Section 12.1 of that agreement.

Section 12.1 of the subcontract stated, in relevant part:

If, in the opinion of [Syska], [Aarow] shall at any time ... fail in any respect to prosecute the Work according to the current schedule ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Young Elec. Contractors, Inc. v. Dustin Constr., Inc.
185 A.3d 170 (Court of Appeals of Maryland, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
417 F. App'x 366, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aarow-equipment-services-inc-v-travelers-casualty-surety-co-of-ca4-2011.