Universal Concrete Products Corp. v. Turner Construction Co.

595 F.3d 527, 2010 U.S. App. LEXIS 3279, 2010 WL 572875
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 19, 2010
Docket09-1569
StatusPublished
Cited by10 cases

This text of 595 F.3d 527 (Universal Concrete Products Corp. v. Turner Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Concrete Products Corp. v. Turner Construction Co., 595 F.3d 527, 2010 U.S. App. LEXIS 3279, 2010 WL 572875 (4th Cir. 2010).

Opinion

Affirmed by published opinion. Judge GREGORY wrote the opinion, in which Judge DUNCAN and Judge BLAKE joined.

OPINION

GREGORY, Circuit Judge:

This appeal requires us to consider the applicability and enforceability of a “pay-when-paid” clause agreed to by the parties in this case. Specifically, we must decide whether certain provisions in a prime contract, which the general contractor and a subcontractor incorporated by reference into their subcontract, render an otherwise unambiguous pay-when-paid clause within that subcontract ambiguous. The district court found that they did not. We affirm.

I.

In October 2007, Universal Concrete Products Corporation (“Universal”), a Pennsylvania corporation, entered into a written agreement with Turner Construction Company (“Turner”), a New York corporation, to install precast concrete on the Granby Tower construction project in Norfolk, Virginia. Turner had earlier contracted with the project’s owner to provide *529 general construction work on the project. The subcontract executed by Turner and Universal incorporated that prime contract by reference.

Like countless other construction ventures since the collapse of the real estate market, the Granby Tower project ultimately fell through in March 2008 when the owner could no longer finance it. By that point, Universal had substantially completed all of its work on the project. Turner, however, had not paid Universal for any of the work performed, because Turner had not yet been paid by the owner. 1

When Universal sought payment of $885,507 from Turner for the work it had performed, Turner refused, citing a pay-when-paid provision in the subcontract. Universal then filed suit in the Eastern District of Virginia pursuant to 28 U.S.C. § 1332 (2006), alleging breach of contract and several other claims not germane to this appeal.

Before the district court, Universal alleged that the subcontract, when read in light of Turner’s contract with the owner, is “patently ambiguous” as to when Turner was required to pay Universal. Turner, in turn, argued that the language in the subcontract is unambiguous and that other terms in the prime contract are consistent with or support the pay-when-paid clause in the subcontract.

The district court agreed with Turner that the provision, even when viewed in light of the prime contract, is unambiguous and granted summary judgment to Turner on the breach of contract claim. Universal appeals.

II.

The sole issue raised by Universal’s appeal is whether or not the district court correctly found that Universal’s contract with Turner contained an unambiguous pay-when-paid clause, which conditioned any payments to Universal on Turner’s first receiving payment from the owner. Universal asks us to reverse the district court’s judgment in Turner’s favor and asks us to follow two, out-of-jurisdiction cases, which support its reading of the contract. We cannot do so, however, because we believe that under Virginia law, the contract unambiguously reflects both parties’ understanding that Universal would only be paid for its work after Turner was paid by the owner. Consequently, we hold that the pay-when-paid clause contained in the Turner-Universal subcontract is enforceable and prevents Universal from demanding payment from Turner unless and until Turner is first paid by the owner.

a.

We review de novo the district court’s granting summary judgment to Turner. Long v. Dunlop Sports Group Ams., Inc., 506 F.3d 299, 301 (4th Cir.2007). Because this appeal invokes our diversity jurisdiction, we must apply Virginia state law, just as the forum would have done had the suit been brought in state court. See Erie R.R. v. Tompkins, 304 U.S. 64, 78, 58 S.Ct. 817, 82 L.Ed. 1188 (1938); St. Paul Fire & Marine Ins. Co. v. Jacobson, 48 F.3d 778, 783 (4th Cir.1995).

b.

We begin by analyzing the contractual language in both the Turner-Universal subcontract and the Turner-owner general contract against the backdrop of Virginia law. Pay-when-paid clauses are *530 valid in Virginia 2 “where the language of the contract in question is clear on its face.” Galloway Corp. v. S.B. Ballard Constr. Co., 250 Va. 493, 464 S.E.2d 349, 354 (1995). A contractor and subcontractor may create a valid pay-when-paid clause by including in their contract “an express condition clearly showing that to be the intention of the parties.” Id. (internal quotation marks omitted). On the other hand, Virginia courts will not enforce pay-when-paid clauses if there is an ambiguity in the contract, which “ ‘exists when language is of doubtful import, admits of being understood in more than one way, admits of two or more meanings, or refers to two or more things at the same time.’ ” Id. at 355 (quoting Allen v. Green, 229 Va. 588, 331 S.E.2d 472, 475 (1985)).

The parties do not dispute that the pay-when-paid clause in the Turner-Universal contract is facially unambiguous. Indeed, it is hard to see how they could. Article IV of the agreement states in relevant part:

The obligation of Turner to make a payment under this Agreement, whether a progress or final payment, or for extras or change orders or delays to the Work, is subject to the express condition precedent of payment therefor by the Owner.

J.A. 67. 3 The agreement further states that the amount paid to Universal will be “out of funds received from the Owner.” Id. Finally, Article II of the subcontract states that the agreement is intended to supplement the agreement between Turner and the owner and that any conflict between the two agreements will be read to impose the greater obligation on the subcontractor. J.A. 66.

Universal argues, however, that the subcontract, which incorporates Turner’s contract with the owner by reference, is ambiguous when read as a whole. Universal claims that the Turner-owner contract, which consists of the standard American Institute of Architects (“AIA”) provisions, reflects an understanding that Turner would pay Universal before being paid by the owner. Specifically, Universal points to A121 section 6.1.3, which states that the costs for which the owner will reimburse Turner include “[pjayments made by the Construction Manager to Subcontractors in accordance with the requirements of the subcontracts.” J.A. 240.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parkway 1046, LLC v. U. S. Home Corporation
961 F.3d 301 (Fourth Circuit, 2020)
Traxys North America LLC v. Concept Mining Incorporated
510 F. App'x 262 (Fourth Circuit, 2013)
Jennifer Scott v. Merck & Company, Incorporated
497 F. App'x 331 (Fourth Circuit, 2012)
Bank of America, N.A. v. Christopher Sands
488 F. App'x 704 (Fourth Circuit, 2012)
Levin v. Alms and Associates, Inc.
634 F.3d 260 (Fourth Circuit, 2011)
Prym Consumer USA, Inc. v. Rhode Island Textile Co.
388 F. App'x 352 (Fourth Circuit, 2010)
Bodkin v. Town of Strasburg, Virginia
386 F. App'x 411 (Fourth Circuit, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
595 F.3d 527, 2010 U.S. App. LEXIS 3279, 2010 WL 572875, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-concrete-products-corp-v-turner-construction-co-ca4-2010.