WMS Const., Inc. v. Palm Springs Mile Assoc., Ltd.
This text of 762 So. 2d 973 (WMS Const., Inc. v. Palm Springs Mile Assoc., Ltd.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
WMS CONSTRUCTION, INC., Appellant,
v.
PALM SPRINGS MILE ASSOCIATES, LTD. and North American Specialty Insurance Company, Appellees.
District Court of Appeal of Florida, Third District.
*974 Frese, Nash & Torpy and Lisa L. Hogreve (Melbourne); Akerman, Senterfitt & Eidson and Kimberly A. Ashby, Orlando, for appellant.
Zarco & Pardo and Elissa Gainsburg, Miami, for appellees.
Before LEVY, FLETCHER, and RAMIREZ, JJ.
FLETCHER, Judge.
WMS Construction, Inc. [Subcontractor] appeals a final summary judgment determining that it failed to comply with a mandatory notice provision of the Construction Lien Law, chapter 713, part I, Florida Statutes (1997), thus is precluded from seeking recovery for labor and materials it supplied to Palm Springs Mile Associates, Inc. [Owner]. The controlling question is whether the payment bond issued to Noland Construction, Inc. [General Contractor] by North American Specialty Insurance Company [Surety] is a conditional payment bond,[1] or is, as held by the trial court, an unconditional payment bond.[2] For the reasons which follow, we reverse.
First, we note that the fundamental purpose of the Construction Lien Law is to protect those who have provided *975 labor and materials for the improvement of real property. Kettles v. Charter Mortgage Co., 337 So.2d 1012 (Fla. 3d DCA 1976). It is to be construed favorably so as to give laborers and suppliers the greatest protection compatible with justice and equity. See Crane Co. v. Fine, 221 So.2d 145 (Fla.1969)(superseded by statute on other grounds as stated in Pilot Elec. Constr. Co. v. Waters, 384 So.2d 61 (Fla. 1st DCA, 1980)). In obtaining this protection a subcontractor must be certain it strictly complies with the statutory provisions by which it seeks affirmative relief. Kettles, 337 So.2d 1012. One of the questions that a subcontractor must successfully resolve, or risk the loss of its compensation, is whether the payment bond issued to the general contractor by the surety is a conditional or an unconditional one. Depending upon that distinction is the procedure (including notice requirements) that a subcontractor must follow in order to secure its legal recourse in the event of nonpayment by the contractor.[3] Here the trial court concluded that the surety bond issued to the General Contractor is an unconditional one and the Subcontractor failed to comply with the applicable procedure for recovery.
Section 713.23(1)(a), Florida Statutes (1997), provides for unconditional payment bonds. It reads in pertinent part:
"The payment bond required to exempt an owner under this part shall be furnished by the contractor in at least the amount of the original contract price before commencing the construction of the improvement under the direct contract, and a copy of the bond shall be attached to the notice of commencement when the notice of commencement is recorded. The bond shall be ... conditioned that the contractor shall promptly make payments for labor, services, and material to all lienors under the contractor's direct contract."
Under this section the lien for a subcontractor's labor, services, and materials attaches to the bond, and an owner's property is exempt therefrom. If a contractor fails to pay lienors under its contract with the owner, then the surety is unconditionally liable for payment to the unpaid lienors,[4] so long as the lienors meet the notice and other requirements relating to unconditional bonds.
On the other hand, a general contractor may avail itself of section 713.245(1), Florida Statutes (1997), which permits a general contractor to provide a conditional surety bond:
"[I]f the contractor's written contractual obligation to pay lienors is expressly conditioned upon and limited to the payments by the owner to the contractor,[5] the duty of the surety to pay lienors will be coextensive with the duty of the contractor to pay, if the bond contains on the front page, in at least 10-point type, the statement:
THIS BOND ONLY COVERS CLAIMS OF SUBCONTRACTORS, SUB-SUBCONTRACTORS, SUPPLIERS, AND LABORERS TO THE EXTENT THE CONTRACTOR HAS BEEN PAID FOR THE LABOR, SERVICES, OR MATERIALS SUPPLIED BY SUCH PERSONS. THIS BOND DOES NOT PRECLUDE YOU FROM SERVING A NOTICE TO OWNER OR FILING A CLAIM OF LIEN ON THIS PROJECT."
Thus, under section 713.245, a contractor can limit its (and its surety's) exposure to payments actually made by an owner to the contractor, by entering into the statutorily defined contract and providing a bond with the 10-point type statement. *976 Under this section an owner's property is not exempt from subcontractors' liens. Section 713.245(3), Florida Statutes (1997). There lies a subcontractor's means of protection in a conditional bond situation in which the owner fails to pay the general contractor (and thus neither the general contractor nor the surety is required to pay the subcontractor).
In the instant case, the payment bond contains the "10-point type" conditional statement from section 713.245. This "pay-when-paid" language limits the Surety's liability to the payments made by the Owner. Under section 713.245, the Owner's property is not exempt from the Subcontractor's lien by which the Subcontractor seeks recovery. The notice and other requirements applicable to section 713.23 unconditional bonds are not relevant.
The instant contract between the General Contractor and the Subcontractor includes paragraph 12.1 which states:
"Final payment, constituting the entire unpaid balance of the Subcontract Sum, shall be made by the Contractor to the Subcontractor when the Subcontractor's Work is fully performed in accordance with the requirements of the Contract Documents, the Architect has issued a Certificate for Payment covering the Subcontractor's completed Work and the Contractor has received payment from the Owner." [emphasis supplied.]
(R.76).
Exhibit D to the instant contract states in full:
"Upon final payment a sworn statement with supporting waiver of lien from your material suppliers and/or subcontractors must be furnished with your final waiver of lien. A sworn statement must be furnished to us listing major material suppliers and subcontractors and the amounts of their contracts at the time of first payout. Interim payments require partial waivers with supporting material supplier's waivers in exchange for payment. Your payments are made in accordance with our interim draws as we show you on our sworn statement with your percentage of completion as we estimate it at the time of our billing to the owner. This may not conform to your billing to us. No funds will be owed to the subcontractor unless the General Contractor is paid by the owner in accordance to the sworn statement. The subcontractor fully understands that in event of non payment by the owner to the General Contractor, the subcontractor has legal recourse against the owner through the mechanic's Lien Laws or other legal procedures for their correct monies due." [emphasis supplied.]
(R.81).
The Florida Supreme Court has held similar language to be unambiguous and to require payment from an owner to a general contractor before payment became due to a subcontractor. See DEC Electric, Inc. v. Raphael Construction Corp., 558 So.2d 427 (Fla.1990). Here then, both the payment bond and the contract[6]
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
762 So. 2d 973, 2000 WL 691136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wms-const-inc-v-palm-springs-mile-assoc-ltd-fladistctapp-2000.