Trump Endeavor 12, LLC v. Fernich, Inc., Etc.

216 So. 3d 704, 2017 WL 1363950, 2017 Fla. App. LEXIS 5075
CourtDistrict Court of Appeal of Florida
DecidedApril 12, 2017
Docket16-1065 & 16-1865
StatusPublished
Cited by3 cases

This text of 216 So. 3d 704 (Trump Endeavor 12, LLC v. Fernich, Inc., Etc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trump Endeavor 12, LLC v. Fernich, Inc., Etc., 216 So. 3d 704, 2017 WL 1363950, 2017 Fla. App. LEXIS 5075 (Fla. Ct. App. 2017).

Opinion

EMAS, J.

In these consolidated appeals, appellant Trump Endeavor 12, LLC (“Trump”) seeks review of two trial court orders: (1) a final judgment of foreclosure of a construction lien by appellee, Fernich, Inc., d/b/a The Paint Spot (“Paint Spot”); and (2) a final judgment awarding attorney’s fees and costs to Paint Spot. 1 We affirm, holding that competent substantial evidence supports the trial court’s determination that Paint Spot substantially complied with the statutory lien provisions in section 713.06(2), Florida Statutes (2013), and that Trump failed to establish it was adversely affected by any omission or error in the Notice to Owner (“NTO”).

BACKGROUND AND PROCEEDINGS BELOW

On October 21, 2014, Paint Spot recorded a Claim of Lien against the Trump National Doral Miami, owned by Trump. When Trump failed to pay $32,535.87 owed to Paint Spot for paint and related materials, Paint Spot filed a complaint to foreclose its Claim of Lien. Trump asserted that the Claim of Lien was invalid because it identified the wrong contractor on the project and because Paint Spot failed to comply with the provisions of section 713.06(2)(a).

The evidence and testimony at trial, taken in a light most favorable to upholding *706 the judgment on appeal, 2 reveals the following:

The project at the Trump National Doral Miami consisted of two parts: renovations to the property’s ten lodges (“the Lodge Project”) and renovations to the clubhouse (“the Clubhouse Project”). Both the Lodge Project and the Clubhouse Project share the same property address: 4400 NW 87 Avenue, Miami, Florida.

Trump hired a different general contractor for each of the two projects: Straticon, LLC for the Lodge Project, and T&G Constructors for the Clubhouse Project. Stra-ticon hired M&P Reynolds, Inc. (“M&P”) to furnish paint and labor for the Lodge Project, which in turn contracted with Paint Spot to supply paint and related materials. Paint - Spot negotiated pricing with M&P, which M&P submitted to Stra-ticon, 3 Trump then approved M&P’s price quotations. 4 Trump recorded multiple Notices of Commencement (“NOC”) for the Lodge Project, identifying Straticon as the general contractor for that project, and later recorded a NOC naming T&G as the general contractor for the Clubhouse Project. All the NOCs disclosed the same address for both projects: 4400 NW 87 Avenue, Miami, Florida.

Prior to supplying materials to the Lodge Project, Paint Spot’s president, Juan Carlos Enriquez, visited the project site for the purpose of obtaining a copy of the NOC, so that Paint Spot could use it to prepare its statutory NTO. Enriquez made it a habit to obtain the NOC from the owner of the project, rather than the general contractor or subcontractor, to ensure that his NTO contained the correct information. When Enriquez asked for the NOC from Trump’s Director of Construction, Frank Sanzo, Sanzo mistakenly handed Enriquez the T&G NOC instead of the Straticon NOC. At this point, Enriquez was unaware that there was a different general contractor for each of the two projects.

Using this T&G NOC, Paint Spot prepared and timely served its NTO on Trump and on T&G by certified mail in November 2013. 5 Paint Spot began supplying materials to the Lodge Project on November 8, 2013.

On November 21, 2013, Straticon’s project manager, Jamie Gram, sent an email to Claudio Bravo, a Benjamin Moore representative and Paint Spot’s paint distributor. In this email, Straticon’s project manager advised Bravo that, after reviewing Paint Spot’s NTO, he determined that it had incorrectly been filed under the T&G NOC, and that the NTO needed to be corrected and addressed to Straticon as the general contractor. Attached to this email was a copy of Paint Spot’s NTO.

Bravo forwarded Straticon’s email to Enriquez and, two days later, Enriquez responded that it was being taken care of. However, due to oversight, Enriquez never prepared or served a corrected NTO on Straticon. Nevertheless, there can be no *707 doubt that, as of November 21, 2013 (at the latest), Straticon was in possession, and had actual knowledge, of the NTO, as it was Straticon’s own project manager who reviewed the NTO, discovered the discrepancy, and sent the email alerting Benjamin Moore and Paint Spot of the error.

Notwithstanding the error on the face of the NTO, Straticon knew that Paint Spot was suppling materials to the Lodge Project and knew that Paint Spot was M&P’s only paint supplier for the project. Paint Spot attended meetings with Straticon regarding the Lodge Project, and Paint Spot submitted signed partial waivers of lien to M&P as a precondition to receiving payment for the paint materials. Straticon would not pay M&P without M&P submitting partial waivers from its suppliers.

Paint Spot continued supplying materials to the Lodge Project through September of 2014, at which time M&P stopped working on the project because it was not being paid by Straticon. At the time M&P left the Lodge Project, $32,535.87 worth of paint and supplies delivered by Paint Spot, which had not been paid for, remained at the Lodge Project. Trump used those materials to finish the painting work, but Paint Spot was never paid for those items, resulting in the instant action to foreclose the lien.

After a non-jury trial, the trial court determined, inter alia, that (1) Trump and Straticon had actual knowledge of Paint Spot’s NTO; (2) Trump and Straticon had actual knowledge that Paint Spot was supplying materials to Straticon (through M&P) for the Lodge Project; (3) Trump was estopped from invalidating Paint Spot’s NTO because Trump caused Paint Spot to rely to its detriment on the T&G NOC; and (4) Paint Spot substantially complied with the statutory requirements of section 713.06 and therefore its NTO was valid and its lien enforceable. The trial court thereafter entered final judgment in favor of Paint Spot, and subsequently entered final judgment awarding attorney’s fees to Paint Spot pursuant to section 713.29, Florida Statutes (2013). These consolidated appeals followed.

Trump asserts that strict compliance with 713.06(2)(a) was required of Paint Spot, and that the trial court erred in enforcing the lien because Paint Spot failed to strictly comply with that provision, despite having knowledge, prior to the statutory deadline, that the NTO was defective. Trump contends that neither detrimental reliance nor substantial compliance applies here to validate, or permit enforcement of, the lien.

To the extent that we are reviewing the trial court’s factual determinations, our standard of review is whether there is competent, substantial evidence to support the judgment. James P. Driscoll, Inc. v. Gould, 521 So.2d 301 (Fla. 3d DCA 1988). To the extent that we are reviewing the trial court’s application of the law to its factual determinations, our standard of review is de novo. Stock Bldg. Supply of Fla. Inc. v. Soares Da Costa Constr., 76 So.3d 313, 316 (Fla 3d DCA 2011).

ANALYSIS

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
216 So. 3d 704, 2017 WL 1363950, 2017 Fla. App. LEXIS 5075, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trump-endeavor-12-llc-v-fernich-inc-etc-fladistctapp-2017.