Professional Plast. v. Bridgeport-Strasberg

940 So. 2d 444, 2006 WL 1931199
CourtDistrict Court of Appeal of Florida
DecidedJuly 12, 2006
Docket5D03-2572
StatusPublished
Cited by6 cases

This text of 940 So. 2d 444 (Professional Plast. v. Bridgeport-Strasberg) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Professional Plast. v. Bridgeport-Strasberg, 940 So. 2d 444, 2006 WL 1931199 (Fla. Ct. App. 2006).

Opinion

940 So.2d 444 (2006)

PROFESSIONAL PLASTERING & STUCCO, INC., Appellant,
v.
BRIDGEPORT-STRASBERG JOINT VENTURE, et al., Appellee.

No. 5D03-2572.

District Court of Appeal of Florida, Fifth District.

July 12, 2006.
Rehearing Denied October 24, 2006.

*445 Phillip C. Dozier of Phillip C. Dozier, P.A., Apopka, for Appellant.

William L. Grant and Earnest DeLoach, Jr., of Shutts & Bowen, LLP, Orlando, for Appellee.

ON MOTION FOR REHEARING EN BANC

THOMPSON, J.

Professional Plastering & Stucco, Inc. ("Professional Plastering") moves for rehearing of our reversal of the trial court's order, which granted summary judgment to General Accident Insurance Company of America ("General Accident"). Prof'l Plastering & Stucco, Inc. v. Bridgeport-Strasberg Joint Venture, 30 Fla. L. Weekly D299, 2005 WL 176601 (Fla. 5th DCA Jan. 28, 2005). We grant the motion for rehearing, withdraw our previous opinion, and substitute in its place the following opinion that affirms in part and reverses in part the trial court's order.

Professional Plastering was the subcontractor on a construction project. It sued the contractor in count one for breach of contract, concerning money owed for working on the project. In count two, it sued General Accident on a bond issued in connection with the project. Professional Plastering alleged that it was owed $88,387.12 for unpaid labor and materials and sought payment from General Accident under the bond. Professional Plastering claimed that work on the construction project had begun before the bond was issued and the notice of commencement was filed. It alleged that the bond was a common law bond and that the notice and other requirements of section 713.23, Florida Statutes (1999), did not apply. The court, however, ruled that the bond was a statutory bond and dismissed count two with prejudice, even though the court indicated during the summary judgment hearing that it was not going to decide whether proper bond notices were given because the dispute over notice was not yet ripe for decision.

The issue framed for our consideration, is whether the bond in this case was a statutory bond or common law bond. We follow the Second District's analysis in Bridgeport, Inc. v. Tampa Roofing Co., 903 So.2d 306, 309 (Fla. 2d DCA 2005) (Bridgeport), and hold that the trial court correctly found that the bond in this case was a statutory bond, and appropriately granted General Accident's motion for summary judgment on Professional Plastering's action on a common law bond claim. Because the court specifically indicated it was not going to decide whether Professional Plastering properly and timely served the notices of nonpayment, and as there appears to be an affidavit in the file that controverts the issue of proper notification, we reverse that part of the order dismissing count two with prejudice.

The payment bond issued on 21 July 1999 was derived from an American Institute of Architects boilerplate form. Its terms and coverage were substantially similar to that outlined in section 713.23(3). See Bridgeport, 903 So.2d at 308; see also Hawaiian Inn of Daytona Beach, Inc. v. Dunn, 342 So.2d 132, 133 (Fla. 1st DCA 1977) (holding that the bond "was intended to and did substantially comply with [s]ection 713.23"; therefore, because its conditions "were not broader and more protective than the statute required," the contention that the bond was a common law bond failed). The bond's *446 notice provision stated that no claimant could commence an action on the bond

[u]nless claimant, other than one having a direct contract with the Principal, shall have given written notice to two of any of the following: the Principal, the Owner, or the Surety . . . within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the materials for which said claim is made. . . .

However, the top of this bond was stamped with the following language: "This bond hereby is amended so that the provisions and limitations of section 255.05 or section 713.23 . . ., whichever is applicable, are incorporated herein by reference."[1] In compliance with sections 713.13 and 713.23(1), the bond was attached to the notice of commencement recorded and entered on 30 July 1999.

Section 713.02(6), Florida Statutes (1999), provided that an owner could avoid construction liens on its property, other than that of the contractor furnishing a payment bond to the owner, by requiring the contractor to furnish a payment bond under section 713.23, which provided:

(1)(a) The payment bond required to exempt an owner under this part shall be furnished by the contractor in at least the amount of the original contract price before commencing the construction of the improvement under the direct contract, and a copy of the bond shall be attached to the notice of commencement when the notice of commencement is recorded. The bond shall be executed as surety by a surety insurer authorized to do business in this state and shall be conditioned that the contractor shall promptly make payments for labor, services, and material to all lienors under the contractor's direct contract. Any form of bond given by a contractor conditioned to pay for labor, services, and material used to improve real property shall be deemed to include the condition of this subsection.
(b) The owner, contractor, or surety shall furnish a true copy of the bond at the cost of reproduction to any lienor demanding it. Any person who fails or refuses to furnish the copy without justifiable cause shall be liable to the lienor demanding the copy for any damages caused by the refusal or failure.
(c) Either before beginning or within 45 days after beginning to furnish labor, materials, or supplies, a lienor who is not in privity with the contractor, except a laborer, shall serve the contractor with notice in writing that the lienor will look to the contractor's bond for protection on the work. If a notice of commencement is not recorded, or a reference to the bond is not given in the notice of commencement, and in either case if the lienor not in privity with the contractor is not otherwise notified in writing of the existence of the bond, the lienor not in privity with the contractor shall have 45 days from the date the lienor is notified of the existence of the bond within which to serve the notice. . . .
(d) In addition, a lienor is required, as a condition precedent to recovery under the bond, to serve a written notice of nonpayment to the contractor and the surety not later than 90 days after the final furnishing of labor, services, or materials by the lienor. . . . The time period for serving a written notice of nonpayment shall be measured from the last *447 day of furnishing labor, services, or materials by the lienor . . .
(e) No action for the labor or materials or supplies may be instituted or prosecuted against the contractor or surety unless both notices have been given. . . . The time period for bringing an action against the contractor or surety on the bond shall be measured from the last day of furnishing labor, services, or materials by the lienor . . .
***
(2) The bond shall secure every lien under the direct contract accruing subsequent to its execution and delivery, except that of the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stock Building Supply of Florida, Inc. v. Soares Da Costa Construction Services, LLC
76 So. 3d 313 (District Court of Appeal of Florida, 2011)
Parc Central Aventura East Condominium v. Victoria Group Services, LLC
54 So. 3d 532 (District Court of Appeal of Florida, 2011)
J.C. Gibson Plastering Co. v. XL Specialty Insurance
521 F. Supp. 2d 1326 (M.D. Florida, 2007)
Wagner v. Orange County
960 So. 2d 785 (District Court of Appeal of Florida, 2007)
Delta Fire Sprinklers v. ONEBEACON INS.
937 So. 2d 695 (District Court of Appeal of Florida, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
940 So. 2d 444, 2006 WL 1931199, Counsel Stack Legal Research, https://law.counselstack.com/opinion/professional-plast-v-bridgeport-strasberg-fladistctapp-2006.