J.C. Gibson Plastering Co. v. XL Specialty Insurance

521 F. Supp. 2d 1326, 2007 U.S. Dist. LEXIS 74826
CourtDistrict Court, M.D. Florida
DecidedOctober 8, 2007
Docket3:07-cr-00268
StatusPublished
Cited by1 cases

This text of 521 F. Supp. 2d 1326 (J.C. Gibson Plastering Co. v. XL Specialty Insurance) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.C. Gibson Plastering Co. v. XL Specialty Insurance, 521 F. Supp. 2d 1326, 2007 U.S. Dist. LEXIS 74826 (M.D. Fla. 2007).

Opinion

ORDER

VIRGINIA M. HERNANDEZ COVINGTON, District Judge.

This cause comes before the Court pursuant to Gibson’s Dispositive Motion for Partial Summary Judgment as to Count I of the Complaint (Doc. # 5), filed on April 25, 2007. XL Specialty Insurance Company and XL Reinsurance America, Inc., (collectively referred to herein as “XL”) jointly filed a response on May 9, 2007. (Doc. # 8). On July 31, 2007, though, Gibson filed an amended complaint dropping two counts. (Doc. #20.) Gibson’s only remaining count is a claim for payment under a surety bond issued by XL. (Doc. # 20.) Gibson’s motion is addressed to the only remaining count. Gibson’s motion would thus be fully dispositive of this case, but for the fact that XL filed a counterclaim on August 9, 2007, (Doc. # 21). 1 For the reasons that follow, Gibson’s motion for partial summary judgment is due to be granted.

I. Background

This litigation arises out of Gibson’s work as a subcontractor on a housing development project. The Auchter Company *1328 was the general contractor. XL as surety issued a payment bond insuring payment to subcontractors in the event Auchter failed to pay. (See Doc. # 1-3.) Gibson alleges that Auchter failed to pay amounts due, and Gibson is now suing XL on the bond to recover those amounts.

Paragraph 4 of the bond details the procedure a subcontractor must follow to make a claim under the bond:

4. The Surety shall have no obligation to Claimants under this bond until:
4.1 Claimants who are employed by or have a direct contract with the Contractor have given notice to the Surety (at the address described in Paragraph 12) and sent a copy, or notice thereof, to the Owner stating that a claim is being made under this Bond and, with substantial accuracy, the amount of the claim.

(Doc. # 1-3, at 2.) Accordingly, the bond requires a subcontractor to send notice of its claim to the owner of the development as well as to the surety. This notice must state the amount of the claim with substantial accuracy.

Once a subcontractor has satisfied the notice requirement, the bond requires XL promptly to determine and pay — or arrange for payment of — the undisputed amount of the claim:

6. When the Claimant has satisfied the conditions of Paragraph 4, the Surety shall promptly and at the Surety’s expense take the following actions:
6.1 Send an answer to the Claimant, with a copy to the Owner, within 45 days after receipt of the claim, stating the amounts that are undisputed and the basis for challenging any amounts that are disputed.
6.2Pay or arrange for payment of any undisputed amounts.

(Doe. # 1-3, at 2.)

Gibson submitted its final billing to Au-chter on January 9, 2007. (Doc. # 5, at 2.) Auchter did not pay, and Gibson sent XL a claim under the bond for $736,416.66. (Doc. # 1-4.) Gibson sent this claim on February 9, 2007,' and sent copies to Au-chter and the owner of the development. (Doc. # 1-4.) On February 12, 2007, Gibson sent XL and Auchter a fourteen-page letter detailing the factual and legal bases of Gibson’s claim. (Doc. # 1-8.) This letter explained that Gibson had previously submitted all records supporting the amount of the claim to a named employee of Auchter. (Doc. # 1-8, at 14.) XL wrote back on February 22, 2007, requesting copies of all cost records supporting the amount of Gibson’s claim. (Doc. # 8-3, at 26.) XL’s letter additionally advised that XL was contacting Auchter to get Auchter’s position on the claim. (Doe. 8-3, at 26; see also Doc. # 8, at 3.) On March 20, 2007, Gibson sent XL the requested materials. (See Doc. # 1-10.) The next day, XL wrote Gibson acknowledging receipt of the materials. (Doc. # 8-3, at 27.)

Gibson wrote XL on April 3, 2007, and explained Gibson’s position that XL breached its “obligations under [Paragraph] 6 of the Payment Bond by failing to make an appropriate response within 45 days of the receipt of Gibson’s claim.” (Doc. # 5-4, at 60.) XL responded promptly on April 4, 2007, that the forty-five-day time period under Paragraph 6 did not begin to run until XL received the cost records on March 21, 2007. (Doc. # 8-3, at 31.) XL again wrote to Gibson on April 5, 2007. (Doc. # 8-3, at 32.) In this letter, XL noted that it was apparent a “legitimate dispute exists on the ... project.” (Doc. # 8-3, at 32.) The letter continued, “XL ... has not been ... em *1329 powered to act as the judge, juror or arbiter as it relates to said dispute. It is not up to XL to determine which party is correct or incorrect as it relates to same.” (Doc. # 8-3, at 32.) Accordingly, XL advised that Gibson would have to resolve the matter directly with Auchter. (Doc. # 8-3, at 32.)

Gibson filed this action on April 4, 2007. (Doc. #1.) Gibson’s complaint alleged three counts, but Gibson subsequently amended its complaint to eliminate two of these counts. (Doc. # 20.) Gibson’s amended complaint now pleads only a claim for payment under the bond. (Doc. #20.) In response to Gibson’s amended complaint, XL brought a three-count counterclaim. (Doc. #21.) In its first two counts, XL seeks to enforce Auchter’s rights under Auchter’s subcontract with Gibson. (Doc. # 21, at 8-10.) XL claims Gibson breached the subcontract. (Doc. # 21, at 8-10.) XL alleges it can enforce Auchter’s rights for two reasons. First, Auchter assigned its rights under the subcontract to XL. (Doc. #21, at 8.) Second, XL can proceed under the doctrine of equitable subrogation. (Doc. # 21, at 9.) XL’s third count is a claim for common law indemnity alleging that XL paid losses occasioned by Gibson’s breach of the subcontract. (Doc. # 21, at 10-11.)

Gibson’s motion for partial summary judgment is addressed only to Gibson’s claim against XL, and not to XL’s counterclaim. Accordingly, this Order does not render judgment upon the whole case. See Fed.R.Civ.P. 56(d). Instead, further litigation is necessary to adjudicate XL’s counterclaims.

II. The Parties’ Arguments

The dispute raised by Gibson’s motion for partial summary judgment is very simple. Gibson argues that its February 9, 2007, notice complied with Paragraph 4 of the bond, thus triggering XL’s obligations under Paragraph 6. Gibson submits that XL failed to meet those obligations. The remedy for that failure, Gibson argues, is that XL is barred from now challenging Gibson’s claim.

On the other side, XL argues that Gibson’s February 9 notice did not comply with Paragraph 4. Instead, according to XL, Gibson did not comply with Paragraph 4 until it sent its cost records on March 20, 2007. As a result, XL’s obligations under Paragraph 6 only began when Gibson received the March 20, 2007, notice. 2 Alternatively, Gibson claims it substantially complied with the requirements of Paragraph 6 by making an adequate response only a few days late.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sloan & Co. v. Liberty Mutual Insurance
653 F.3d 175 (Third Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
521 F. Supp. 2d 1326, 2007 U.S. Dist. LEXIS 74826, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jc-gibson-plastering-co-v-xl-specialty-insurance-flmd-2007.