Sloan & Co. v. Liberty Mutual Insurance

653 F.3d 175, 2011 U.S. App. LEXIS 15798, 2011 WL 3250447
CourtCourt of Appeals for the Third Circuit
DecidedAugust 1, 2011
Docket10-1725, 10-1765
StatusPublished
Cited by35 cases

This text of 653 F.3d 175 (Sloan & Co. v. Liberty Mutual Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sloan & Co. v. Liberty Mutual Insurance, 653 F.3d 175, 2011 U.S. App. LEXIS 15798, 2011 WL 3250447 (3d Cir. 2011).

Opinion

OPINION OF THE COURT

AMBRO, Circuit Judge.

This case involves principally the interpretation of a construction subcontract. A dispute arose when a general contractor, Shoemaker Construction Company (“Shoemaker”), failed to pay a subcontractor, Sloan & Company (“Sloan”), the remaining balance on its subcontract. The appellant in this case, Liberty Mutual Insurance Company (“Liberty Mutual”), is the surety on the subcontract and the party Sloan has sued for payment on the surety bond. Sloan cross-appeals with respect to one aspect of its claim. For the reasons that follow, we reverse in part and remand for further proceedings consistent with this opinion as to Liberty Mutual’s appeal, and affirm the ruling on Sloan’s cross-appeal.

I. Background

Isla of Capri Associates LP (“IOC”) owned and developed waterfront condominiums in Philadelphia. Shoemaker contracted with IOC to build the project (the “prime contract”). Shoemaker then lined up various subcontractors that included Sloan, who agreed to perform drywall and carpentry work on the project (the “subcontract”). Payment for the subcontractors’ work was insured by a surety bond issued by Liberty Mutual. At the project’s completion, IOC refused to pay Shoemaker nearly $6.5 million owed under the prime contract. Of that amount, $5 million was due the subcontractors. IOC claimed it was withholding money for several reasons, one of which was that some of the subcontractors’ work was untimely and deficient. 1 Shoemaker then refused to pay Sloan the full amount of the remaining balance Sloan claimed was due under their subcontract — $1,074,260.

In May 2007, Shoemaker sued IOC to recover the balance on the prime contract. Sloan then made a claim against Liberty Mutual for payment on the surety bond. Five weeks later, Liberty Mutual denied the claim in its entirety, reserving all rights and defenses. As a ground for denying any payment obligation to Sloan, Liberty Mutual asserted that one of the subcontract’s terms, found in Paragraph 6.f, conditioned Sloan’s right to payment on Shoemaker’s receipt of payment from IOC. Relying on that interpretation of the subcontract, Liberty Mutual claimed that Sloan was not entitled to payment from Shoemaker because IOC had not paid Shoemaker.

In December 2007, Sloan filed a complaint against Liberty Mutual in the District Court. Sloan moved for summary judgment in the amount of $1,074,260.09, plus interest and taxable costs. Liberty Mutual cross-motioned for summary judgment. It argued that even if Sloan were entitled to payment, the amount at most *178 was $785,067 because of various offsets. Sloan’s claim, and Liberty Mutual’s alleged offsets, broke down as follows:

Liberty Mutual’s Undisputed Amount
_Sloan’s Claim Alleged Offsets_in Controversy
_$1,074,260_
Legal fees (attributable
to Sloan)_;_$ 16,579 2 _
Repairs_'_$ 40,370_
Deficiencies_$ 24,600_
Time & Materials Provided ._$ 66,324_
Lump Sum Proposals
Performed_;_$141,320_
Subtotal of offsets
claimed_$289,193_
_$785,067

Meanwhile, Shoemaker’s lawsuit against IOC hit a dead end. Shoemaker learned that IOC’s financial situation made it unable to satisfy a judgment for the entire claim even if one were awarded to Shoemaker. It entered into a settlement agreement with IOC for $1 million, apparently all that IOC was able to pay. 3 Shoemaker offered its subcontractors their pro rata share of amounts owed in exchange for a release of claims, but Sloan did not agree to that arrangement and continued to press its suit against Liberty Mutual. 4

In August 2009, the District Court granted partial summary judgment in favor of Sloan for $785,067 (the “First Judgment”). It rejected Liberty Mutual’s interpretation of the subcontract as conditioning Sloan’s right to payment on IOC’s payment to Shoemaker. The Court allowed the parties to conduct additional discovery as to whether Sloan was entitled to any additional amounts.

After discovery, the parties again moved for summary judgment. The Court granted partial summary judgment in favor of Sloan on the issue of legal fees and deficiencies, and awarded prejudgment interest (on that amount as well as on the previous sum awarded — $785,067), for an additional sum aggregating $145,895 (the “Second Judgment”). 5

In lieu of trial on the remaining amounts, the parties stipulated to the entry of a third and final judgment in favor of Sloan on February 12, 2010 (the “Final Judgment”). Included within the Final Judgment were sums set forth in the First Judgment, the Second Judgment, and the *179 additional amount of $179,876 ($156,224, plus prejudgment interest of $23,652). 6 The combined amounts in the Final Judgment (excluding interest) were $91,790 less than Sloan’s initial claim of $1,074,260.

The parties agreed to preserve their rights to appeal all three of the District Court’s judgments, and Liberty Mutual does so, challenging the District Court’s interpretation of the subcontract. It argues that Shoemaker’s obligation to pay Sloan was conditioned on its receipt of payment from IOC, or, put another way, Sloan was entitled to be paid only whatever amount Shoemaker received from IOC for Sloan’s work. Liberty Mutual also contests the District Court’s determination on litigation costs. It argues it is entitled to deduct Sloan’s share of the legal fees stemming from Shoemaker’s suit against IOC. In addition, Sloan cross-appeals the $91,790 shortfall from its initial claim. It argues that Liberty Mutual waived the right to claim offsets by failing to state their bases within 45 days of Sloan’s initial claim. 7

II. Discussion

Summary judgment is in order when “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R.Civ.P. 56(a). Our review over the District Court’s grant of summary judgment is plenary. Lawrence v. City of Phila., 527 F.3d 299, 310 (3d Cir.2008). We also exercise plenary review over the District Court’s interpretation of state law. Emerson Radio Corp. v. Orion Sales, Inc., 253 F.3d 159, 162 (3d Cir.2001).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kimmel's Coal and Packaging, Inc.
M.D. Pennsylvania, 2021
FARHANGUI v. GROSSINGER
E.D. Pennsylvania, 2021
Gotham v. Basement Care, Inc.
2019 Ohio 3872 (Ohio Court of Appeals, 2019)
Young Elec. Contractors, Inc. v. Dustin Constr., Inc.
185 A.3d 170 (Court of Appeals of Maryland, 2018)
Superior Steel, Inc. v. Ascent at Roebling's Bridge, LLC
540 S.W.3d 770 (Missouri Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
653 F.3d 175, 2011 U.S. App. LEXIS 15798, 2011 WL 3250447, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sloan-co-v-liberty-mutual-insurance-ca3-2011.