Traxys North America LLC v. Concept Mining Incorporated

510 F. App'x 262
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 19, 2013
Docket11-2054
StatusUnpublished
Cited by3 cases

This text of 510 F. App'x 262 (Traxys North America LLC v. Concept Mining Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Traxys North America LLC v. Concept Mining Incorporated, 510 F. App'x 262 (4th Cir. 2013).

Opinion

Affirmed in part and reversed in part by unpublished opinion. Judge Agee wrote the opinion, in which Judge DUNCAN and Judge DAVIS concur.

Unpublished opinions are not binding precedent in this circuit.

AGEE, Circuit Judge:

In this diversity-based breach of contract action, Concept Mining, Inc. (“Concept”) 1 appeals a damages award of $4,167,760, and a prejudgment interest, attorneys’ fees, and litigation expenses award of $547,518.19 in favor of Traxys North America, LLC (“Traxys”). The district court held that Concept breached its 2009 obligation to deliver coal to Traxys and that this breach excused Traxys from having to exercise an option to extend the obligation through 2010. It thus held Concept liable in damages to Traxys for both 2009 and 2010. Pursuant to the parties’ agreement, Traxys was also entitled to recover prejudgment interest and “legal costs” arising from the breach. The district court construed this provision to include attorneys’ fees, expert witness fees, and certain witness travel expenses.

For the reasons set forth below, we affirm the district court’s judgment regarding the 2009 breach and attendant damages, but we reverse the district court’s judgment as to a breach in 2010 or any resulting damages. In light of this disposition, and because we conclude the district court misconstrued the provision regarding recovery of “legal costs,” we also vacate the district court’s judgment concerning prejudgment interest, attorneys’ fees, and certain litigation expenses, and remand the case in order for the district court to recalculate an appropriate award.

I.

In 2007, Concept and Traxys entered into a contract (the “Contract”) in which Concept agreed to supply Traxys with approximately 4,000 tons of coal per month for a total of approximately 48,0000 tons in 2008. A Special Provisions Clause set forth reciprocal options to extend the Contract beyond 2008:

This transaction has an additional two year term that is an integral part of the contract with a $5.00 (Five Dollar) collar for each year. Commencing on November 1, 2008, the Parties shall mutually agree to negotiate in good faith and attempt to agree upon a new Contract to be in effect for Contract year 2009.... If ... Traxys is unwilling to pay $88.00 per ton fob car as a Base Price[,] ... then [Concept] and [Traxys] agree this Agreement shall terminate on December 31, 2008.

(J.A. 28.)

In the fall of 2008, Traxys elected to extend the Contract one additional year when it sent Concept a letter agreeing to pay the high-end $5.00 collar of $83.00 per ton fob car of coal in 2009. Although the parties remained in contact throughout

2009, Concept did not deliver any coal to Traxys toward the 2009 obligation. Neither party exercised the option to extend the Contract into 2010. 2

In May 2010, Traxys filed the underlying complaint in the United States District Court for the Western District of Virginia *264 alleging Concept had breached the Contract by failing, inter alia, to supply coal in 2009 and 2010. 3 Concept then filed a counterclaim alleging Traxys breached the Contract by thwarting delivery of the coal and thereby violating its duty of good faith and fair dealing. Both parties asserted they were entitled to damages based on the other party failing to fulfill its obligations during 2009 and 2010, which resulted in no coal being shipped for either year. At the heart of these claims lay the interpretation of the Special Provisions Clause, whether a binding Contract existed in 2009 and/or 2010, and which party (if either) breached the Contract in 2009 and/or 2010.

Following a bench trial, the district court entered judgment upon an opinion in favor of Traxys on its claim and against Concept’s counterclaim. Traxys N. Am. v. Concept Mining, Inc., 808 F.Supp.2d 853 (W.D.Va.2011). The district court found that Concept’s lead coal buyer for the Americas, Liem Hazoumé, had misinterpreted the Contract, which mistakenly “led him, on behalf of Concept, to take the position with Traxys that there was no binding agreement for 2009.” Id. at 860. It further found that “Concept was obligated to deliver the 2009 tonnage” as a result of Traxys’ exercise of the 2009 option, and that Concept materially breached the Contract by failing to deliver coal toward its 2009 obligation. Id. The district court concluded that Traxys’ remedies for the breach included awaiting performance, and that it did not violate a duty of good faith by remaining silent, despite the fact that its “silence may have been in part strategic and sensitive to market considerations.” Id. at 862.

The district court rejected Concept’s argument that “Traxys’ refusal to communicate ... frustrated Concept’s ability to fulfill its obligations.” Id. at 863. This is so, the court concluded, because Traxys “advised Concept of its ability to accept any proposed delivery dates,” id. at 864, and yet Concept never sent Traxys any such dates and thus had not “demonstrated its willingness to perform and [thereby] signified its intent to remedy its delinquency.” Id. at 863.

In addition, the district court found that “[b]ecause Concept repudiated any obligation to deliver coal under the Contract after 2008 and was in breach of the Contract throughout 2009, Traxys was not required to give any notice of an election to take the 2010 tonnage.” Id. at 860. The court concluded that Concept’s “ongoing breach throughout 2009 had legal consequence for the parties’ status in 2010.” Id. at 865. Namely, it held that because Concept was in breach of contract in 2009, Concept had no right to demand performance of condition precedents to performance such as requiring Traxys to make “a futile election on the 2010 tonnage.” Id. The court concluded Concept was hable to Traxys for its failure to deliver any coal during 2010.

On appeal, the parties do not dispute the district court’s method of calculating damages. Broken out by year, the damages award consisted of $46,696 for 2008, $800,367 for 2009, and $3,324,697 for 2010, for a total award of $4,167,760. Id. at 866.

After entry of the damages judgment, Traxys moved for prejudgment interest, attorneys’ fees, and other litigation ex *265 penses. The Contract provided that in the event of Concept’s unexcused failure to perform, Concept would be obligated to pay “Legal Costs incurred by [Traxys].” (J.A. 27.) The parties disputed the definition of “Legal Costs,” and whether it included the attorneys’ fees and litigation expenses. The district court found “that the plain meaning of ‘Legal Costs’ as used in the Contract includes expenses incidental to litigation, such as attorneys’ fees and disbursements, as well as expert witness fees.” Traxys N. Am., LLC v. Concept Mining, Inc., Case No. 1:10CV00029, 2011 WL 4440412, 2011 U.S. Dist. LEXIS 108530 (W.D.Va. Sept. 22, 2011). It explained:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
510 F. App'x 262, Counsel Stack Legal Research, https://law.counselstack.com/opinion/traxys-north-america-llc-v-concept-mining-incorporated-ca4-2013.