Cambridge Technologies, Inc. v. Argyle Industries, Inc.

807 A.2d 125, 146 Md. App. 415, 48 U.C.C. Rep. Serv. 2d (West) 966, 2002 Md. App. LEXIS 154
CourtCourt of Special Appeals of Maryland
DecidedSeptember 9, 2002
Docket1519, September Term, 2001
StatusPublished
Cited by6 cases

This text of 807 A.2d 125 (Cambridge Technologies, Inc. v. Argyle Industries, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cambridge Technologies, Inc. v. Argyle Industries, Inc., 807 A.2d 125, 146 Md. App. 415, 48 U.C.C. Rep. Serv. 2d (West) 966, 2002 Md. App. LEXIS 154 (Md. Ct. App. 2002).

Opinion

SALMON, Judge.

In the fall of 1997, Argyle Industries, Inc. (“Argyle”), contracted to deliver 14,500 sets of parts to Cambridge Technologies, Inc. (“Camtec”). The parts were to be delivered in accordance with a schedule that was set forth in a purchase order. Camtec intended to assemble the parts manufactured by Argyle (and others) and to sell the assembled product to ■ the Department of Defense (“DOD”) in fulfillment of a contract it had with the U.S. government.

*419 Argyle did not meet the delivery schedule set forth in its contract with Camtec. Nevertheless, Argyle made some late deliveries, and Camtec did not complain about the fact that the delivery schedule was not being met. After Argyle had delivered approximately forty percent of the sets of parts it had promised, and after the deadline for supplying all the contracted-for parts had expired, the DOD cancelled its contract with Camtec — due to the latter’s tardiness in making its deliveries. Immediately after the DOD contract was can-celled, Camtec, in turn, cancelled its contract with Argyle.

Argyle filed a two-count complaint against Camtec in the Circuit Court for Dorchester County. The first count was for breach of contract, and the second was under a quantum meruit theory. Camtec filed an answer to the complaint, together with a counter-complaint, in which it alleged, inter alia, that Argyle’s tardiness in making delivery caused it to lose the DOD contract. The breach (allegedly) caused Camtec to make expenditures that would have otherwise been unnecessary and to lose the profits it would have otherwise made.

At the conclusion of a bench trial, the trial judge delivered a brief oral opinion in which he found that there had been “substantial compliance” with the contractual terms on Argyle’s part and awarded Argyle damages in the amount of $33,541.08 as to Count I. The damage award, purportedly, was based on figures supplied by Camtec.

The trial court disposed of the counterclaim with the following words: “The counterclaim is denied for failure of proof of damages.” Camtec filed this timely appeal and raises three major questions:

1. Did the trial court err in finding that Argyle had substantially performed the contract?
2. Did the trial judge err in calculating damages?
3. Did the trial court err in denying Camtec’s counterclaim on the basis that it had failed to prove damages?

*420 I. BACKGROUND FACTS 1

Argyle, a New Jersey corporation, is in the business of providing wholesalers with manufactured metal products. Camtec is in the business of manufacturing mechanical and electrical systems for the health-care industry. Over the last forty years, one of Camtec’s main customers had been the DOD.

In 1996, Camtec began negotiations with the DOD to provide the latter with telescoping I.V. rods, which were to be designed so that I.V. bottles could be hung from the rods and the rods themselves could be attached to stretchers. The negotiations with the DOD were fruitful, and on April 7, 1997, the DOD awarded Camtec a contract for the manufacture of 14,162 I.V. rods. 2 The contract originally required Camtec to deliver the rods on or before November 18, 1997. Between April and October 1997, Camtec worked with the DOD to update the specifications for the rods to conform to the most modern technology.

Meanwhile, in contemplation of fulfilling its contract with the DOD, Camtec, on March 12, 1997, asked Argyle for an estimate of the cost of fabricating 14,500 I.V. poles, 500 “rod-jaws,” and 14,500 lock rings, which were all to be used in connection with the assembly of the I.V. rods. Argyle provided Camtec with a price for those items. Later, in September 1997, Camtec sought an additional quote from Argyle for some other items needed in conjunction with the construction of the rods.

On October 6, 1997, Camtec and Argyle entered into the contract that is the subject of this suit. The contract was set forth in Purchase Order No. 01057. In the purchase order, Argyle agreed to produce and deliver 14,500 sets of parts *421 needed to construct the I.V. rods. 3 The purchase order provided that Argyle was to commence work when Camtec approved Argyle’s design prints for each of the seven items that made up the individual sets of parts needed to construct the I.V. rods. The seven parts were: (1) a 17" tube; (2) a 13.625" tube; (3) an “upper rod”; (4) a clamp; (5) a “jaw,” which attaches to the rod; (6) Lock Rings No. 1; and (7) Lock Rings No. 2. All seven parts were necessary in order for Camtec to commence its assembly of the I.V. rods. The contract between Argyle and Camtec provided that “parts must be free of burrs and chips.” Chemical and physical analyses were required to be provided with each shipment.

By December 23, 1997, all the sample parts that Argyle had provided to Camtec had been approved for production. Under the terms of the purchase order, Argyle was to supply twenty-five percent of the 14,500 sets of parts within ten weeks of December 23, 1997, and then provide twenty-five percent of the sets every two weeks thereafter. Thus, under the contract, Argyle was obligated to deliver 3,625 sets of parts by March 3 and a similar number on March 17, March 31, and April 14, 1998. From the outset, Argyle understood that time was of the essence.

After Camtec contracted with Argyle, the DOD and Camtec agreed to revise Camtec’s delivery schedule. Camtec was required under the revised contract to deliver fifty percent of the I.V. rods (7,081) by February 27, 1998, and fifty percent by March 31,1998.

A Camtec representative testified at trial that the extension had been expected because previously he had “verbal assurances” from the DOD that the latter would not hold Camtec to the original schedule. Therefore, in October 1997, when the purchase order was issued to Argyle, Camtec knew it would have additional time to complete the DOD contract — according to Camtec’s witness.

*422 By February 27, 1998, Argyle knew that it was not going to be able to meet the schedule of producing twenty-five percent of the order (ie., 3,625 sets) by March 3, 1998, nor was it going to be able to deliver a similar number every two weeks as scheduled. As of February 27, 1998, of the seven parts ordered, Argyle had delivered all the 17" tubes, all the 13.625" tubes, as well as all the upper rods. But it had delivered only 198 clamps and a similar number of jaws. It had delivered no Lock Rings Nos. 1 or 2.

On February 27, 1998, a representative of Argyle wrote Camtec and said:

We will be shipping the following on Monday, 3/2/98:
237 pcs. of Lock Ring # 1
243 pcs. of Lock Ring # 2
686 pcs. of the Jaws

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dexter v. Brake
269 P.3d 846 (Court of Appeals of Kansas, 2012)
United States Life Insurance v. Wilson
18 A.3d 110 (Court of Special Appeals of Maryland, 2011)
collins/snoops Associates, Inc. v. Cjf, LLC
988 A.2d 49 (Court of Special Appeals of Maryland, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
807 A.2d 125, 146 Md. App. 415, 48 U.C.C. Rep. Serv. 2d (West) 966, 2002 Md. App. LEXIS 154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cambridge-technologies-inc-v-argyle-industries-inc-mdctspecapp-2002.