Chemetron Corporation v. McLouth Steel Corporation

381 F. Supp. 245, 15 U.C.C. Rep. Serv. (West) 832, 1974 U.S. Dist. LEXIS 7821
CourtDistrict Court, N.D. Illinois
DecidedJune 28, 1974
Docket73 C 228
StatusPublished
Cited by30 cases

This text of 381 F. Supp. 245 (Chemetron Corporation v. McLouth Steel Corporation) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chemetron Corporation v. McLouth Steel Corporation, 381 F. Supp. 245, 15 U.C.C. Rep. Serv. (West) 832, 1974 U.S. Dist. LEXIS 7821 (N.D. Ill. 1974).

Opinion

MEMORANDUM OF DECISION

JULIUS J. HOFFMAN, Senior District Judge.

This is an action for breach of contract. Although properly within this Court’s jurisdiction, 1 the action, where *249 appropriate, is governed by the applicable law of Michigan. 2

Under the contract in issue, the plaintiff, Chemetron Corporation, obligated itself to purchase from the defendant, McLouth Steel Corporation, a minimum quantity of 975 tons of liquid oxygen and/or liquid nitrogen, combined (collectively, “liquid product”), each calendar month of the contract term. McLouth, on its part, obligated itself to make available for purchase by Chemetron, as requested, a guaranteed maximum quantity of 1,950 tons of liquid product each calendar month of the contract term. This arrangement provided Chemetron with an assured supply of liquid product so that it could meet its needs, 3 whatever they might be, from 975 tons to 1,950 tons per month. McLouth agreed to deliver the product “ . . . on a twenty-four hour daily call basis . in approximately equal quantities each day except . . . Saturdays, Sundays, and holidays . . . . ” 4

The written agreement, executed on April 17, 1964, became effective for a five-year term on April 21, 1965, and, pursuant to contract proviso, was automatically renewed for an additional five-year term effective April 21, 1970.

In its suit, commenced January 26, 1973, Chemetron charged that, because of McLouth’s repeated failures to meet its requests during the renewal term of the contract, it has been forced to purchase liquid product from other sources at prices considerably higher than those payable to McLouth under the agreement; that therefore it has sustained, and is continuing to sustain, substantial money damages.

At trial, certain evidence was introduced which revealed the nature of contract performance during the original term of the contract. In the early years of the original term, performance was according to contract specification: in the 27 months from May, 1965 through July, 1967, in averaging 1,348 tons per month, McLouth regularly made available and Chemetron purchased a quantity of product well in excess of the minimum monthly quantity; there was no credible evidence that McLouth’s performance for this period was in any sense inadequate to meet Chemetron’s needs for liquid product. In the next year, however, McLouth’s performance declined: from August, 1967 through July, 1968, McLouth made available and Chemetron purchased more than the minimum monthly quantity in only six of those months, with the monthly average slipping to 856 tons; about this inadequate performance, Chemetron complained, and in response, McLouth offered assurances that its performance, would improve and that its plans to change its steel manufacturing processes would not impair its ability to supply Chemetron’s needs for liquid product. The possibility of immediate improvement was forestalled by a strike that began in August, but by December, after a period of recovery, Mc-Louth’s performance returned to approximately the level of the first two years of the original term: from December, 1968 through April, 1969, McLouth made available and Chemetron purchased, each and every month of this period, a quantity of product well in excess of the minimum monthly quantity, the average rising to 1,283 tons per month; once again, there was no evidence that McLouth’s performance for this period was in any sense inadequate to meet Chemetron’s needs for liquid product.

It was against this background, then, that the contract was renewed; the deadline for notification of intent not to renew passed on April 21,1969.

The outcome of this case in large part depends upon the legal significance of *250 facts proved and not proved. The principal issues arise out of certain defenses interposed by the defendant, and the amount of damages, if any, to which the plaintiff is entitled. There is no dispute with respect to the execution of the contract, nor is there any dispute over the quantities of liquid product actually purchased during the period for which damages are sought.

I.

Cancellation Provision

McLouth maintains that in order to sue for damages Chemetron had first to cancel the contract in its entirety. This contention finds support in the following language of paragraph XII of the contract :

“[I]n the event of failure of either party to perform any provision of this Agreement, the only rights of the other party shall be to cancel the Agreement as provided in this paragraph to recover damages for breach of this Agreement.”

Under the facts of this case, however, the harshness of this provision seems obvious.

From the outset of the 1964 contract, McLouth knew that Chemetron was purchasing liquid product from it for resale to Chemetron’s customers. In April, 1964 McLouth gave Chemetron a letter addressed “to whom it may concern.” In that letter McLouth stated that it had entered into an agreement to supply Chemetron “with a minimum of 65 tons per day” of liquid product. McLouth must have known that the letter' would be used by Chemetron to solicit new sales agreements, and, in fact, a copy of the letter was given to the Jones & Laughlin Steel Corporation. Chemetron also advised McLouth that it had committed itself to supply large quantities of liquid oxygen to Jones & Laughlin. Within a few weeks of the execution of its contract with McLouth, Chemetron signed a sales contract to supply Jones & Laughlin with its liquid oxygen requirements. Relying on its guarantee of product availability from McLouth, Chemetron made other such commitments.

During the renewal term of the contract, when the quantities of liquid product supplied by McLouth fell far below Chemetron’s needs for serving its Detroit customers, Chemetron endeavored to obtain substitute product from other sources. By late 1972, Chemetron could not obtain enough substitute product from these other sources, and, in the spring of 1973, was forced to institute an allocation program under which its customers received only 50 to 80 percent of their needs.

Under these circumstances it would have been commercially unfeasible for Chemetron to cancel its contract with McLouth notwithstanding McLouth’s breaches, for Chemetron would obviously have been in an even worse position and less able to serve its customers if it had received no product at all from Mc-Louth instead of the quantities, however insufficient, that McLouth made available.

While parties may agree to limit the remedies for breach of their contract, 5 the policy of the Uniform Commercial Code disfavors limitations and specifically provides for their deletion if they would act to deprive a contracting party of reasonable protection against breach. Subsection (2) of Section 2719, Uniform Commercial Code of Michigan, provides:

“Where circumstances cause an exclusive or limited remedy to fail of its essential purpose, remedy may be had as provided in this act.” 440 M.C.L. § 2719(2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sta-Rite Industries, LLC v. Franklin Electric Co., Inc.
519 F. App'x 370 (Sixth Circuit, 2013)
In Re Old Carco LLC
452 B.R. 100 (S.D. New York, 2011)
Cambridge Technologies, Inc. v. Argyle Industries, Inc.
807 A.2d 125 (Court of Special Appeals of Maryland, 2002)
American Nursery Products, Inc. v. Indian Wells Orchards
797 P.2d 477 (Washington Supreme Court, 1990)
Duvergee, Inc. v. Government of the Virgin Islands
22 V.I. 56 (Supreme Court of The Virgin Islands, 1986)
A & M PRODUCE CO. v. FMC Corp.
135 Cal. App. 3d 473 (California Court of Appeal, 1982)
Jacobs v. Rosemount Dodge-Winnebago South
310 N.W.2d 71 (Supreme Court of Minnesota, 1981)
T. J. Stevenson & Co. v. 81,193 Bags of Flour
629 F.2d 338 (Fifth Circuit, 1980)
Frank's Maintenance & Engineering, Inc. v. C. A. Rorerts Co.
408 N.E.2d 403 (Appellate Court of Illinois, 1980)
Polycon Industries, Inc. v. Hercules Inc.
471 F. Supp. 1316 (E.D. Wisconsin, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
381 F. Supp. 245, 15 U.C.C. Rep. Serv. (West) 832, 1974 U.S. Dist. LEXIS 7821, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chemetron-corporation-v-mclouth-steel-corporation-ilnd-1974.