Jay V. Zimmerman Co. v. General Mills, Inc.

327 F. Supp. 1198, 9 U.C.C. Rep. Serv. (West) 680, 1971 U.S. Dist. LEXIS 13396
CourtDistrict Court, E.D. Missouri
DecidedMay 7, 1971
DocketNo. 70C268(2)
StatusPublished
Cited by25 cases

This text of 327 F. Supp. 1198 (Jay V. Zimmerman Co. v. General Mills, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jay V. Zimmerman Co. v. General Mills, Inc., 327 F. Supp. 1198, 9 U.C.C. Rep. Serv. (West) 680, 1971 U.S. Dist. LEXIS 13396 (E.D. Mo. 1971).

Opinion

MEMORANDUM OPINION AND ORDER

REGAN, District Judge.

This removed action was brought to recover $16,400 allegedly due under a contract. Defendant counterclaimed for $70,892.79 for alleged breach of the same contract.

Plaintiff, a Missouri corporation, is engaged in the business of designing, fabricating, and selling various novelty items, including “inpack premiums” or novelties which are inserted in breakfast cereals for advertising purposes. Defendant, a Delaware corporation, is engaged, inter alia, in the business of manufacturing and selling breakfast cereals.

In April, 1969, Jay V. Zimmerman, the president of plaintiff, demonstrated to Thomas R. Nelles, defendant’s Assistant Promotion Supervisor, a miniature plastic dune buggy concept for possible use as an inpack premium in one of defendant’s breakfast cereals. Nelles expressed interest, having in mind using the dune buggy in defendant’s cereal known as “Clackers.” Thereafter, on May 13, 1969, Zimmerman presented a promotional brochure to Nelles, in which, because of his concern that plaintiff might have difficulty in meeting defendant’s proposed delivery schedule, he stated that a “(s)econd set of molds will be made if the lead time for delivery to your packing plant is insufficient.”

On May 27, 1969, Nelles verbally gave Zimmerman defendant’s order for two designs of dune buggies. The following day Zimmerman confirmed this order in writing. Therein, plaintiff stated in part:

“Re — : Confirming Verbal Order on DUNE BUGGY as In-Pack Premium

Dear Tom,

This acknowledges and confirms the verbal order given us by you yesterday on the Dune Buggy, as follows — :

1. DESIGNS — to be an assortment of TWO styles.

2. SPECIFICATIONS — per our presentation to you, dated May 9, 1969.

3. MOLDS — -to meet your weekly requirements, two 24-cavity molds will be engineered.

4. ASSORTMENT — each mold will produce one of the two styles, in three assorted colors, for a total of six colors.

5. QUANTITY — 3,600,000.

6. TARGET DATE — at your West Chicago packing plant the week of September 2.

7. WEEKLY REQUIREMENTS— 600,000 minimum.

******

Unless some unforeseen catastrophic situation come us (sic), we are confident we will be in production the week of August 25th.

This tight schedule is predicated on working overtime and paying ineen[1201]*1201tives to expedite all phases of the mold making and make ready.

With two molds, our weekly production will be in excess of 660,000. Once the flow to West Chicago has been started, common carriers can be used on a daily basis.

Regarding the revised, lower costs — :

1. We are quoting on the finished units, delivered to Per Pak (via Common Carrier), with the one mold and design amortized, * * *

Initial Order of 3,600,000 —$26.30 M

2. The additional 24-cavity mold, the second model, all phases of this and the first mold produced on a ‘crash’ basis, including the up-charge of the first mold, will cost —$16,400.”

After discussion with defendant on June 4, 1968, plaintiff ordered two molds from Designs for Tomorrow, Inc., a subcontractor- which agreed to furnish the first operational mold to plaintiff on August 22 and the second mold one week later. On June 5, defendant gave plaintiff written authorization to proceed with the tooling for the contract. Thereafter, on June 24, 1969, defendant issued its “Premium Purchase Order” based on the previous verbal agreement and plaintiff’s confirmation, with slight modifications. This premium purchase order is referred to in the pleadings and briefs of both parties as the contract. Therein, defendant ordered 3,600,000 “Dune Buggy” inpack premiums at $26.30 per thousand, the price to include the amortization of one 24-cavity mold.

The purchase order provided for an additional payment by defendant of $16,400, the “cost of second 24 cavity mold required to meet our tight timing schedule,” as well as for the cost of a prototype development in the amount of $1,220.

The mold used for the production of the dune buggies consisted of a “frame” (a metal base and top) into which were inserted 48 “cavities” or “berrylliums” (24 male and 24 female) made from steel castings known as “hobs.” When operational, the mold was placed into an injection molding press and molten plastic was injected into the mold thereby producing 24 plastic dune buggies, 12 of each design, with each operation or “shot.” The 24 dune buggies were connected by plastic “gates” and “runners” which required manual detachment or “degating.”

At issue on plaintiff’s claim is defendant’s liability for the cost of the second mold, all other agreed payments having been made. Initially, plaintiff and Injex, Inc., plaintiff’s injection molding subcontractor, had anticipated a production rate of 120 cycles or 2,880 dune buggies per hour, but within a week after the first mold was operational, production was stepped up to 180 cycles or 4,320 dune buggies per hour, so that plaintiff was actually able to produce 100,000 dune buggies per 24 hour day from the first mold alone. However, plaintiff did not notify defendant of the production rate it was able to achieve by use of the first mold until October 29, 1969, which was only 6 days before production was completed.

In the meantime, on September 22, 1969, Nelles had telephoned plaintiff inquiring as to the status of the second 24-cavity mold. Two days later he was informed that the mold was three-quarters completed, all the parts for the mold having been received. He was told that if work on the mold was then stopped, about $4,100 in labor costs could be saved, and to notify plaintiff by September 26th if defendant wanted the work stopped. At that time the first mold was not fully operational and no production deliveries had been made. In view of the foregoing, defendant may not be held to have waived its right to deny liability for the cost of the second mold by reason of Nelles’ failure to direct that work on the mold be “stopped.” This is particularly true in view of the further fact that no second mold (not even the [1202]*120220 cavity mold which plaintiff unilaterally decided was preferable to the 24 cavity mold agreed upon) was either completed or operational until after the dune buggies had been produced. We hold that plaintiff is not entitled to the sum of $16,400 the agreed cost of a second 24 cavity mold “required to meet (defendant’s) tight timing schedule.”

That time was of the essence of the contract is evident not only from the specific provisions thereof relating to the time of delivery but also by reason of the very fact that defendant agreed to pay the additional sum of $16,400 for a second mold in order to make certain the dune buggies would be timely delivered. In effect, plaintiff agreed to meet defendant’s “tight timing schedule” in consideration of defendant’s agreement to pay the additional sum of $16,400 for a second mold,- the existence of which was represented as necessary to insure performance by plaintiff. Defendant would not have agreed to make that payment but for plaintiff’s representation that defendant’s “tight timing schedule” could and would be met provided two operational molds were available for use.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shoemaker v. Menard Inc.
W.D. Missouri, 2023
May v. Makita U.S.A., Inc.
E.D. Missouri, 2023
In re Adi Liquidation, Inc.
555 B.R. 423 (D. Delaware, 2016)
Ohline Corp. v. Granite Mill
849 P.2d 602 (Court of Appeals of Utah, 1993)
Micro-Managers, Inc. v. Gregory
434 N.W.2d 97 (Court of Appeals of Wisconsin, 1988)
Stamper Black Hills Gold Jewelry, Inc. v. Souther
414 N.W.2d 601 (North Dakota Supreme Court, 1987)
T. J. Stevenson & Co. v. 81,193 Bags of Flour
629 F.2d 338 (Fifth Circuit, 1980)
Oregon Lumber Co. v. Dwyer Overseas Timber Products Co.
571 P.2d 884 (Oregon Supreme Court, 1977)
T. J. Stevenson & Co. v. 81,193 Bags of Flour
449 F. Supp. 84 (S.D. Alabama, 1976)
A & G Const. Co., Inc. v. Reid Brothers Logging Co., Inc.
547 P.2d 1207 (Alaska Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
327 F. Supp. 1198, 9 U.C.C. Rep. Serv. (West) 680, 1971 U.S. Dist. LEXIS 13396, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jay-v-zimmerman-co-v-general-mills-inc-moed-1971.