A & G Const. Co., Inc. v. Reid Brothers Logging Co., Inc.

547 P.2d 1207, 19 U.C.C. Rep. Serv. (West) 37, 1976 Alas. LEXIS 376
CourtAlaska Supreme Court
DecidedMarch 1, 1976
Docket2360, 2388
StatusPublished
Cited by42 cases

This text of 547 P.2d 1207 (A & G Const. Co., Inc. v. Reid Brothers Logging Co., Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A & G Const. Co., Inc. v. Reid Brothers Logging Co., Inc., 547 P.2d 1207, 19 U.C.C. Rep. Serv. (West) 37, 1976 Alas. LEXIS 376 (Ala. 1976).

Opinion

OPINION

BOOCHEVER, Chief Justice.

These appeals concern disputes as to the amounts due for materials furnished for use on a highway construction project. Our resolution of the issues involves application of provisions of the Uniform Commercial Code (U.C.C.) to the contract in dispute.

On August 10, 1971, A & G Construction Co., Inc. (“A & G”) and Reid Brothers Logging Co., Inc. (“Reid”) entered into a materials supplier agreement wherein Reid agreed to supply A & G with sand; crushed aggregate base course, grading Dl (“Dl”); and hot bituminous pavement aggregate (“hot rock”). The material was to be used in a state highway construction project in the Petersburg area for which A & G was the general contractor. Payment for the materials was to be on the basis of “State accepted scale ticketed tonnage at the price of $2.65 per ton”. The payments to Reid were to be made within ten days of the state’s payment to A & G. The original agreement, however, did not specify the amount of material or the time of delivery.

Shortly after the agreement was executed, A & G sent Reid a purchase order for 59,466 tons of Dl, 21,780 tons of hot rock, and 2,500 tons of sand. Reid was to deliver the material to a stockpile in Scow Bay, outside of Petersburg. The Dl and sand were weighed by the state at the stockpile and placed directly on the road. The hot rock, however, was taken by A & G from the stockpile to its mixing plant where it was mixed with oil to make asphalt. During this process, quantities of hot rock were wasted or lost. The finished asphalt was then taken to the road where it was weighed by the state before being placed on the road.

During the course of performance, the agreement was modified in three respects. In the late spring of 1972, A & G and Reid agreed to raise the price of the hot rock to $2.95 per ton. Toward the end of the project, it became necessary for A & G to procure more Dl than was supplied under the original purchase order. At Reid’s request, the parties agreed to increase the price of the additional Dl by $1.00 per ton to $3.65. Furthermore, since the highway construction project ran into time difficulties, A & G agreed to pay half of the overtime costs if Reid, would work 24 hours a day to supply the additional Dl.

Reid brought suit against A & G claiming it had not been paid the amount due under the written contract and additional agreements. The trial court’s findings and *1211 awards, which are contested by A & G on this appeal, are:

First, the agreement should be construed to read that A & G was to pay Reid for all material delivered to Scow Bay, so that Reid was entitled to payment for 6,067.5S tons of hot rock “lost” between the stockpile and the road. Reid was awarded $17,-899.27 for this material.

Second, A & G was late in its payments to Reid, so that Reid was awarded $3,625.-75 as interest on those payments and $173.-67 interest on short-term loans taken by Reid because of the late payments.

Third, the original contract was not a requirements contract, i. e. a contract to supply A & G all of the quantities required for completion of the contract with the state, and a new agreement for valid consideration had been made whereby A & G owed Reid $5,888.00 for the additional D1 supplied.

Fourth, the original agreement concerning the hot rock had been modified, and A & G owed $5,094.73 for an additional $.30 per ton for 19,682.5 .tons of hot rock.

Reid appeals from the decision of the trial court that Reid did not meet its burden of proof as to 800 tons of rejected D1 that it contended A & G had appropriated.

A & G contends that the trial court erred in awarding $17,899.27 for the loss of 6,067.55 tons of “hot rock” delivered by Reid to A & G. The trial court based this award on the finding that, sometime between the delivery of the hot rock to the stockpile at Scow Bay and the time that it was placed on the road, there was a loss or “waste” of 6,067.55 tons.

The dispute is whether A & G was liable fpr the amount of hot rock that Reid delivered to the stockpile or whether A & G was liable only for that amount of hot rock actually put on the road. A & G contends that the contract language “[pjayment for the materials will be on the basis of State accepted scale ticketed tonnage, at the price of $2.65 per ton” is unambiguous in meaning that A & G would only be liable for the amount of hot rock that was actually put on the road, weighed and paid for by the state.

The U.C.C. [AS 45.05.002 et seq.] provides a comprehensive scheme of obligations and rights of the parties to an agreement. 1 These obligations and rights apply to any contract for the sale of goods unless the parties otherwise agree. 2

*1212 We must therefore look to the contract between A & G and Reid to determine if the parties agreed to some specific payment provision. The contract did make detailed provision for payment. Our problem is therefore to interpret the contract provisions.

Although the U.C.C. does contain provisions dealing with the interpretation of an agreement, they are inapplicable under the circumstances presented in this appeal. 3 Therefore general principles of contract law will determine this issue. 4

Day v. A & G Constr. Co., Inc., 528 P.2d 440, 443 (Alaska 1974), states the relevant law concerning the interpretation of a contract. The interpretation of words is a matter for the court, 5 while resolution of a dispute as to the surrounding circumstances is for the trier of facts. Questions pertaining to the meaning to be given to the words of the contract are to be considered in the same manner as questions of law. Consequently, this court, in interpreting the words of a contract, is not bound by the lower court’s views, and the “clearly erroneous” standard used in reviewing a *1213 trial court’s factual findings is inapplicable. 6

We must first decide whether the contract is ambiguous as to payment. 7 A contract is ambiguous when it is reasonably subject to varying constructions, interpretations, or meanings. 8 In the contract under review, the agreement was clear and unambiguous as long as the materials were weighed by the state at the stockpile. This was the situation with regard to the D1 and sand. 9 But the agreement is ambiguous with regard to the hot rock. ■

The agreement states that “[p]ayment for the materials will be on the basis of State accepted scale ticketed tonnage”. A & G argues that this phrase clearly implies that Reid was to be paid only for those amounts of material actually weighed by the state.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re the Adoption of S.K.L.H.
204 P.3d 320 (Alaska Supreme Court, 2009)
North Pacific Processors, Inc. v. City & Borough of Yakutat
113 P.3d 575 (Alaska Supreme Court, 2005)
Philbin v. Matanuska-Susitna Borough
991 P.2d 1263 (Alaska Supreme Court, 1999)
Johnson v. Olympic Liquidating Trust
953 P.2d 494 (Alaska Supreme Court, 1998)
Pittsley v. Houser
875 P.2d 232 (Idaho Court of Appeals, 1994)
Dawkins and Co. v. L & L PLANTING CO.
602 So. 2d 838 (Mississippi Supreme Court, 1992)
Jackson v. Barbero
776 P.2d 786 (Alaska Supreme Court, 1989)
Ranier Fund, Inc. v. Blomfield Real Estate Co.
717 P.2d 850 (Alaska Supreme Court, 1986)
Howard Construction Co. v. Jeff-Cole Quarries, Inc.
669 S.W.2d 221 (Missouri Court of Appeals, 1984)
State v. Alaska Land Title Ass'n
667 P.2d 714 (Alaska Supreme Court, 1983)
Harned v. Dura Corporation
665 P.2d 5 (Alaska Supreme Court, 1983)
Atlan Industries, Inc. v. O.E.M., Inc.
555 F. Supp. 184 (W.D. Oklahoma, 1983)
Foster v. Cross
650 P.2d 406 (Alaska Supreme Court, 1982)
Nanakuli Paving & Rock Co. v. Shell Oil Co.
664 F.2d 772 (Ninth Circuit, 1981)
Boese-Hilburn Co. v. Dean MacHinery Co.
616 S.W.2d 520 (Missouri Court of Appeals, 1981)
Balfour, Guthrie & Co. v. Gourmet Farms
108 Cal. App. 3d 181 (California Court of Appeal, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
547 P.2d 1207, 19 U.C.C. Rep. Serv. (West) 37, 1976 Alas. LEXIS 376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-g-const-co-inc-v-reid-brothers-logging-co-inc-alaska-1976.