W. R. Grimshaw Company and National Surety Corporation v. Nevil C. Withrow Co., Inc.

248 F.2d 896
CourtCourt of Appeals for the Eighth Circuit
DecidedNovember 15, 1957
Docket15768_1
StatusPublished
Cited by58 cases

This text of 248 F.2d 896 (W. R. Grimshaw Company and National Surety Corporation v. Nevil C. Withrow Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. R. Grimshaw Company and National Surety Corporation v. Nevil C. Withrow Co., Inc., 248 F.2d 896 (8th Cir. 1957).

Opinion

WOODROUGH, Circuit Judge.

On September 12, 1951, the University of Arkansas entered into a contract with the W. R. Grimshaw Company, an Oklahoma corporation, as general contractor, to construct the University Medical Center at Little Rock, Arkansas. In compliance with the requirements of the contract, the Grimshaw Company executed, as principal, a bond on which the National Surety Corporation of New York was surety.

In compiling their prime bid for the overall contract on the Medical Center, the Grimshaw Company prepared detailed cost estimates on the work they planned to perform themselves, but left specialty items, such as windows, doors, terrazzo, et cetera, to specialty companies that are familiar with them. They depend on these companies to quote a price for which the companies, under sub-bids, can furnish the necessary materials and perform the required labor. In that connection and in order to prepare a sub-bid for the aluminum windows, ornamental doors and X-Ray protection, the Nevil C. Withrow Company, Inc., an Arkansas corporation specializing in aluminum windows — subcontracts and furnishing material and supplies in connection therewith, secured a set of blue prints and specifications from the architect for use in compiling their sub-bid on the Little Rock Medical Center.

On September 28, 1951, Nevil C. With-row, president of the plaintiff company, confirmed his sub-bid to the Grimshaw Company covering “Item 1, aluminum windows, Section M-l to M-5 for $310,-000.00 and the erection thereof for $25,-000.00 more, a total of $335,000.00”. The bid was accepted and the amount was included in the sub-contract between the Grimshaw Company as prime and With-row Company as sub-contractor, dated September 26, 1951.

In June of 1952, the Shop Drawings, required under the contract, showing in detail the material the window manufacturer expected to supply in connection with the sub-contract, were submitted to Grimshaw Company by Withrow. They indicated that Ware Laboratories were to do work for Withrow Company. On July 7, 1952 the Shop Drawings were returned to Withrow for correction and resubmission. The Shop Drawings at “Section 29” were labeled “Not by Ware Laboratories.” This referred to the Shop Drawings that Ware Laboratories prepared for the Withrow Company and in each case that the sills — interior and exterior — were indicated on the Shop Drawings, there was a notation “Not by Ware Laboratories nor W. C. Withrow Company.” A conference with the superintendent for the Grimshaw Company and subsequent correspondence between Withrow and the Grimshaw Company during the period March through July, 1953, shows a dispute between the companies with Grimshaw contending that under the specifications, Section M-l through M-5, Withrow was required to furnish the specified window stools and sills. Withrow maintained that Section M-l through M-5 did not provide for the stools and sills and that he had bid *899 on the stools and sills under Section J 1 of the specifications, a section not awarded his company under the sub-contract.

During the correspondence that followed, over a period of 15 weeks, the Grimshaw Company insisted that unless With-row installed the window sills and stools under the sub-contract, the work would have to be performed by someone else and back-charged to Withrow or With-row’s sub-contract cancelled in its entirety. On June 23,1953, Withrow wrote Grimshaw that he recognized that their position was sincere and on July 2, 1953, Withrow wrote the Grimshaw Company:

“* * * We dislike involving others in the controversy that has arisen between your Company and ours as to whether the exterior sills and interior sills (as shown on the architect’s plans) are included in our Company’s sub-contract. It would seem impractical to do so at this time although our construction of what is covered by our sub-contract remains unchanged.
“Therefore, Nevil C. Withrow Company, Inc., is proceeding to include and furnish said exterior sills and interior sills (as shown on the architect’s plans) which are in dispute and future shop drawings will be changed accordingly.
“Please delete from shop drawings in your possession note pertaining to exterior and interior sills so that resubmission will not be necessary.”

Grimshaw Company acknowledged receipt of the letter containing the agreement on July 6, 1953, and wrote With-row as follows:

“We acknowledge receipt of your letter dated July 2, 1953, wherein you state, ‘Nevil C. Withrow Company Inc., is proceeding to include and furnish said exterior sills and interior sills (as shown on the architect’s plans) which are in dispute and future shop drawings will be changed accordingly.’
“Please be advised the sills referred to are to be furnished and installed in strict accordance with the specifications Section M-l through M-5, applicable drawings, Addenda No. 1, 2, 3, and 4, and subject to the terms of the contract. The foregoing are the provisions of your contract, and under these conditions you may proceed with the execution of your contract in its entirety.”

Withrow then proceeded to furnish the stools and sills and perform the necessary labor and the percentage payments made to and accepted by him under the subcontract, as the work progressed, included allowance therefor. Withrow was paid in full, except as to the ten per cent retainage.

On February 26, 1956, the Withrow Company brought this action at law in the United States District Court for the Eastern District of Arkansas and alleged in substance that on or about October 23, 1951, Withrow Company entered into an agreement with Grimshaw Company which provided that Withrow Company should furnish certain labor and materials in connection with the construction of the University of Arkansas Medical Center and that Grimshaw Company agreed to pay to Withrow Company, for said labor, material, et cetera, the sum of $335,000.00; that Withrow Company has now completely performed all its obligations under the contract; that on or about June 8, 1952, Grimshaw Company and Withrow Company entered into a further agreement in which Withrow Company agreed to furnish certain other *900 labor, material, et cetera, in connection with the seventh floor addition to the Medical Center and Grimshaw Company agreed to pay to Withrow Company the sum of $64,589.95 for said labor, material, et cetera, and that Withrow Company has now completely performed all its obligations under said contract; that Grimshaw Company has retained the sum of $24,180.42 as retainage on the original contract and Withrow Company is entitled to that sum with 6%

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'Dell v. Qualscript LLC
E.D. Arkansas, 2023
Smallwood Creek, Inc. v. Build Alaska, LLC
513 P.3d 253 (Alaska Supreme Court, 2022)
Dooley v. Dillard's, Inc.
W.D. Arkansas, 2020
Glenn Gunter v. Farmers Insurance Company
736 F.3d 768 (Eighth Circuit, 2013)
Marks v. Southcoast Hospitals Group, Inc.
29 Mass. L. Rptr. 277 (Massachusetts Superior Court, 2011)
Curtis Lumber Co., Inc. v. Louisiana Pacific Corp.
618 F.3d 762 (Eighth Circuit, 2010)
Ward v. Ward
26 Mass. L. Rptr. 434 (Massachusetts Superior Court, 2010)
Laudani v. Tribeca Lending Corp. (In Re Laudani)
401 B.R. 9 (D. Massachusetts, 2009)
Cabot Corp. v. AVX Corp.
863 N.E.2d 503 (Massachusetts Supreme Judicial Court, 2007)
Country Cove Development, Inc. v. May
150 P.3d 288 (Idaho Supreme Court, 2006)
Hannah v. American Republic Insurance
416 F. Supp. 2d 605 (W.D. Tennessee, 2006)
Cabot Corp. v. AVX Corp.
18 Mass. L. Rptr. 36 (Massachusetts Superior Court, 2004)
Guenin v. Benson
1999 Mass. App. Div. 94 (Mass. Dist. Ct., App. Div., 1999)
Inter-Tel, Inc. v. Bank of America
985 P.2d 596 (Court of Appeals of Arizona, 1999)
Smith v. Fallon Clinic, Inc.
8 Mass. L. Rptr. 518 (Massachusetts Superior Court, 1998)
Cox v. McLaughlin
867 S.W.2d 460 (Supreme Court of Arkansas, 1993)
Mellon v. Norwest Bank of Mandan, North Dakota, N.A.
493 N.W.2d 700 (North Dakota Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
248 F.2d 896, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-r-grimshaw-company-and-national-surety-corporation-v-nevil-c-withrow-ca8-1957.