Philbin v. Matanuska-Susitna Borough

991 P.2d 1263, 1999 Alas. LEXIS 153, 1999 WL 1063047
CourtAlaska Supreme Court
DecidedNovember 19, 1999
DocketS-8573
StatusPublished
Cited by32 cases

This text of 991 P.2d 1263 (Philbin v. Matanuska-Susitna Borough) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philbin v. Matanuska-Susitna Borough, 991 P.2d 1263, 1999 Alas. LEXIS 153, 1999 WL 1063047 (Ala. 1999).

Opinions

OPINION

EASTAUGH, Justice.

I. INTRODUCTION

Before he was paid, a contractor signed a release. The superior court held that the release barred his breach of contract action. Because the contractor raised genuine material fact disputes about the intended effect of the release, we reverse the summary judgment entered against him.

II. FACTS AND PROCEEDINGS

Joseph Philbin, doing business as Philbin Construction, entered into a written contract with the Matanuska-Susitna Borough on October 6, 1995 to supply, load, haul, and deliver approximately 9,250 cubic yards of crushed gravel.1 The gravel was to be overlaid on Beverly Lakes Road, Vine Extension Road, and Meadow Lakes Road, in that order. The borough issued Philbin a notice to proceed on October 10; work was to be completed by November 6.

Although Philbin thought he could complete the project within the time the contract allotted, by October 20 the project was behind schedule. Chuck Kaucic, a project manager at the borough’s public works department, met that day with Philbin and discussed the project’s status. At that meeting Kaucic gave Philbin a letter dated October 19 asking for a revised schedule of anticipated quantities and delivery times, through completion of the project.2

By October 24 Philbin had only completed the first, Beverly Lakes Road, portion of the contract. At the suggestion of the borough’s construction inspector, on October 25 Philbin billed the borough $19,608 for that portion of the contract. Philbin blamed his lack of progress on deteriorating weather which made crushing rock difficult and caused equipment breakdowns. Moreover, cold weather caused the road surfaces to freeze, preventing installation of more rock.

In early November but before November 6, Kaucic and Philbin met and discussed the possibility of a winter shutdown. A winter shutdown would have allowed Philbin to carry the project over to the spring. Philbin testified that Kaucic instructed him to shut down due to the onset of winter, and that written notification of a winter shutdown would be forthcoming.3 Kaucic denied telling Philbin to stop producing material. Rather, he testified that he spoke to Philbin [1265]*1265about the possibility of shutting down and restarting in the spring if the freezing road conditions prevented further work in 1995.

Regardless of what was said at that meeting, the borough, by letter dated November 6, 1995, terminated the contract for nonperformance. The letter stated, in part:

This letter is to serve as official notification that the Matanuska-Susitna Borough is terminating the Load, Haul and Supply Gravel Agreement contract signed on October 6, 1995.... This agreement is being terminated under Section 10A which states “This Agreement may be terminated by the Borough if the Contractor fails to perform any obligation under this Agreement.” You are in noncompliance_
... As of today, 2,280 cubic yards of the 9,250 cubic yards specified in the agreement have been produced and hauled....
... [I]t has been agreed that in the best public interest the Matanuska-Susitna Borough must terminate this agreement effective 12:01 a.m. November 7,1995.

On November 8 Philbin met with executives from the borough’s public works department; they reiterated the borough’s decision to terminate the contract. But they suggested that Philbin submit a written proposal regarding the possible purchase of crushed rock the following spring. Philbin testified that he declined that offer until he could speak to an attorney.

Philbin later executed an affidavit describing his discussions with the borough and his understanding based on the November 8 discussion of what the borough would do. We discuss that affidavit below in more detail.

On November 15 Philbin picked up a borough check for the Beverly Lakes Road portion of the contract. Before giving Philbin the check, the borough required him to sign a form entitled “CONTRACTOR’S RELEASE AND AFFIDAVIT OF ' PAYMENTS OF DEBTS AND CLAIMS.” The form stated that “in consideration of the final payment ... the undersigned contractor ... releases and discharges the Matanuska-Sus-itna Borough ... from any and all further claim, debt, charge, demand, liability or other obligation whatsoever under or arising from said contract_” By his handwritten reservation to the release on lines provided for the purpose, Philbin reserved claims to recover payments to individuals to whom he owed money for the rock-crushing equipment.

The following spring the borough refused to buy additional crushed rock from Philbin. In April 1997 Philbin sued the borough, alleging that the borough’s refusal in the spring of 1996 to purchase the remaining “Contract material” from Philbin was a breach of contract. Philbin’s complaint did not claim that the borough breached the contract by issuing the November 6, 1995 termination letter. The borough raised the release as an affirmative defense, and moved for summary judgment. Enforcing the release, the superior court granted the borough’s motion. Philbin appeals.

III. DISCUSSION

A. Standard of Review

We review a grant of summary judgment de novo.4 Drawing all reasonable inferences in favor of the non-movant, we determine whether the parties genuinely dispute any facts material to a viable legal theory and, if not, whether the undisputed facts entitle the movant to judgment as a matter of law.5 The moving party bears the initial burden of proving through admissible evidence (1) the absence of genuine fact disputes, and (2) its entitlement to judgment as a matter of law.6 Once the [1266]*1266moving party has established a prima facie case, “the non-movant is ‘required, in order to prevent entry of summary judgment, to set forth specific facts showing that he could produce admissible evidence reasonably tending to dispute or contradict the movant’s evidence, and thus demonstrate that a material issue of fact exists.’ ”7

Whether the trial court applied the law correctly is a question of law which we review de novo.8 “Under this standard, it is our duty to adopt the rule of law that is most persuasive in light of precedent, reason, and policy.”9

B. The Parties’ Intentions and Understanding of the Release Document

Philbin first argues that the evidence demonstrated a factual dispute concerning the parties’ intent when he signed the release. He also argues that there is a factual dispute as to whether factors exist sufficient to set aside the release, precluding summary judgment.10 The borough argues that the release is clear and unambiguous, that Phil-bin has not established by clear and convincing evidence that the release should be set aside, and that Philbin’s unilateral mistake in understanding the release cannot excuse its application to him.

In our prior cases we have used two approaches to determine whether a release is enforceable. Though consistent, they vary in their emphasis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cynthia J. Notti v. David G. Hoffman
513 P.3d 245 (Alaska Supreme Court, 2022)
Christensen v. Alaska Sales & Service, Inc.
335 P.3d 514 (Alaska Supreme Court, 2014)
Tesoro Alaska Company v. Union Oil Company of California
305 P.3d 329 (Alaska Supreme Court, 2013)
Estate of Kim Ex Rel. Alexander v. Coxe
295 P.3d 380 (Alaska Supreme Court, 2013)
Kuretich v. Alaska Trustee, LLC
287 P.3d 87 (Alaska Supreme Court, 2012)
State v. Native Village of Tanana
249 P.3d 734 (Alaska Supreme Court, 2011)
Weimer v. CONTINENTAL CAR & TRUCK, LLC
237 P.3d 610 (Alaska Supreme Court, 2010)
Krone v. STATE, DEP. OF HEAL. AND SOC. SER.
222 P.3d 250 (Alaska Supreme Court, 2009)
Krone v. State, Department of Health & Social Services
222 P.3d 250 (Alaska Supreme Court, 2009)
Beal v. McGuire
216 P.3d 1148 (Alaska Supreme Court, 2009)
State, Department of Health & Social Services v. Okuley
214 P.3d 247 (Alaska Supreme Court, 2009)
Cikan v. ARCO Alaska, Inc.
125 P.3d 335 (Alaska Supreme Court, 2005)
Still v. Cunningham
94 P.3d 1100 (Alaska Supreme Court, 2004)
Barry v. University of Alaska
85 P.3d 1022 (Alaska Supreme Court, 2004)
Froines v. Valdez Fisheries Development Ass'n
75 P.3d 83 (Alaska Supreme Court, 2003)
Ball v. Birch, Horton, Bittner and Cherot
58 P.3d 481 (Alaska Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
991 P.2d 1263, 1999 Alas. LEXIS 153, 1999 WL 1063047, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philbin-v-matanuska-susitna-borough-alaska-1999.