Martech Construction Co. v. Ogden Environmental Services, Inc.

852 P.2d 1146, 1993 Alas. LEXIS 47
CourtAlaska Supreme Court
DecidedMay 21, 1993
DocketS-4484
StatusPublished
Cited by42 cases

This text of 852 P.2d 1146 (Martech Construction Co. v. Ogden Environmental Services, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martech Construction Co. v. Ogden Environmental Services, Inc., 852 P.2d 1146, 1993 Alas. LEXIS 47 (Ala. 1993).

Opinions

OPINION

COMPTON, Justice.

This dispute arises from the failed contractor-subcontractor relationship between Ogden Environmental Services, Inc. (Ogden) and Martech Construction Co. (Mar-tech). After Ogden and Martech terminated their relationship through a settlement, Martech was sued by another subcontractor for breach of contract related to the Ogden job. Martech joined Ogden as a party and filed a third party complaint against it. The trial court granted Ogden’s motion for summary judgment dismissing the third party complaint with prejudice and directing entry of judgment pursuant to Civil Rule 54(b). Martech appeals. We affirm.

I. FACTUAL AND PROCEDURAL BACKGROUND

Ogden contracted with ARCO Alaska, Inc. to perform the PCB remediation project at the Swanson River Oil Field Site. Ogden entered into a subcontract with Mar-tech under which one of Martech’s tasks was to purchase, deliver and install two 250 kilowatt gas fired generators “including all connection requirements.”

Martech brought Ogden together with Cummins Northwest, Inc. (Cummins), a designer who could fabricate switchgear which would automatically shed and transfer electrical loads between the generators. However, a dispute arose in July 1988 over whether “including all connection requirements” required Martech to supply the switchgear, as Ogden claimed, or whether the switchgear was Ogden’s responsibility. In October 1988 Martech ordered the switchgear from Cummins at Ogden’s request. Both parties continued to deny liability for the switchgear. Each party continued to claim the other was responsible. It was never formally resolved who would pay for or take ownership of the switchgear.

On November 4, 1988, Ogden terminated its subcontract with Martech. On November 10, 1988, Ogden and Martech entered into a Settlement Agreement, Mutual Release and Waiver ending their relationship. The agreement provided that Martech would sell Ogden the on-site equipment and facilities purchased by Martech for the project and listed in the agreement. The switchgear, not yet being on-site, was not listed. Ogden promised to make a payment of $1.5 million to Martech to cover undisputed unpaid invoices.

The settlement recognized that “[t]he exact nature and amounts of the parties’ financial and contractual obligations to each other [were] in dispute” and noted that Martech and Ogden were “desirous of fully, finally and forever effecting a mutual release of their financial and contractual obligations to each other.” Paragraph 2 of the settlement provides:

2. The parties agree that all claims, demands, rights, and causes of action that each other has or may have against the other with respect to the above-described dispute or contract are hereby satisfied, discharged, and settled. The parties also agree to stipulate to the dissolution of the TRO, to discharge the injunction bond, and to seek, obtain and [1148]*1148be bound by a dismissal with prejudice in the above-described action. Except as herein set forth, no party shall have any further obligation to pay any sum pursuant to the contract whether now or hereafter due, whether contingent or uncon-tingent, whether liquidated or unliquidat-ed.

Paragraph 18, a comprehensive mutual release, provides:

18. The parties agree that this settlement is the compromise of their disputed claims referred to above and hereby agree and acknowledge that any other claims against each other, known or unknown, which arose on or prior to November 4, 1988, or arose pursuant to the contract for past or future losses, expenses or claims of any nature whatsoever (including any liability pursuant to the contract which might have arisen in the future had the contract not been terminated) are forever abandoned, and any right to assert such additional claims for any damages whatsoever are hereby forever waived and barred. It is hereby declared and acknowledged that the undersigned are familiar with the decision of the Alaska Supreme Court in the case of Witt v. Watkins, 579 P.2d 1065 (Alaska, 1978),1 and that it is still the true intent and desire to fully release all individuals, agents, firms or corporations who could at any future date be possible defendants in any action arising out of the matters described herein. The parties acknowledge and assume all risk, chance, or hazard that the alleged damages arising out of this dispute, if any, may be different, greater, or more extensive than is now known by any of the parties hereto. By this agreement the parties intend to discharge any liability which may be discovered now or hereafter, and specifically understand and agree that each has given the consideration herein mentioned in order to be released fully, finally, and completely from all liability for whatever damage, known or unknown, arising from or relating to the subject contract. The parties specifically release and renounce any right they may now or hereafter have to reform, rescind, modify, or set aside this Settlement Agreement,' Mutual Release and waiver because of mutual or unilateral mistake. The risk of mistake is hereby assumed by the parties in consideration of the dismissal of the action described above. It is declared and acknowledged that no promise or inducement which is not herein expressed is made to secure this release. It is represented that this settlement release was not secured in haste by the instigation of the parties released, the undersigned were not (in agreeing to this settlement and to this release) at a bargaining disadvantage because of the nature of the action or the injuries or damages or for any other reason, and that all parties have been represented by legal counsel throughout the course of negotiations which have led to this release.

The settlement agreement also provided for arbitration of disputes regarding approval of daily worksheets for work performed and payment of invoices. Martech filed a demand for arbitration against Ogden on December 30, 1988 on a number of these claims, but not for the switchgear. Martech was awarded $19,127.24 by the arbitrator.

On November 17, 1988, Cummins informed Ogden by letter that Ogden could [1149]*1149purchase the switchgear for $54,183.75. The letter noted that the switchgear would be ready for delivery by December 15 if Ogden accepted the bid by November 18. The letter also noted that Martech was being assessed a cancellation charge of at least $44,000 on the initial order. Ogden, however, purchased an automatic switchgear from another supplier.2

On August 24, 1989, Cummins filed suit against Martech alleging numerous payments due, including that for the switchgear. In response, Martech asserted that it was acting as a disclosed agent and that Cummins had failed to join necessary parties. Martech also filed a third party complaint against Ogden. The superior court denied Martech’s motion to join Ogden as a third party defendant.3 Martech then moved to join Ogden as a necessary party under Civil Rule 19 and to reconsider its denial of the motion to file the third party complaint.4 See Alaska R.Civil P. 19(a) (1991-92). The court joined Ogden under Civil Rule 19 and ordered that Mar-tech’s complaint against Ogden be filed.

Ogden moved for summary judgment on the third party complaint on the basis of the settlement agreement. The trial court granted the motion. It also granted Ogden’s motion for attorney’s fees.5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jovanov v. State, Department of Corrections
404 P.3d 140 (Alaska Supreme Court, 2017)
Hunter v. Philip Morris USA Inc.
364 P.3d 439 (Alaska Supreme Court, 2015)
In Re the Necessity for the Hospitalization of Daniel G.
320 P.3d 262 (Alaska Supreme Court, 2014)
Tesoro Alaska Company v. Union Oil Company of California
305 P.3d 329 (Alaska Supreme Court, 2013)
Estate of Kim Ex Rel. Alexander v. Coxe
295 P.3d 380 (Alaska Supreme Court, 2013)
Beal v. McGuire
216 P.3d 1148 (Alaska Supreme Court, 2009)
Burnett v. Covell
191 P.3d 985 (Alaska Supreme Court, 2008)
Maines v. Kenworth Alaska, Inc.
155 P.3d 318 (Alaska Supreme Court, 2007)
Rathke v. Corrections Corp. of America
153 P.3d 303 (Alaska Supreme Court, 2007)
Cikan v. ARCO Alaska, Inc.
125 P.3d 335 (Alaska Supreme Court, 2005)
Industrial Commercial Electric, Inc. v. McLees
101 P.3d 593 (Alaska Supreme Court, 2004)
Barry v. University of Alaska
85 P.3d 1022 (Alaska Supreme Court, 2004)
Williams v. Abood
53 P.3d 134 (Alaska Supreme Court, 2002)
Old Harbor Native Corp. v. Afognak Joint Venture
30 P.3d 101 (Alaska Supreme Court, 2001)
Botelho v. Griffin
25 P.3d 689 (Alaska Supreme Court, 2001)
Peter v. Schumacher Enterprises, Inc.
22 P.3d 481 (Alaska Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
852 P.2d 1146, 1993 Alas. LEXIS 47, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martech-construction-co-v-ogden-environmental-services-inc-alaska-1993.