Micro-Managers, Inc. v. Gregory

434 N.W.2d 97, 147 Wis. 2d 500, 7 U.C.C. Rep. Serv. 2d (West) 1375, 1988 Wisc. App. LEXIS 1061
CourtCourt of Appeals of Wisconsin
DecidedNovember 10, 1988
Docket87-1506
StatusPublished
Cited by30 cases

This text of 434 N.W.2d 97 (Micro-Managers, Inc. v. Gregory) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Micro-Managers, Inc. v. Gregory, 434 N.W.2d 97, 147 Wis. 2d 500, 7 U.C.C. Rep. Serv. 2d (West) 1375, 1988 Wisc. App. LEXIS 1061 (Wis. Ct. App. 1988).

Opinion

DYKMAN, J.

Stanley Gregory d/b/a Consulting Engineers appeals from a judgment requiring him to pay Micro-Managers, Inc., (MMI) $24,503.68. MMI had sued Gregory for breach of contract after Gregory refused to pay for a computer program he had contracted for and had thereafter sold to a third party. The issues are: (1) whether the contract was a transaction for goods, and thus subject to the Uniform *504 Commercial Code (U.C.C.); (2) whether there was an implied warranty from MMI to Gregory; (3) whether MMI substantially performed the contract; and (4) whether the trial court abused its discretion in denying Gregory’s motion to amend his counterclaim. We conclude that: (1) the contract was mainly for services, and that therefore the U.C.C. does not apply; (2) there was no implied warranty; (3) MMI substantially performed the contract; and (4) the trial court did not abuse its discretion by denying Gregory’s motion to amend his counterclaim. Therefore we affirm.

FACTS

In the fall of 1982, Oilgear, an industrial manufacturing company in Milwaukee, contracted with Gregory to develop a new programmable controller to replace equipment which Oilgear was using. Gregory contacted Rex Peterson, general manager of MMI, who indicated MMI was interested in designing and developing the software required for the controller. Gregory’s technical, coordinator, Terry Coleman, met with his counterpart at MMI, Mike Christie, to find out whether MMI had the personnel and expertise to design and develop the required software in accordance with Oilgear’s specifications. After MMI had prepared certain cost estimates, Gregory told MMI to go ahead with the design and development of the controller software. MMI began work on the project on October 7, 1982.

On October 22, 1982, MMI drafted a letter incorporating what it believed to be the working arrangements between the parties. The letter provided that "all MMI time will be billed by MMI at a rate of *505 $40/hour for software, $50/hour for engineering, and $75/hour for supervision .... Direct expenses will be billed as charged MMI.” The letter also provided that MMI was to receive a fifteen percent incentive bonus if it completed the project on an accelerated schedule. The letter further provided that Gregory must give MMI a two-week project termination notice for termination to be effective. The letter ended: "If the terms of this letter meet with your understanding, please sign and return a copy to me no later than October 25, 1982.”

On October 25, 1982, Coleman signed the letter, acknowledging receipt of the letter and confirming that the items in the letter had been discussed and agreed upon. During the next two months, the parties agreed to a number of amendments to the agreement. Gregory confirmed all of these changes with Oilgear. In January of 1983, Coleman and MMI agreed that the software was to be completed and ready for final testing by February 1, 1983 for MMI to earn the bonus.

On February 1, the parties from MMI (Sally Peterson, president of MMI, and Mike Christie) were not available. Gregory took the software from MMI but complained that it had not been completed to his satisfaction. However, Gregory did not permit MMI to correct any of the alleged defects in the software, and never communicated any specific objections to MMI regarding the software until legal action began.

Pursuant to the parties’ stipulation, the trial court ordered the trial bifurcated because of the complexity of the issues. This was because many of Gregory’s counterclaims against MMI would apply only if the parties’ contract were one mainly for goods, *506 and thus subject to U.C.C. strictures. 1 In the first phase, the issue would be whether the contract was governed by the U.C.C., i.e., whether the contract was mainly for services or mainly for goods. Because Gregory’s defenses of modification of the contract and failure of consideration would apply even if the contract were mainly for services, the trial court would consider evidence relevant to those issues in the first phase. Only if the trial court determined that the contract was for goods would a second trial be held.

After the first phase, the trial court concluded that the October 22 letter was the contract, that it was mainly for services rather than goods, and that therefore the U.C.C. did not apply. The court also concluded that, although the parties had modified the original contract, this had no effect on Gregory’s liability to compensate MMI for all services performed. In addition, the trial court concluded that there was no failure of consideration. This was because the parties’ mutual promises, i.e., MMI’s promise to use its expertise and skill in the design and development of the controller software and Gregory’s promise to pay for these services, were sufficient consideration for each other. The court further concluded that MMI had made no express or implied warranty that the end product of the services agreement would meet certain specifications. The court granted MMI judgment against Gregory for $24,503.68, which represented MMI’s unpaid invoices to Gregory plus interest to date of judgment minus the fifteen percent bonus, which MMI had waived.

*507 CONTRACT FOR GOODS OR SERVICES?

Although at trial Gregory contested MMI’s claim that the October 22, 1982 letter was the parties’ contract, he does not argue on appeal that the trial court’s conclusion is erroneous. The interpretation of an unambiguous contract presents a question of law which we review de novo. Schmitz v. Grudzinski, 141 Wis. 2d 867, 871, 416 N.W.2d 639, 641 (Ct. App. 1987). It is undisputed that this was a mixed contract, i.e., a contract for both goods and services. Van Sistine v. Tollard, 95 Wis. 2d 678, 684, 291 N.W.2d 636, 639 (Ct. App. 1980). The issue is whether the mixed contract was predominantly for goods or for services.

The test for inclusion or exclusion [within the U.C.C.] is not whether [contracts] are mixed, but, granting that they are mixed, whether their predominant factor, their thrust, their purpose, reasonably stated, is the rendition of service, with goods incidentally involved (e.g., contract with artist for painting) or is a transaction of sale, with labor incidentally involved (e.g., installation of a water heater in a bathroom).

Bonebrake v. Cox, 499 F.2d 951, 960 (8th Cir. 1974) (footnotes omitted), quoted in Van Sistine, 95 Wis. 2d at 684, 291 N.W.2d at 639.

Gregory cites many cases which he alleges support construing the contract as one primarily for goods. Nevertheless, we conclude that Data Processing v. L. H. Smith Oil Corp., 492 N.E.2d 314 (Ind. App.), aff’d on rehearing,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S & L Properties New Pinery, LLC v. Todd W. Bennett
Court of Appeals of Wisconsin, 2024
Ver Hagen v. BeneTek Inc
E.D. Wisconsin, 2024
Amara Gerger v. Yajaira Vanessa Avila Gerger
Court of Appeals of Wisconsin, 2023
Zielinski v. Zielinski
2018 WI App 71 (Court of Appeals of Wisconsin, 2018)
Racine County v. Oracular Milwaukee, Inc.
2010 WI 25 (Wisconsin Supreme Court, 2010)
Farmers Automobile Insurance v. Union Pacific Railway Co.
2009 WI 73 (Wisconsin Supreme Court, 2009)
FARMERS AUTO. INS. ASS'N v. Union Pac. Ry.
2009 WI 73 (Wisconsin Supreme Court, 2009)
Racine County v. Oracular Milwaukee, Inc.
2009 WI App 58 (Court of Appeals of Wisconsin, 2009)
Yorgan v. Durkin
2006 WI 60 (Wisconsin Supreme Court, 2006)
State v. Armstrong
2005 WI 119 (Wisconsin Supreme Court, 2005)
Linden v. Cascade Stone Company, Inc.
2005 WI 113 (Wisconsin Supreme Court, 2005)
Dealer Management Systems, Inc. v. Design Automotive Group Inc.
822 N.E.2d 556 (Appellate Court of Illinois, 2005)
Town of Eagle v. Franklin-Stiglitz
2005 WI App 1 (Court of Appeals of Wisconsin, 2004)
Insurance Co. of North America v. Cease Electric Inc.
2004 WI 139 (Wisconsin Supreme Court, 2004)
Linden v. Cascade Stone Co., Inc.
2004 WI App 184 (Court of Appeals of Wisconsin, 2004)
Bloomer Housing Ltd. Partnership v. City of Bloomer
2002 WI App 252 (Court of Appeals of Wisconsin, 2002)
Kain v. Bluemound East Industrial Park, Inc.
2001 WI App 230 (Court of Appeals of Wisconsin, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
434 N.W.2d 97, 147 Wis. 2d 500, 7 U.C.C. Rep. Serv. 2d (West) 1375, 1988 Wisc. App. LEXIS 1061, Counsel Stack Legal Research, https://law.counselstack.com/opinion/micro-managers-inc-v-gregory-wisctapp-1988.