Gl Capasso Res. v. West Haven Hsg. Auth., No. Cv98-00636525 (Nov. 29, 1999)

1999 Conn. Super. Ct. 14827
CourtConnecticut Superior Court
DecidedNovember 29, 1999
DocketNo. CV98-00636525
StatusUnpublished

This text of 1999 Conn. Super. Ct. 14827 (Gl Capasso Res. v. West Haven Hsg. Auth., No. Cv98-00636525 (Nov. 29, 1999)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gl Capasso Res. v. West Haven Hsg. Auth., No. Cv98-00636525 (Nov. 29, 1999), 1999 Conn. Super. Ct. 14827 (Colo. Ct. App. 1999).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION RE: PLAINTIFF'S AND DEFENDANT'S MOTIONS FOR SUMMARY JUDGMENT
In early 1998, the West Haven Housing Authority solicited bids to perform masonry work. Prospective bidders were furnished with a project manual which contained the plans and specifications for the job. The manual contained a bid form, a form of contract, a performance and payment bond and general conditions of the contract for construction. On April 9, 1998, the executive director of the Housing Authority sent a written letter awarding the job to the plaintiff. On April 20, 1998, the defendant Housing Authority, again acting through its executive director, sent a letter to the plaintiff repudiating and revoking the award of the contract. The court will discuss other facts and refer to the Project Manual and Bid Form for this job as it becomes necessary during the course of its decision. Both parties have filed cross motions for summary judgment. The plaintiff has moved for judgment as to liability. The standards to be applied on motions for summary judgment are well known. The court cannot grant such a motion if there is a disputed issue of material fact. The court will now discuss the various claims and counterclaims of the parties on the legal issues presented.

I
In this case, the plaintiff has brought a breach of contract claim. The defendant argues that no contract had been entered into between the parties. The defendant also maintains that even if such a contract had been entered into, the plaintiff cannot now bring its breach of contract claim because the plaintiff failed to exhaust its administrative remedies. The defendant also makes a broader claim relying on the case of Lawrence Brunoli,Inc. v. Town of Branford, 247 Conn. 407 (1999). The court will deal with the argument under Brunoli first. Basically, Brunoli held that a trial court, faced with a claim by an unsuccessful bidder against a municipality, lacks subject matter jurisdiction to consider a damage claim; that is, where a municipality has engaged in fraud, corruption or favoritism in the bidding CT Page 14829 process, an unsuccessful bidder has standing under the applicable municipal bidding statute only to bring an action for injunctive relief. The defendant basically argues whether a contract was formed here by the sending of the award letter to the plaintiff is irrelevant under Brunoli. At pp. 9-10 of its March 3, 1999 brief, the defendant argues: "In the present case, the plaintiff contends that Capasso brought a breach of contract claim rather than a bid protest as was the case in Brunoli and, therefore,Brunoli is unapplicable to this case. However, the argument is without merit, just as in Brunoli, the plaintiff here claims that he is entitled to sue for damages for breach of contract in a public contract matter. Just as in Brunoli, the law, as set forth by the Connecticut Supreme Court, establishes that in such a setting the plaintiff has no right to sue for damages. The only remedy available to the plaintiff was to file an injunction to prevent the case from going forward until a court ruled on the merits of the claim of the plaintiff."

The defendant apparently relies on language at p. 409 of the opinion where before going on to discuss the merits of the case the court said for the purposes of the appeal it assumed that the allegations of the revised complaint were true and noted that the plaintiff (Brunoli) "was informed that it was the `lowest qualified bidder', but that the defendant subsequently withdrew its award of the contract to the plaintiff because the plaintiff had failed to attend a prebid conference . . ." 247 Conn. at p. 409. As noted, the defendant seems to argue from this language that Brunoli stands for the proposition that even if the sending and receipt of the city's award letter created a binding contract, or more generally, even if a contract had come into existence, a plaintiff cannot sue in damages under the contract but is confined to the remedy of an injunction if the city breached the contract or tried to terminate its contractual obligations. This, however, is not what Brunoli really says; ifBrunoli were taken to have adopted this position, it would be a position that is contrary to rulings in numerous other jurisdictions and would raise possible due process constitutional arguments.

The Brunoli court never addressed the issue of whether a binding contract had, in fact, been created between Brunoli and Branford before it told Brunoli the job was in fact not being assigned to Brunoli. The continuing discussion in Brunoli makes clear it was analyzing the case under traditional law that holds that injunctive relief not damages is the only remedy for an CT Page 14830 "unsuccessful bidder" as opposed to a party who already had a contract which the city rescinds. In fact, the language of the dissent indicated that that was what was involved in Brunoli, where at p. 417, it characterizes the factual setting for the legal issues before the court. Justice Berdon said: "In the present case, the plaintiff, Lawrence Brunoli, Inc., alleges that the defendant, the Town of Branford, had informed the plaintiff that it was `the lowest qualified bidder' for the construction project in question but did not award the contract to the plaintiff because it apparently failed to attend a prebid conference." By any argument, merely informing a company that it is the lowest qualified bidder cannot be tantamount to an award of a contract — in most of these cases, as here, the project manual for the job reserves the town's right to reject any and all bids. See 247 Conn. at p. 411; court refers to John BrennanConstruction Corporation. Inc. v. Shelton, 187 Conn. 695, 702 (1982). Thus, Brunoli was dealing with the situation of an unsuccessful bidder, not the claim of a party who argued that a contract had been formed between it and the city.

As noted, it is fairly universally held that where in fact a contract has been formed between the city and a contractor, suit can be brought by the contractor for breach and the contractor is not confined to seeking injunctive relief.

Thus, in 64 Am.Jur.2d 833 et seq, "Public Works and Contracts "the general rule and the reasons behind it are stated as they are in Brunoli. At § 86, p. 948 it says:

"A bidder for public work cannot base a right of action for damages against the public body upon a statutory requirement that contracts for the performance of public work shall be let to the lowest bidder, and cannot recover lost profits in case the contract is, contrary to the statute, awarded to a higher bidder. Such a statutory provision, enacted as a protection to the public cannot be used to make disobedience of its provisions by public officers a double service of punishment to the public body . . ."

The commentary immediately goes on to say:

"Many cases, however, take the position that if a binding agreement came into existence when the award was made, the public body cannot revoke the award. Accordingly, there are numerous instances in which a bidder's right to recover damages for the CT Page 14831 breach of the contract inherent in the public body's attempted revocation of the prior award is upheld.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Purcell Envelope Co.
249 U.S. 313 (Supreme Court, 1919)
McKart v. United States
395 U.S. 185 (Supreme Court, 1969)
City of Susanville v. Lee C. Hess Co.
290 P.2d 520 (California Supreme Court, 1955)
State v. Zia, Inc.
556 P.2d 1257 (Alaska Supreme Court, 1976)
K.L. Conwell Corp. v. City of Albuquerque
802 P.2d 634 (New Mexico Supreme Court, 1990)
Weltz v. Bd. of Educ. of Scotland Sch. Dist.
329 N.W.2d 131 (South Dakota Supreme Court, 1983)
John J. Brennan Construction Corporation, Inc. v. Shelton
448 A.2d 180 (Supreme Court of Connecticut, 1982)
Premier Electrical Construction Co. v. Board of Education
388 N.E.2d 1088 (Appellate Court of Illinois, 1979)
Randolph Construction Co. v. Kings East Corporation
334 A.2d 464 (Supreme Court of Connecticut, 1973)
City of Lake Station v. State Ex Rel. Moore Real Estate, Inc.
558 N.E.2d 824 (Indiana Supreme Court, 1990)
Texaco, Inc. v. Pennzoil, Co.
729 S.W.2d 768 (Court of Appeals of Texas, 1987)
Atlantic Terra Cotta Co. v. Chesapeake Terra Cotta Co.
112 A. 156 (Supreme Court of Connecticut, 1921)
Pratt v. . Hudson River Railroad Company
21 N.Y. 305 (New York Court of Appeals, 1860)
Greenwich Insurance v. Oregon Improvement Co.
27 N.Y.S. 794 (New York Supreme Court, 1894)
Muncy Area School District v. Gardner
497 A.2d 683 (Commonwealth Court of Pennsylvania, 1985)
LaCroix v. Board of Education
505 A.2d 1233 (Supreme Court of Connecticut, 1986)
Shortt v. New Milford Police Department
562 A.2d 7 (Supreme Court of Connecticut, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
1999 Conn. Super. Ct. 14827, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gl-capasso-res-v-west-haven-hsg-auth-no-cv98-00636525-nov-29-1999-connsuperct-1999.