Anthony P. Miller, Inc. v. Wilmington Housing Authority

179 F. Supp. 199, 1959 U.S. Dist. LEXIS 2351
CourtDistrict Court, D. Delaware
DecidedNovember 3, 1959
DocketCiv. A. 1739
StatusPublished
Cited by10 cases

This text of 179 F. Supp. 199 (Anthony P. Miller, Inc. v. Wilmington Housing Authority) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anthony P. Miller, Inc. v. Wilmington Housing Authority, 179 F. Supp. 199, 1959 U.S. Dist. LEXIS 2351 (D. Del. 1959).

Opinion

LAYTON, District Judge.

These are cross motions for summary judgment arising out of an action 1 to recover monies allegedly wrongfully withheld under a certain construction contract between Anthony P. Miller, Inc. (Miller), plaintiff, and Wilmington Housing Authority, the defendant. 2

Miller, the successful bidder on the prime contract, commenced construction of a low rent housing project in this area on or about May 26, 1952. However, the course of the work was plagued by numerous delays including inclement weather and, particularly, strikes, and was not finished until long after the specified completion date.

Part II, Section B, Paragraph 2 of the Contract authorized the defendant to withhold $148 daily as liquidated damages for failure to complete the contract on time.

See. 13(a) of the Contract reads as follows:

“13. Delays — Damages
“a. * * * Provided, That the right of the Contractor to proceed shall not be terminated or the Contractor charged with liquidated damages because of any delays in the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to acts of God, or of the public enemy, acts of the Government, acts of the Local Authority, acts of another contractor in the performance of a contract with the Local Authority, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather or delays of subcontractors due to such causes, if the Contractor shall within 10 days from the beginning of any such delay (unless the Local Authority, with the approval of the PH A, shall grant a further period of time prior to the date of final settlement of the Contract) notify the Contracting Officer in writing of the causes of delay, who shall ascertain the facts and the extent of delay, and the *201 Local Authority shall, subject to prior approval of the PHA, extend the time for completing the work when in its judgment the findings of fact of the Contracting Officer justify such an extension, and his findings of fact thereon shall be final and conclusive upon the parties hereto.” (My emphasis.)

The plaintiff filed written notices as to the causes of the several delays with the contracting officer who, in accordance with the provisions of paragraph 13 quoted above, proceeded to “ascertain the facts and the extent of delay.” He determined that of 713 3 days’ delay for which extensions were requested by the plaintiff, only 304 were justifiable as having occurred without his fault or negligence. 4 Subtracting this 304 days from the actual overrun of 465 days, the contracting officer determined that 161 days of the overrun constituted inexcusable delay, which, when multiplied by the per diem penalty of $148, resulted in a proper withholding by defendant from monies due plaintiff under the Contract of $23,-828 as liquidated damages. 5 The defendant Local Authority ratified this determination by resolution pursuant to the provisions in Sec. 13 quoted above.

Plaintiff alleges that defendant is wrongfully withholding this sum of $23,-828, arguing that no such damages for delay are lawfully chargeable to plaintiff because the contracting officer, in making his determinations of excusable delay attributable to labor shortages, applied a formula which was entirely inappropriate and erroneous for such calculation, the result of which amounts to such gross error as to constitute constructive fraud.

Also sought to be recovered is the sum of $3,626.96, allegedly improperly retained by the defendant resulting from a dispute between the parties as to whether or not this represented work required by the Contract. The plaintiff takes the position that the work was not specified in the Contract and should be regarded as a compensable extra.

Defendant’s Motion for Summary Judgment.

The plaintiff’s first argument is predicated upon the settled principle of law which forbids the construction of a Contract by a contracting officer. United States v. L. P. & J. A. Smith, 256 U.S. 11, 41 S.Ct. 413, 65 L.Ed. 808. The second argument rests upon an interpretation of one of the provisions of the Con *202 tract itself which in so many words limits the power of the contracting officer to the making of fact findings and nothing more. Theoretically, therefore, if the contracting officer, in making any of his determinations, did something which amounted to a construction of the Contract itself, such a determination would have to be set aside because forbidden by the rule of law above referred to or because, by the very terms of the Contract itself, he had exceeded his authority. However, as a practical matter, the controversy arises, not from the fact that the contracting officer construed the Contract, but rather, made determinations (whether amounting to fact findings or a construction of the Contract) which were so unfair as to injure the plaintiff. Accordingly, I express no opinion on either of the first two contentions and will confine this discussion to the third point, namely, regardless of whether the contracting officer made a finding of fact or a construction of the Contract, was what he did so palpably erroneous as to be regarded in law as a constructive fraud ?

It is a familiar principle that where parties to a building contract agree to be bound by the conclusions or decisions of an arbiter, contracting officer, engineer or architect, the Courts will not entertain jurisdiction over disputes arising from such a determination. Corbin on Contracts, Vol. 3, Sec. 652, P. 600. Mundy v. Louisville & N. R. R. Co., 6 Cir., 67 F. 633; Terminal Construction Co. v. Bergen County, Errors & Appeals, 18 N.J. 294, 113 A.2d 787; Annotation in 54 A.L.R. 1255 and 110 A.L.R. 137; Restatement of the Law, Contracts, Sec. 303. It is an equally familiar principle that Courts will entertain jurisdiction of such a dispute when it is alleged that the findings of an arbiter, contracting officer, etc., were based upon fraud and, if fraud is found, then set aside such findings. Thus, in 110 A.L.R. at page 143, it is said:

“As stated in an earlier annotation, notwithstanding a contract makes the certificate, report, opinion, or decision of an engineer or architect conclusive' on the parties, the law writes into this provision that the conduct of the arbiter must be free from fraud. Fraud on his part destroys the effect of the provision.”

See also Wagner Whirler & Derrick Corp. v. U. S., 1954, 121 F.Supp. 664, 128 Ct.Cl. 382; United States v. Lennox Metal Mfg. Co., 2 Cir., 1955, 225 F.2d 302. The law of this State is in accord with this proposition. Crumlish v. Wilmington & Western R. Co., 5 Del.Ch. 270. 6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deakyne v. Department of Army
530 F. Supp. 1322 (D. Delaware, 1982)
Davis v. Howard
404 F. Supp. 678 (N.D. Georgia, 1975)
Collison v. Deisem
265 A.2d 57 (Court of Chancery of Delaware, 1970)
Limestone Realty Co. v. Town & Country Fine Furniture & Carpeting, Inc.
256 A.2d 676 (Court of Chancery of Delaware, 1969)
Wilson Contracting Co. v. State
224 A.2d 396 (Supreme Court of Delaware, 1966)
Wilson Contracting Co. v. State
243 A.2d 65 (Superior Court of Delaware, 1965)
Ruvolo v. American Casualty Co.
189 A.2d 204 (Supreme Court of New Jersey, 1963)
Puerto Rico Housing Authority v. Superior Court
82 P.R. 333 (Supreme Court of Puerto Rico, 1961)
Autoridad Sobre Hogares v. Tribunal Superior de Puerto Rico
82 P.R. Dec. 344 (Supreme Court of Puerto Rico, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
179 F. Supp. 199, 1959 U.S. Dist. LEXIS 2351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anthony-p-miller-inc-v-wilmington-housing-authority-ded-1959.