Wilson Contracting Co. v. State

224 A.2d 396, 1966 Del. LEXIS 150
CourtSupreme Court of Delaware
DecidedNovember 15, 1966
StatusPublished
Cited by8 cases

This text of 224 A.2d 396 (Wilson Contracting Co. v. State) is published on Counsel Stack Legal Research, covering Supreme Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilson Contracting Co. v. State, 224 A.2d 396, 1966 Del. LEXIS 150 (Del. 1966).

Opinion

CAREY, Justice.

The appellant, Wilson Contracting Co., Inc. (Wilson) is a road contractor. In August 1958, it entered into contracts with the State Highway Commission (Department) for the construction of three sections of road in Kent and New Castle Counties. After the completion thereof, it brought this action in Superior Court to recover for loss allegedly caused by Department’s delays in *397 certain respects. 1 Three questions are presented in the briefs. They are: (1) was the claim subject to determination by Department’s Chief Engineer as “referee” under the Clause 27 of the Standard Specifications ; (2) if Clause 27 is applicable, did the Court below err in refusing to decide appellant’s charge of constructive fraud in the Chief Engineer’s determination; (3) does Clause 62 of the Standard Specifications limit appellant’s rights, in case of delay caused by Department, to an extension of time for completion of the work and suspension of liquidated damages for the period of delay.

In making its bids, Wilson relied upon representations of the Department that all rights-of-way had been acquired or would be acquired in such time as not to interfere with orderly prosecution of the work. After contracts had been signed and bonds posted, Wilson was told that certain rights-of-way had not been actually acquired but were expected to be obtained in ample time for Wilson to proceed without interruption. In fact, as matters turned out, there were delays in acquiring certain rights-of-way and rights-of-entry, and in relocating certain utility lines. Further delays were caused by Department’s refusal to permit Wilson to enter upon rights-of-way which had been acquired, by the alterations of plans and specifications and by failure of the plans to show the need for certain “undercutting”. The consequence was, charges Wilson, that it suffered severe losses by being forced to keep its equipment idle, to move its heavy equipment from place to place, to move fill unusual distances and at times to use hand labor for work ordinarily done with machines, all of which could have been avoided had it not been for Department’s defaults. Wilson was allowed extra time to complete the work, without payment of liquidated damages for the time allowed.

Following completion, Wilson wrote letters to the Department’s Division Engineers for the two counties involved presenting the claims here made. The matter was taken up with the Highway Commission which referred it to the Chief Engineer for study and recommendation. He caused an investigation to be made by his staff and by auditors who examined Wilson’s books. After studying their reports, he recommended to the Commission that the claims be disallowed. Conferences took place between Wilson’s representatives and Department’s Committee on Contract Administration. The Chief Engineer was present at all these conferences. Finally, on February 11th, 1963, a letter signed by both the Chief Engineer and the Director of Operations was sent to Wilson containing this paragraph :

“On the basis of their consideration and review of the material, the Department’s Chief Engineer and Director of Operations each concluded that your claims were not meritorious, either from the standpoint of the facts or the relevant contract provisions, and, therefore, that each of the claims should be denied and rejected in its entirety, and they so recommended to the Commissioners of the Department at the meeting of the Commissioners held on January 23, 1963. The Contract Administration Committee and the Department’s General Counsel concurred in such conclusions and recommendations of the Chief Engineer and Director of Operations.”

The Department’s lengthy standard specifications were included by reference in the contracts. Clause 27 thereof reads as follows :

“27. AUTHORITY OF ENGINEER: — The Chief Engineer shall act as referee in all questions arising under the terms of this contract between the parties hereto, and the decision of the *398 Chief Engineer shall be final and binding. On all questions concerning the interpretation of plans and Standard Specifications, the acceptability, quality, and quantity of materials or machinery furnished and work performed, the classification of material, the execution of the work and the determination of payment due or to become due, the decision of the Chief Engineer shall be final and binding.”

In the Court below, following extensive discovery, both parties moved for summary judgment. That Court denied Wilson’s motion, and granted Department’s application, with leave to Wilson to file an amendment to the complaint. The Court held that the claims herein made were subject to the provisions of Clause 27 and that the Chief Engineer’s decision was final in the absence of fraud. Wilson challenges this holding, and contends that its claims are outside the scope of Clause 27, that the Chief Engineer did not in fact make a decision under it, and that, if he did act under it, the facts are such as to show constructive fraud in making his decision.

I

Wilson argues that clauses like the one used here providing for final decision of disputes are construed strictly and limited to the kind of matters clearly set forth therein; that the present dispute does not arise under the contract, but from a breach thereof by Department; and that it is not seeking additional payments under the contract, but consequential damages for its breach. It cites a number of cases to support its views, including Pat J. Murphy Inc. v. Drummond Dolomite, Inc., D.C., 214 F.Supp. 496; M. DeMatteo Constr. Co. v. Maine Turnpike Authority, D.C., 184 F. Supp. 907; Faber v. City of New York, 222 N.Y. 255, 118 N.E. 609; Young v. Crescent Dev. Co., 240 N.Y. 244, 148 N.E. 510. These cases were instances where arbitration clauses were construed not to include the particular type of loss claimed or the kind of alleged wrong which produced that loss. None of them indicates that there is anything inherently wrong legally with a provision naming a referee to resolve disputes between parties, even though the referee be a person employed by one of them; they hold that his power to act extends no further than is granted to him by the terms of the arbitration clause. There are, of course, other cases in which the arbitration clause has been held to cover particular types of. claims or losses. Crumlish v. Wilmington & Western R. Co., 5 Del.Ch. 270; United States v. Moorman, 338 U.S. 457, 70 S.Ct. 288, 94 L.Ed. 256; Anthony P. Miller, Inc. v. Wilmington Housing Authority, D.C., 179 F.Supp. 199; Nelley v. Mayor & City Council of Baltimore, 224 Md. 1, 166 A.2d 234; Kerr v. State of Maine, 127 Me. 142, 142 A. 197; Terminal Constr. Corp. v. Bergen County etc., 34 N.J. Super. 478, 112 A.2d 762. None of the cases cited involves language exactly like that before us. The applicable basic rule is stated in 3A Corbin on Contracts § 652 in these words:

“The issues over which the engineer or architect is given power of decision must be determined by the reasonable interpretation of the contract provision creating such power.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kuhn Construction, Inc. v. Diamond State Port Corp.
990 A.2d 393 (Supreme Court of Delaware, 2010)
Gauntt Construction Co. v. Delaware River & Bay Authority
575 A.2d 13 (New Jersey Superior Court App Division, 1990)
Gauntt Const. v. RIVER & BAY AUTH.
575 A.2d 70 (New Jersey Superior Court App Division, 1989)
Kuhn Construction Company v. State
248 A.2d 612 (Superior Court of Delaware, 1968)
Ruckman & Hansen, Inc. v. Delaware River & Bay Authority
244 A.2d 277 (Supreme Court of Delaware, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
224 A.2d 396, 1966 Del. LEXIS 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilson-contracting-co-v-state-del-1966.