Calumet Const. Corp. v. Metro. Sanitary Dist. of Greater Chicago

581 N.E.2d 206, 222 Ill. App. 3d 374, 163 Ill. Dec. 255, 1991 Ill. App. LEXIS 1707
CourtAppellate Court of Illinois
DecidedSeptember 30, 1991
Docket1-89-1933
StatusPublished
Cited by4 cases

This text of 581 N.E.2d 206 (Calumet Const. Corp. v. Metro. Sanitary Dist. of Greater Chicago) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calumet Const. Corp. v. Metro. Sanitary Dist. of Greater Chicago, 581 N.E.2d 206, 222 Ill. App. 3d 374, 163 Ill. Dec. 255, 1991 Ill. App. LEXIS 1707 (Ill. Ct. App. 1991).

Opinion

PRESIDING JUSTICE MANNING

delivered the opinion of the court:

On September 15, 1983, plaintiff, Calumet Construction Corporation, entered into a contract with defendant, The Metropolitan Sanitary District. In accordance with the contract, plaintiff agreed to construct six sludge digestion tanks, three boilers, a methane gas compressor building and to perform rehabilitation work on 12 existing sludge tanks. Plaintiff agreed to perform these services at a cost to defendant of $22,575,000 and to complete the work within 900 days.

The United States Environmental Protection Agency (hereinafter EPA) funded a major percentage of the expenditures for the project. In accordance with its funding guidelines, the contract contained the standard Federal appendices (appendix B), as well as general condition provisions. The “suspension of work” clause in appendix B provided that an “equitable adjustment” could be made for delay damages except where such an adjustment was provided for or excluded under any other provision of the contract. Article 27 of the general conditions provisions specifically listed what damages were recoverable due to delay by defendant.

Plaintiff did not complete the project within the 900-day period due to problems attributable to defendant. Plaintiff charged that on October 10, 1983, defendant directed it not to proceed on the sludge grinding system and that directions to continue the project were not given until June 28, 1984. Plaintiff further charged that defendant issued a change order without extending the time within which the modification should be completed. Plaintiff asserted that these actions and others by defendant caused delay damages and that it incurred extra work as a direct result of these problems.

Plaintiff filed a complaint against defendant seeking declaratory relief for damages resulting from the delays and interference with its performance. The complaint was filed before the contract was substantially performed and sought “equitable adjustments” in the contract price and performance time totaling $4,300,000.

On January 17, 1989, defendant filed a motion for partial summary judgment. Defendant alleged that plaintiff was precluded from receiving an “equitable adjustment” to the contract under the “suspension of work” clause of the Federal appendix to the contract, and that plaintiff’s delay damages were limited by article 27 of the general conditions provisions.

On January 27, 1989, the trial court granted defendant’s motion for partial summary judgment. The court held that article 27 of the general conditions applied to the suspension of work “equitable adjustment” provision of the contract; therefore, plaintiff’s damages for delay were precluded. The court also held that the exclusionary language of article 27 applied to the provision covering “changes and differing site conditions.” Thereafter, plaintiff filed a motion to reconsider and a motion requesting leave to file an amended complaint. These motions were denied. The parties reached a settlement; however, they reserved the right to appeal the court’s January 27, 1989, ruling. On July 11, 1989, plaintiff filed its appeal.

Plaintiff argues on appeal that the trial court erred in finding that the “no damages for delay” general conditions provisions of the contract barred it from recovering under one of the “equitable adjustment” provisions of the same contract. Defendant does not deny that the delays complained of were attributable to it; however, defendant maintains that any recovery was properly limited by the language of article 27 of the general conditions of the contract and the “suspension of work” clause in the Federal appendix to the contract.

Article 27 of the general conditions of the contract provides in pertinent part:

“Should the contractor be obstructed or delayed in the commencement, prosecution or completion of the work hereunder by any act or delay of the Sanitary District, or by inability, with the exercise of due diligence; to obtain necessary railroad and transportation facilities, *** the times fixed in the Agreement for the completion of said work to the extent specified shall be extended for a period equivalent to the time lost by reason of any of the aforesaid causes mentioned ***.
* * *
The Contractor shall not be entitled to any damages or compensation from the Sanitary District except on account of any delay or delays resulting from any act or delay of the Sanitary District or other parties under contract with the Sanitary District, and such damages shall be limited solely to premiums actually paid by the Contractor on his bond and for wages and salaries of employees and other extra expenses of the Contractor that are necessary only for the proper maintenance of the work and of the plant and equipment of the Contractor during or on account only of a delay or delays caused by the Sanitary District or other contractors for said Sanitary District.”

The “suspension of work” clause provides:

“(b) If the performance of all or any part of the work is suspended, delayed or interrupted for an unreasonable period of time by an act of the recipient in administration of this subagreement, an adjustment shall be made for any increase in the cost of performance of this subagreement (excluding profit) necessarily caused by such unreasonable suspension, delay or interruption and the contract modified in writing. However, no adjustment shall be made under this clause for any suspension, delay or interruption'to the extent ***. *** (2) for which an equitable adjustment is provided for or excluded under any other provision of this subagreement.”

The appendix to the contract defines “subagreement” as:

“A written agreement between an EPA recipient and another party (other than another public agency) and any lower tier agreement for services, supplies, equipment, or construction necessary to completé the project. Subagreement includefs] contracts and subcontracts for personal, and' professional services, agreements with consultants, and purchase orders.”

Plaintiff contends that the clause contained in the suspension of work “equitable adjustment” provision refers solely to the other provisions contained in the appendix, and not to the general conditions of the contract. Plaintiff maintains that there are only three provisions of the contract which refer to “equitable adjustment” and that all three are contained in appendix B. He argues that because article 27 of the general conditions' does not use the term “equitable adjustment,” the “suspension of work” clause cannot be construed to refer to article 27.

It is a well-established principle in the law of contracts that a construction should be adopted which harmonizes all the various parts so that no provision is deemed conflicting with or repugnant to, or neutralizing of any other. (Zannis v. Lake Shore Radiologists, Ltd. (1979), 73 Ill. App. 3d 901, 906, 392 N.E.2d 126

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bielecki v. Painting Plus, Inc.
637 N.E.2d 1054 (Appellate Court of Illinois, 1994)
George S. May International Co. v. King
629 N.E.2d 257 (Indiana Court of Appeals, 1994)
Resolution Trust Corp. v. Holtzman
618 N.E.2d 418 (Appellate Court of Illinois, 1993)
Heider v. Leewards Creative Crafts, Inc.
613 N.E.2d 805 (Appellate Court of Illinois, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
581 N.E.2d 206, 222 Ill. App. 3d 374, 163 Ill. Dec. 255, 1991 Ill. App. LEXIS 1707, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calumet-const-corp-v-metro-sanitary-dist-of-greater-chicago-illappct-1991.