Ruffin Woody & Associates, Inc. v. Person County

374 S.E.2d 165, 92 N.C. App. 129, 1988 N.C. App. LEXIS 1029
CourtCourt of Appeals of North Carolina
DecidedDecember 6, 1988
Docket889SC279
StatusPublished
Cited by15 cases

This text of 374 S.E.2d 165 (Ruffin Woody & Associates, Inc. v. Person County) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ruffin Woody & Associates, Inc. v. Person County, 374 S.E.2d 165, 92 N.C. App. 129, 1988 N.C. App. LEXIS 1029 (N.C. Ct. App. 1988).

Opinion

*132 PARKER, Judge.

Plaintiff first assigns error to the trial court’s denial of its motion to enjoin the arbitration on the grounds that there was no valid agreement to arbitrate. Plaintiff next assigns error to the trial court’s granting of defendant’s motion to confirm the award prior to the expiration of the ninety-day period prescribed in G.S. l-567.13(b). Plaintiffs third and fourth assignments of error are that the trial court erred in denying plaintiffs motion to depose the arbitrators or alternatively to vacate the award on the grounds that the neutral arbitrator failed to disclose prior business dealings with defendant.

Before considering plaintiffs argument in support of its first assignment of error, we must address defendant's contention that plaintiff waived its right to challenge the arbitrability of defendant’s claims by participating in the arbitration. One who participates in an arbitration hearing without objection may not raise an objection after the award is entered. McNeal v. Black, 61 N.C. App. 305, 300 S.E. 2d 575 (1983). In this case, however, plaintiffs objection was filed before the hearing was commenced. Moreover, plaintiff followed the correct procedure by applying for a court order to stay the arbitration proceeding. G.S. 1-567.3. Once the trial court refused to enjoin the arbitration, plaintiff had no choice but to participate in the proceeding. The specific instances in which an appeal may be taken from ah arbitration order are set out in G.S. 1-567.18, and the statute does not permit an appeal to be taken from the denial of an application to stay arbitration.

Defendant contends that plaintiffs limited participation in the arbitration before it filed its amended answer was sufficient to operate as a waiver of its right to object. General Statute 1-567.3(b) provides, however, that, upon a showing that there is no agreement to arbitrate, “the court may stay an arbitration proceeding commenced or threatened.” This provision clearly contemplates that objections to arbitration proceedings may be raised after the institution of the proceedings. Plaintiff in this case raised its objection before the hearing on the merits and before the selection of arbitrators was complete. Therefore, the objection was timely.

Defendant also contends that plaintiff should be bound by the admission in its initial answer that the claims were subject to ar *133 bitration. This argument is without merit. By filing its amended answer, plaintiff raised the issue of arbitrability. Nothing in the record indicates that defendant objected to the filing of the amended answer, and both the AAA and the trial court considered the merits of the issue. Accordingly, we hold that plaintiff has not waived its right to object to arbitration on the grounds that there was no agreement to arbitrate.

Plaintiff contends that defendant’s claims are not arbitrable because the terms of the contract provide that the architect’s decision as to the acceptability of the work is binding and conclusive. The determination of whether a particular claim is arbitrable is controlled by the language of the parties’ agreement. Rodgers Builders v. McQueen, 76 N.C. App. 16, 23-24, 331 S.E. 2d 726, 731 (1985), disc. rev. denied, 315 N.C. 590, 341 S.E. 2d 29 (1986). Plaintiff relies on the following provision of the EDA General Conditions:

35. Architect/Engineer Authority
The Architect/Engineer shall give all orders and directions contemplated under this contract and specifications relative to the execution of the work. The Architect/Engineer shall determine the amount, quality, acceptability, and fitness of the several kinds of work and materials which are to be paid for under this contract and shall decide all questions which may arise in relation to said work and the construction thereof. The Architect/Engineer’s estimates and decisions shall be final and conclusive, except as herein otherwise expressly provided. In case any question shall arise between the parties hereto relative to said contract or specifications, the determination or decision of the Architect/Engineer shall be a condition precedent to the right of the Contractor to receive any money or payment for work under this contract affected in any manner or to any extent by such question.

General Condition 35 clearly designates the architect as the final authority on questions concerning the work performed by the contractor. Our courts have held that such a provision is binding on the parties to a construction contract. Heating Co. v. Board of Education, 268 N.C. 85, 150 S.E. 2d 65 (1966); Elec-Trol, Inc. v. Contractors, Inc., 54 N.C. App. 626, 284 S.E. 2d 119 (1981), disc. rev. denied, 305 N.C. 298, 290 S.E. 2d 701 (1982).

*134 Article 14 of AIA Document A107, however, provides:

All claims or disputes arising out of this Contract or the breach thereof shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. . . .

Article 8 of Document A107 includes the following provision:

8.5 The Architect will be, in the first instance, the interpreter of the requirements of the Contract Documents. He will make decisions on all claims and disputes between the Owner and the Contractor. All his decisions are subject to arbitration.

The additional AIA General Conditions further provide:

2.2.12 Any claim, dispute or other matter in question between the Contractor and the Owner referred to the Architect, except those relating to artistic effect as provided in Subparagraph 2.2.11 and except those which have been waived by the making or acceptance of final payment as provided in Subparagraphs 9.9.4 and 9.9.5, shall be subject to arbitration upon the written demand of either party. . . .

Thus, there is a clear conflict between EDA General Condition 35 which provides that the architect’s decisions are final and conclusive, and the AIA documents, which provide that most decisions of the architect are subject to arbitration.

Plaintiff contends that General Condition 35 is controlling because EDA General Condition 41 states: “Any provision in any of the contract documents which may be in conflict or inconsistent with any of the paragraphs in these General Conditions shall be void to the extent of such conflict or inconsistency.” Plaintiff argues that this condition overrides the AIA provisions for arbitration of the architect’s decisions. Defendant, however, contends that the AIA provisions should be given effect because General Condition 35 states that the architect’s decisions are final and conclusive “except as herein otherwise expressly provided.” Defendant argues that the AIA provisions come within this exception. Plaintiffs counter-argument is that the word “herein” in the exception indicates that the exception was intended only to *135 include other provisions in the EDA general conditions and not other documents incorporated into the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reynolds v. Devotion Fam., LLC
Court of Appeals of North Carolina, 2025
Harper Hofer & Assocs., LLC v. Nw. Direct Mktg., Inc.
412 P.3d 659 (Colorado Court of Appeals, 2014)
ELJ, Inc. v. Jefferys
Court of Appeals of North Carolina, 2014
Paradigm Fin. Grp., Inc. v. Church
2014 NCBC 16 (North Carolina Business Court, 2014)
Walnut Street Securities, Inc. v. Lisk
497 F. Supp. 2d 714 (M.D. North Carolina, 2007)
Wein v. Morris
909 A.2d 1186 (New Jersey Superior Court App Division, 2006)
Miller v. ROCA & Son, Inc.
604 S.E.2d 318 (Court of Appeals of North Carolina, 2004)
Sloan Financial Group, Inc. v. Beckett
583 S.E.2d 325 (Court of Appeals of North Carolina, 2003)
Raspet v. Buck
554 S.E.2d 676 (Court of Appeals of North Carolina, 2001)
HBS Contractors, Inc. v. National Fire Insurance
501 S.E.2d 372 (Court of Appeals of North Carolina, 1998)
William C. Vick Construction Co. v. North Carolina Farm Bureau Federation
472 S.E.2d 346 (Court of Appeals of North Carolina, 1996)
Carteret County v. United Contractors of Kinston, Inc.
462 S.E.2d 816 (Court of Appeals of North Carolina, 1995)
Creative Homes and Millwork, Inc. v. Hinkle
426 S.E.2d 480 (Court of Appeals of North Carolina, 1993)
Calumet Const. Corp. v. Metro. Sanitary Dist. of Greater Chicago
581 N.E.2d 206 (Appellate Court of Illinois, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
374 S.E.2d 165, 92 N.C. App. 129, 1988 N.C. App. LEXIS 1029, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ruffin-woody-associates-inc-v-person-county-ncctapp-1988.