Welborn Plumbing & Heating Co. v. Randolph County Board of Education

150 S.E.2d 65, 268 N.C. 85, 1966 N.C. LEXIS 1131
CourtSupreme Court of North Carolina
DecidedSeptember 21, 1966
Docket604
StatusPublished
Cited by12 cases

This text of 150 S.E.2d 65 (Welborn Plumbing & Heating Co. v. Randolph County Board of Education) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Welborn Plumbing & Heating Co. v. Randolph County Board of Education, 150 S.E.2d 65, 268 N.C. 85, 1966 N.C. LEXIS 1131 (N.C. 1966).

Opinion

Parker, C.J.

Before Judge Riddle the parties stipulated: (1) Defendant, as the governmental agency of Randolph County, North Carolina, charged with the responsibility of constructing and maintaining public schools in said county, has authority to enter into contracts for these purposes. On 12 January 1961 the defendant entered into a contract with plaintiff providing, inter alia, that plaintiff was to install heating facilities in the addition to the Archdale Public School, which was to be constructed according to plans and specifications submitted by defendant through its architects; (2) the work contracted to be performed by plaintiff for defendant in connection with the Archdale Public School is governed by the contract between the parties dated 12 January 1961, the proposal of the same date of plaintiff to defendant for the accomplishment of the work proposed, the contract and the proposal of plaintiff each referring to and incorporating therein “Contract Documents” as prepared by the architect, John James Croft, Jr., and referred to as *88 “General Conditions,” Section 00-G1, consisting of seven pages, and “Heating Work” referred to as Section 38-011, consisting of two pages; (3) defendant deducted the sum of $1,541.58 from the contract price of $9,580, being the amount approved by the architect for payment to the general contractor for the protection and repair of damage; and (4) the wall in question was a foundation bearing wall with earth filling inside the building and backfilling on the outside of the building.

This evidence seems undisputed: The building plans for the addition to Archdale Public School called for the construction of three new walls and the use of one wall of the existing building. The particular wall involved in the instant case was a new foundation wall some 15 feet in height from its base “with earth filling inside the building and backfilling on the outside of the building.” Under the contract plaintiff was to install heating lines adjacent to the outside of this foundation wall along its entire length. To install the heating lines plaintiff had to dig a ditch along the entire length of this foundation wall. At the time plaintiff dug the ditch the general contractor had finished the wall, and had mounted on it the concrete frames which would support the roof of the building; the wall was up and the roof was partially on.

Plaintiff’s evidence, considered in the light most favorable to it, tends to show that it performed its work according to the terms of its contract with defendant, that defendant is indebted to it in the amount sued for, to wit, $1,541.58, which was deducted from the contract price by order of the architect, John James Croft, Jr.

Defendant’s evidence tends to show that for a period of three days prior to plaintiff’s digging the ditch on the outside of the foundation wall there had been constant rainfall, and as a result thereof the ground was extremely wet and muddy, and plaintiff was guilty of negligence in the manner in which it dug the ditch too close to the foundation wall, and guilty of negligence also in digging the ditch under the conditions of wetness and mud, and as a proximate result thereof the foundation wall cracked and bowed out some two or three inches; that the architect, John James Croft, Jr., knew certain work had to be done by the general contractor to correct the damaged condition of the new foundation wall, and that he authorized the payment by defendant of $1,541.58 from the contract price of $9,580 to the general contractor for this work, and defendant deducted this amount from the contract price. The first witness for plaintiff was Clyde B. Welborn, its president. Just before defendant’s counsel, Mr. Miller, began his cross-examination of this witness, the court asked Mr. Miller this question: “Do you admit every *89 thing was alright (sic) about the work except causing this wall to fall, is that right?” Mr. Miller replied: “Yes sir.”

Defendant assigns as error the denial by the court of its motion for judgment of involuntary nonsuit made at the close of all the evidence. It contends as follows: (1) It deducted the sum of $1,541.58 from the contract price of $9,580, being the amount approved by the architect for payment to the general contractor for the protection and repair of damage to the foundation bearing wall, and that the decision of the architect under the contract entered into by and between the parties is final and conclusive, and it is not indebted to plaintiff in any amount; and (2) “the evidence construed in a light most favorable to the plaintiff clearly establishes plaintiff’s negligence in performance of its contract, which negligence constituted a breach of contract precluding recovery on the express contract” and “there is no allegation in the pleadings or evidence in the record which recovery (sic) may be had under any other theory of law.”

The contract entered into by and between the parties here contains the following as to “Status of the Architect”:

“Architect is Owner’s authorized representative. He shall have general supervision of work, and authority to stop work to insure its proper execution.
“The Architect shall give all orders and directions contemplated under this contract and specifications relative to the execution of the work. He shall determine the amount, quality, acceptability, and fitness of the' several kinds of work and materials which are to be paid for under this contract, and shall decide all questions which may arise in relation to said work and the construction thereof. His estimates and decisions shall be final and conclusive.
“The Architect shall decide the meaning and intent of any portion of the specifications and of any plans or drawings where the same may be found obscure or be in dispute.
“Any differences or conflicts in regard to their work which may arise between the Contractor under this contract and other contractors performing work for the Owner shall be adjusted and determined by the Architect.
“The Architect shall certify to Owner when payments to Contractor are due and amounts to be paid. The Architect shall make decisions on all claims.of the Contractor.”
“In building and construction' contracts the parties frequently provide that the completion, sufficiency, classification, or amount of *90 the work done by the contractor shall be determined by a third person, usually an architect or engineer. Such stipulations which, in their origin, were designed to avoid harassing litigation over questions that can be determined honestly only by those possessed of scientific knowledge, have generally been. held valid. This is true even though the architect or engineer is employed by the owner unless unknown to the contractor, he has guaranteed to keep the cost of the work below a certain sum.” 13 Am. Jur., 2d, Building, Etc. Contracts, § 32.

This is said in 13 Am. Jur., 2d, Building, Etc. Contracts, § 34:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

N. State Envtl., Inc. v. Town of Mooresville
Court of Appeals of North Carolina, 2025
Finish Line v. J.F. Pate & Associates Contractors, Inc.
90 So. 3d 749 (Court of Civil Appeals of Alabama, 2012)
MCI Constructors, Inc. v. City of Greensboro
125 F. App'x 471 (Fourth Circuit, 2005)
MCI CONSTRUCTORS, INC. v. Hazen and Sawyer, PC
310 F. Supp. 2d 754 (M.D. North Carolina, 2004)
RPR & Associates v. O'Brien/Atkins Associates, P.A.
24 F. Supp. 2d 515 (M.D. North Carolina, 1998)
Top Line Construction Co. v. J.W. Cook & Sons, Inc.
455 S.E.2d 463 (Court of Appeals of North Carolina, 1995)
Ruffin Woody & Associates, Inc. v. Person County
374 S.E.2d 165 (Court of Appeals of North Carolina, 1988)
Elec-Trol, Inc. v. C. J. Kern Contractors, Inc.
284 S.E.2d 119 (Court of Appeals of North Carolina, 1981)
Burke County Public Schools Board of Education v. Juno Construction Corp.
273 S.E.2d 504 (Court of Appeals of North Carolina, 1981)
BURKE CTY. PUBLIC SCH., ETC. v. Juno Const.
273 S.E.2d 504 (Court of Appeals of North Carolina, 1981)
Grissett v. Ward
179 S.E.2d 867 (Court of Appeals of North Carolina, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
150 S.E.2d 65, 268 N.C. 85, 1966 N.C. LEXIS 1131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/welborn-plumbing-heating-co-v-randolph-county-board-of-education-nc-1966.